Stop-The-Barge, by its President
Kathleen Gilrain, et al.,
Appellants,
v.
John P. Cahill, as Commissioner
of Environmental Conservation,
et al.,
Respondents.
2003 NY Int. 146
In this article 78 proceeding where petitioners seek to set aside action taken by the New York State Department of Environmental Conservation (DEC) and the New York City Department of Environmental Protection (DEP), we must determine which agency action triggers the statute of limitations. Like the Appellate Division, we conclude that on these facts the statute of limitations began to run when the conditioned negative declaration (CND) issued by DEP became final.
In the Fall of 1996, respondent New York City Energy
(NYCE) submitted an Environmental Assessment Statement to DEP in
Simultaneously, when NYCE further modified the proposal
in 1999, NYCE applied to the DEC for an Air Permit pursuant to
the Environmental Conservation Law, article 19. DEC determined
that the impacts of air emissions from the proposed facility
would not contravene the standards imposed by the Environmental
Protection Agency and on August 9, 2000, tentatively approved an
Air Permit for the facility. Following this tentative
determination, DEC issued a public notice stating that it would
On February 20, 2001 -- one year after the CND became final, and two months after the Air Permit was issued -- petitioners commenced this CPLR article 78 proceeding contending that the DEP's issuance of the CND and DEC's issuance of the Air Permit were arbitrary and capricious in violation of SEQRA, Environmental Conversation Law (ECL)3-0301, and article 19 of the ECL. Respondents moved to dismiss the petition as time barred.
DEC claimed the challenge to the Air Permit -- issued on December 18, 2000 -- was time barred under ECL 19-0511(2)(b) because the agency was not served within two months after the Air Permit was issued. DEP argued that the challenge to the CND -- issued on January 10, 2000 -- was time barred under CPLR 217 1) because the action was not brought within four months after the CND was issued. NYCE answered and sought dismissal under both statutes of limitations.
Supreme Court dismissed the action as time barred,
concluding the ECL 19-0511(2)(b) barred petitioners' challenges
because they failed to serve respondents within two months of the
On this appeal, petitioners as well as respondent DEC argue that the four-month period of limitations commenced on December 18, 2000, when DEC issued the Air Permit. Petitioner and DEC claim that the CND was merely a preliminary step in the decisionmaking process and that no sufficient predicate for judicial review existed until a permit or approval was issued for the project. DEP and NYCE argue that the period of limitations began to run when the CND was issued, or at the latest, when the 30-day comment period after issuance of the declaration was complete.
We agree with DEP, NYCE and the Appellate Division that
In Essex County v Zagata, we conclude that an agency action is final when the decisionmaker arrives at a "definitive position on the issue that inflicts an actual, concrete injury" (91 2 447, 453 [1998]). We stated:
"[A] determination will not be deemed final because it stands as the agency's last word on a discrete legal issue that arises during an administrative proceeding. There must additionally be a finding that the injury purportedly inflicted by the agency may not be prevented or significantly ameliorated by further administrative action or by steps available to the complaining party.
* * *
If further agency proceedings might render the disputed issue moot or academic, then the agency position cannot be considered definitive or the injury actual or concrete"
( id. at 453-54 [internal quotes and citations omitted]; see also Gordon v Rush, , 100 NY2d 236, 242-243 [2003]).
Here, the agency reached a definitive position on
February 18, 2000, when the public comment period ended because,
at that point, its SEQRA review ended. DEP conducted no further
SEQRA investigation, and issued no further SEQRA declaration on
the project. Petitioners had an opportunity to comment but
failed to alert the DEP to the concerns it subsequently raised
with regard to the SEQRA review. Thus, to the extent that
petitioners challenge the conclusions reached by DEP from its
Moreover, to allow petitioners to postone their challenge to the CND until the issuance of the Air Permit would be particularly unreasonable here, since the declaration had been final for ten months before the Permit was issued. Given these circumstances, commencing the period of limitations from the finality of the CND is consistent with the policy of resolving environmental issues and determining whether an environmental impact statement will be required at the early stages of project planning ( see e.g. Long Island Pine Barrens Soc. Inc. v. Planning Bd. of the Town Brookhaven, , 78 NY2d 608 [1991]).
Accordingly, the order of the Appellate Division, insofar as appealed from, should be affirmed, with costs.