1 No. 62
Bates Advertising USA, Inc.,
Respondent, v. 498 Seventh, LLC,
Appellant.
2006 NY Int. 66
May 11, 2006
This opinion is uncorrected and subject to revision before
publication in the New York Reports.
Edward L. Sadowsky, for appellant. John F. Triggs, for respondent.
READ, J.:
In November 1997, plaintiff Bates Advertising, LLC,
Inc., a large advertising and marketing firm, entered into a
lease with defendant 498 Seventh, LLC so that Bates might
relocate its 700-person worldwide headquarters from the Chrysler
Building into space in 498's building in New York City's Garment
District. Both plaintiff-tenant and defendant-landlord,
sophisticated business entities, were represented by experienced
real estate counsel throughout lengthy negotiations that produced
an 85-page lease with 23 exhibits. Bates was to become the
building's anchor tenant and occupy approximately 25% of its
floor space. The base rent for the 16-year lease, with options
and other rent escalations, exceeds $100 million. Exhibit C to the lease, captioned "Landlord's Work,"
lists numerous upgrades and improvements that 498 agreed to make
to the building in order to provide Bates with the amenities,
safety and security that it had bargained for. Part E of Exhibit
C lists 11 required alterations, including providing a Class E
fire alarm and communications system, installing a card key
system for after-hours access to the building, and upgrading an
existing freight elevator to passenger-elevator quality. "[I]n
an attempt to have the tenancy begin as early as possible while
ensuring that [498] would be sufficiently motivated to follow
through with these items [in part E of Exhibit C] after [Bates]
took possession," the parties followed the common practice
"adopted by the real estate profession generally" and included a
rent abatement clause in the lease (291 2 179, 181 [1st Dept
2002]). Under the terms of this provision, if 498 had not
substantially completed the described work by January 1, 1999,
and Bates had already moved in and was conducting its ordinary
business, then Bates was entitled to abatement of one-half day's
rent for each day's delay in substantially completing one or more
of nine of the 11 items; and abatement of a full day's rent for
each day's delay in substantially completing either or both of
the two most important of the 11 items, one of which was
provision of a Class E fire alarm and communications system. Bates's lease in the Chrysler Building expired on March
31, 1999, without any renewal options, and so Bates moved into
498's building on March 22, 1999. After an initial and
undisputed rent-free period, Bates commenced paying rent as of
June 13, 1999, subject to reservation of its rights under the
lease's rent abatement clause. Alleging that work required by
the lease remained unfinished, Bates commenced this action
against 498 in December 1999, seeking refund of rent and other
relief. Bates contended that it had not received the benefit of
its bargain under the lease, forcing it to occupy space that was
less valuable than the top-shelf commercial accommodations
envisaged by the parties when they fixed the rent, and posing a
threat to its employees' safety and security, its global
operations and worldwide computer systems, and its image in the
international advertising and marketing industry. Supreme Court dismissed Bates's causes of action
grounded on the rent abatement clause, concluding that this
provision was an unenforceable penalty. The Appellate Division
reversed on the law, reinstated these causes of action, and
remanded the matter for further proceedings. The Appellate
Division noted that the situation that the rent abatement clause
sought to address was "not unique to these parties" (291 2 at
181). Namely, the contracted-for alterations "were a vital part
of the deal," but "as a practical matter, it would be difficult
for [Bates] to prove the value of its damages arising from a
breach of this lease term" because, for example,
"there would be no way of knowing whether a loss of a
client, or an employee, had been caused by conditions
in the building. Therefore, although [Bates] was
willing to begin its tenancy before all agreed-upon
alterations had been completed, and [498] was no less
interested in the tenancy beginning, it was necessary
for the parties to acknowledge and somehow provide for
the possibility of delays attendant to these additional
alterations"
( id.). The Appellate Division further observed that "[b]y
imposing [a] one-to-one proportionality between the days the
breach continued and the value of the compensation, the parties
successfully avoided the possibility that the tenant would obtain
a benefit in gross disproportion to the injury it suffered" ( id.
at 183). Nor was "vast disproportion created by the fact that
the full-day abatement would be applicable whether one or both of
two possible improvements remained uncompleted," or by the
parties' designation of a "group of work items, any or all of
which would trigger the maximum of a half-day rent abatement for
each day of delay" ( id.). These "minor" disproportions were "as
likely to inure to the benefit of the landlord as to that of the
tenant" ( id. at 184).
After a bench trial, Supreme Court concluded that 498
breached the lease by failing to provide the required Class E
fire alarm and communications system until May 9, 2000, or 412
days after March 23, 1999, the day after Bates moved into the
building. There was no dispute that Bates's rent payments for
the 412-day period following June 13, 1999, when Bates commenced
paying rent, totaled $4,339,528.61. Thus, Supreme Court awarded
Bates rent abatement credits in this amount against which to
offset future rent payments.[1]
The Appellate Division affirmed
"for the reasons stated" by Supreme Court (19 AD3d 290 [1st Dept
2005]). We granted permission to appeal, and now also affirm. Although 498 protests that it did not breach the lease,
Supreme Court concluded otherwise and the Appellate Division
affirmed. We may not revisit Supreme Court's affirmed factual
findings underpinning the determination of breach, which are
supported by the record ( see Karger, Powers of the New York Court
of Appeals § 13:10 at 489 [rev 3d ed] ["[F]indings of fact made
by the nisi prius court which have been expressly affirmed by the
Appellate Division and have the requisite evidentiary support are
. . . conclusive and binding on the Court"]). Moreover, in light
of these factual findings, 498 materially breached the lease.
Thus, the only remaining issue for us to resolve -- and the main
point of contention between the parties -- is whether the rent
abatement clause is a proper remedy for this breach. Whether a contractual provision "represents an
enforceable liquidation of damages or an unenforceable penalty is
a question of law, giving due consideration to the nature of the
contract and the circumstances" ( JMD Holding Corp. v Congress
Fin. Corp., 4 NY3d 373, 379 [2005]). The party challenging the
liquidated damages -- in this case, 498 -- "must demonstrate
either that damages flowing from [the failure to complete on time
the items of work called for by the lease] were readily
ascertainable at the time [Bates and 498] entered into their
[lease], or that [the rent abatement] is conspicuously
disproportionate to these foreseeable losses" ( id. at 380). 498 has not attempted to show that damages attributable
to its failure to complete the contracted-for work by the
promised date were readily ascertainable at the time the parties
entered into the lease. Instead, 498 argues that the rent
abatement clause is illegitimate and unenforceable because
Bates's attorney testified that the clause was intended to
"incentivize" the landlord, and to provide "a club over his head
to make sure he gets the work done." But the prospect of damages
in the event of breach may always be said to encourage parties to
comply with their contractual obligations. Liquidated damages
are not transformed into a penalty merely because they operate in
this way as well, so long as they are not grossly out of scale
with foreseeable losses. In this case, we agree with the
Appellate Division that 498 has not demonstrated that the rent
abatements are conspicuously disproportionate to Bates's
foreseeable losses. Rent abatement was keyed to the number of
days of 498's non-performance, and varied from a half-day to a
day depending upon the importance of the item of work not
completed. Accordingly, the order of the Appellate Division should
be affirmed, with costs.
Footnotes
1 Supreme Court also determined that 498 breached the lease
by providing the lobby card access system 314 days late, and the
private passenger elevator service 23 days late. Because the
rent abatements under the lease's liquidated damages clause run
concurrently, the resulting half-day credits for these breaches
were subsumed within the $4 million credit.