In the Matter of Citineighbors
Coalition of Historic Carnegie
Hill, &c., et al.,
Appellants,
v.
The New York City Landmarks
Preservation Commission, et al.,
Respondents.
2004 NY Int. 27
MEMORANDUM:
The appeal should be dismissed, with costs, as moot.
On June 10, 2002, the New York City Landmarks
Preservation Commission issued a Certificate of Appropriateness
(COA) approving a proposal for 47 East 91st Street, LLC, the
property owner, and Tamarkin Co., a real estate developer, to
construct an eight-story building with a one-story penthouse atop
an existing one-story building located on the northeast corner of
On July 2, 2002, petitioners commenced this article 78 proceeding to annul the COA. They did not apply for a temporary restraining order or preliminary injunction to halt the highly visible construction work by then underway at the site. Petitioners argued, as relevant on this appeal, that the Commission's issuance of a COA was a discretionary act requiring compliance with the environmental review procedures of the State Environmental Quality Review Act (SEQRA). On January 8, 2003, Supreme Court denied the petition and dismissed the proceeding, concluding that issuance of a COA is a ministerial act exempt from SEQRA. The Appellate Division subsequently affirmed (306 2 113 [1st Dept 2003]), and we granted leave to appeal (100 2 514 [2003]).
"Typically, the doctrine of mootness is invoked where a
change in circumstances prevents a court from rendering a
decision that would effectively determine an actual controversy"
( Matter of Dreikausen v Zoning Bd. of Appeals of the City of Long
This construction project is substantially complete.
By July 31, 2003, after more than a year of construction, the
building's steel and concrete structure, including its supporting
columns and floors, had been erected; the brick facade was 100%
complete; and 90% of the window frames had been installed. The
property owner and developer had already spent roughly $25.7
million. Further, we cannot say that the building's top several
stories may be readily demolished without undue hardship, a
Nor have the property owner and developer engaged in an unseemly race to completion intended to moot petitioners' lawsuit. After obtaining the approvals necessary to commence construction -- a time-consuming endeavor -- the property owner and developer had every business incentive to complete the building as quickly as possible so as to profit from their investment and avoid paying interest on construction loans.
Importantly, petitioners did not try to enjoin
construction during this litigation's pendency, nonfeasance that
they chalk up to "monetary constraints" and the unlikelihood of
success. In short, petitioners simply assumed that Supreme Court
would not grant them injunctive relief or, in the alternative,
would require an undertaking in an amount more than they could or
wanted to give. Under Dreikhausen, however, petitioners were
required, at a minimum, to seek an injunction in the
circumstances presented here. Having pursued a strategy that
foisted all financial risks (other than their own legal fees and
related expenses) onto the property owner and the developer,
Finally, the exception to the mootness doctrine does not apply because "[t]here is a realistic likelihood that the issues presented here will recur with an adequately developed record and with a timely opportunity for review" ( Matter of Gold- Greenberger v Human Resources Admin. of the City of New York, , 77 NY2d 973, 974-975 [1991]). Specifically, those objecting to a COA on SEQRA grounds may safeguard their challenge against mootness by promptly requesting injunctive relief.