3 No. 99
In the Matter of John L. Eadie,
et al.,
Appellants, v. Town Board of the Town of North
Greenbush, et al.,
Respondents.
2006 NY Int. 100
July 5, 2006
This opinion is uncorrected and subject to revision before
publication in the New York Reports.
Marc S. Gerstman, for appellants. Joshua Sabo, for respondent Town Board. Mary Elizabeth Slevin, for Gallogly respondents. Linda A. Mandel Clemente, for respondent Planning
Board.
R. S. SMITH, J.:
The Town of North Greenbush has rezoned a large area of
land to permit retail development. Petitioners seek to annul the
rezoning. The case raises these three issues:
1. Did the rezoning require a three-fourths majority
vote of the Town Board under Town Law § 265 (1)? We hold that it
did not, because the petition that sought to require a super-
majority vote was not signed, as section 265 (1) requires, by the
owners of 20% of the land within 100 feet of the land included in
the rezoning. The 100 feet must be measured from the boundary of
the rezoned area, not from the boundary line of the property in
which the rezoned area is located. 2. Was petitioners' challenge to the rezoning under
the State Environmental Quality Review Act (SEQRA) timely
brought? We hold that it was, because in this case the statute
of limitations ran from the adoption of the rezoning, not from
the earlier completion of the SEQRA process. 3. Did the Town comply with SEQRA? We hold that it
did.
Facts and Procedural History
In September 2003, the Town released a Draft Generic
Environmental Impact Statement (DGEIS), prepared pursuant to
SEQRA to address a proposed area-wide rezoning of many parcels of
land located near the intersection of Routes 4 and 43. The
rezoning had been requested by landowners, including John and
Thomas Gallogly, who wanted to build retail stores on their
property. Retail development was not permitted by the then-
existing zoning. The DGEIS is a document of more than 200 pages with
lengthy appendices. One section of the document discusses
traffic; that section says that an "access management plan" will
be needed, but describes only in general terms what the plan will
contain. "Access management," as we understand it from the
parties' presentations, involves planning for the entry and exit
of traffic on major roads in such a way as to keep interference
with traffic flow to a minimum. After public hearings and written comments, the Town
adopted a final Generic Environmental Impact Statement (GEIS) on
March 25, 2004. Responding to comments urging the development of
an access management plan, the Town included such a plan in the
final GEIS, proposing to construct several access roads and other
improvements, and describing proposed allocations of costs and
sources of funding for this construction. The final GEIS did not
specify the timing of the proposed improvements. After another comment period, the Town took the last
step in the SEQRA process by adopting a Findings Statement on
April 28, 2004. The Findings Statement approved a project that
included the rezoning of a number of parcels. It described
proposed "mitigation measures," including those contained in its
access management plan, but said that "[t]he timing of the
improvements is beyond the scope of this GEIS," noting that "the
Town cannot logistically or accurately determine at this time
which parcels will be developed and when."
On May 4, 2004, the Town Board held a public hearing on
the proposed zoning change at which petitioners, opponents of the
change, presented a protest petition pursuant to Town Law § 265
(1). The petition, if effective, would have required a three-
quarters vote of the Town Board to approve the rezoning.
Petitioners claim the protest was effective, because it was
signed by owners of more than 20% of the land located within 100
feet of the parcels affected by the rezoning, as shown by the
Town's tax map. However, not all the land contained in the tax
map parcels was affected by the rezoning; some of the land owned
by the Galloglys was not rezoned. A "buffer zone" between 200
and 400 feet wide was left between the rezoned portion of the
Galloglys' property and the property line. Measuring from the
boundary of the rezoned area, the Town determined that
petitioners did not own 20% of the land within 100 feet, and that
their protest petition was therefore invalid. On May 13, 2004,
the Town Board passed the rezoning by a vote of three to two. On September 10, 2004 -- more than four months after
the SEQRA process was completed, but less than four months after
the rezoning was enacted -- petitioners began this proceeding
under CPLR article 78 against the Town Board, the Planning Board
of the Town and the Galloglys. The petition contained five
causes of action, one alleging that the rezoning was not lawfully
enacted because it required a super-majority vote and four under
SEQRA, two of which have now been abandoned. The remaining SEQRA
claims were related to the access management plan in the GEIS.
Petitioners asserted that the Town's proposed mitigation efforts
were "vague and discretionary" and therefore inadequate and that
its "proposed changes to the transportation infrastructure"
required preparation of a supplemental GEIS. Supreme Court denied motions to dismiss the proceedings
on statute of limitations and necessary-party grounds, and
granted petitioners a preliminary injunction. In a later order,
Supreme Court granted the article 78 petition and annulled the
rezoning on the basis of petitioners' Town Law § 265 (1) claim.
The Appellate Division reversed and dismissed the petition,
holding that the protest petition was insufficient under Town Law § 265 (1) (b); that petitioners' SEQRA claims were barred by the
statute of limitations; and that the SEQRA claims in any event
lacked merit. We now affirm the Appellate Division's order,
although we disagree with its statute of limitations holding, the
first of its two alternative grounds for dismissing the SEQRA
claims.
Discussion
I
Under Town Law § 265 (1), zoning regulations may be
amended "by a simple majority vote of the Town Board, except that
any such amendment shall require the approval of at least three-
fourths of the members of the Town Board" in certain
circumstances. Petitioners here rely on Town Law § 265 (1) (b),
which requires a super-majority vote where the zoning change is
the subject of a written protest presented to the Town Board and
signed by:
"the owners of twenty percent or more of the
area of land immediately adjacent to that
land included in such proposed change,
extending one hundred feet therefrom."
We conclude, as did the Appellate Division, that the
"one hundred feet" must be measured from the boundary of the
rezoned area, not the parcel of which the rezoned area is a part.
The language of the statute, on its face, points to that result:
"land included in such proposed change" can hardly be read to
refer to land to which the proposed zoning change is
inapplicable. Fairness and predictability point in the same
direction. The interpretation we adopt is fair, because it makes
the power to require a super-majority vote dependent on the
distance of one's property from land that will actually be
affected by the change. Petitioners complain that this allows
landowners who obtain rezoning to insulate themselves against
protest petitions by "buffer zoning" -- i.e., leaving the zoning
of a strip of property unchanged, as occurred with the Galloglys'
property here. But we see nothing wrong with this. The whole
point of the "one hundred feet" requirement is that, where a
buffer of that distance or more exists, neighbors beyond the
buffer zone are not entitled to force a super-majority vote. If
we adopted petitioners' interpretation, such a vote could be
compelled by property owners within 100 feet of the boundary of
even a very large parcel -- though these owners might be far away
from any land that would be rezoned.
The interpretation we adopt also makes the operation of
the statute more predictable. We see no reason why the right to
compel a super-majority vote should change when the boundaries
between parcels change -- i.e., when parcels are merged or sub-
divided. Indeed, in this case, petitioners accuse the Galloglys
of deeding property to themselves in order to create two parcels
and invalidate the protest petition. Whether that was their
original intention or not, the Galloglys now argue, and we agree,
that such a reconfiguration of property lines, whether done in
good faith or bad faith, should have no impact on the Town Law §
265 (1) (b) issue. Measurement from the boundary of the rezoned area --
so-called "buffer zoning" -- has been upheld in a New York
Supreme Court case ( Ryan Homes, Inc. v Town Bd. of Town of
Mendon, 7 Misc3d 709, 712-714 [Sup Ct, Monroe County 2005]) and
in several decisions in other states: Pfaff v City of Lakewood,
712 P2d 1041, 1043 (Colo App 1985); Midway Protective League v
City of Dallas, 552 SW2d 170, 174 (Tex Ct Civ App 1977); St.
Bede's Episcopal Church v City of Santa Fe, 85 NM 109, 110, 509
P2d 876, 877 (1973); Rodgers v Village of Menomonee Falls, 55
Wis2d 563, 569-570, 201 NW2d 29, 33 (1972); Heaton v City of
Charlotte, 277 NC 506, 525-528, 178 SE2d 352, 364-366 (1971). Petitioners rely on Herrington v County of Peoria (11
Ill 3 7, 295 NE2d 729 [1973]), but that case is
distinguishable; it did not involve a statute that required
measurement of a distance from the land included in the proposed
zoning change. The statute in Herrington provided for a protest
petition by "the owners of twenty percent of the frontage
directly opposite the frontage proposed to be altered" (11 Ill
App3d at 9 295 NE2d at 730; cf.Town Law § 265 [1] [c]). The
holding of Herrington is that the purpose of such a statute
cannot be avoided by refraining from rezoning a few feet or
inches next to the frontage of the rezoned parcel. The
Herrington court distinguished Heaton, the North Carolina case we
cited above, saying that the statute in Heaton (which resembles
Town Law § 265 [1] [b]) "appears to have been considered by the
court as a legislative declaration, that 'one hundred feet' was a
legally sanctioned buffer or barrier insulating the property from
the claims of protesters" (11 Ill App3d at 13 295 NE2d at 733).
We think that the Illinois court correctly characterized the
North Carolina's court's interpretation of its statute, and we
interpret our statute in the same way.
II
An article 78 proceeding brought to review a
determination by a body or officer "must be commenced within four
months after the determination to be reviewed becomes final and
binding upon the petitioner" (CPLR 217 [1]). We have held that
this time period begins to run when the petitioner has "suffered
a concrete injury not amenable to further administrative review
and corrective action" ( Matter of City of New York [ Grand
Lafayette Props. LLC], 6 NY3d 540, 548 [2006]; see also Matter of
Best Payphones, Inc. v Dept. of Info. Tech. & Telecom. of City of
NY, 5 NY3d 30, 34 [2005]). The issue to be decided here is
whether petitioners suffered "concrete injury" from the alleged
SEQRA violations on April 28, 2004, when the SEQRA process
culminated in the issuing of a Findings Statement, as the
Appellate Division held; or on May 13, 2004, when the Town Board
enacted the rezoning, as Supreme Court held. We conclude that no
concrete injury was inflicted until the rezoning was enacted, and
that therefore petitioners' SEQRA claims were timely brought. In Matter of Save the Pine Bush, Inc. v City of Albany
(70 2 193, 200 [1987]), we held "that a proceeding alleging
SEQRA violations in the enactment of legislation must be
commenced within four months of the date of enactment of the
ordinance." The Town Planning Board argues that Save the Pine
Bush is "no longer good law," and that under Stop-The-Barge v
Cahill (1 3 218 [2003]) the statute runs from the end of the
SEQRA process. Stop-The-Barge, however, is distinguishable. In that case, the petitioners challenged a conditioned
negative declaration (CND) issued under SEQRA by the Department
of Environmental Protection (DEP), determining that a project for
the installation of a power generator on a barge would have no
significant adverse impact on the environment. After DEP's
issuance of the CND completed the SEQRA process, the proponent of
the project obtained an air permit from another agency. We held
that a challenge to DEP's determination of no adverse impact must
be brought within four months of the CND, not the later issuance
of the air permit.
Stop-The-Barge does not control this case because it
did not involve "the enactment of legislation," as Save the Pine
Bush did and this case does; and also because in Stop-The-Barge
the completion of the SEQRA process was the last action taken by
the agency whose determination petitioners challenged. Any
injury to the petitioner that DEP inflicted was concrete when the
CND was issued. It did not depend on the future passage of
legislation, and it was not subject to review or corrective
action by DEP. Here, petitioners suffered no concrete injury until the
Town Board approved the rezoning. Until that happened, their
injury was only contingent; they would have suffered no injury at
all if they had succeeded in defeating the rezoning through a
valid protest petition, or by persuading one more member of the
Town Board to vote their way. We thus reaffirm the holding of Save the Pine Bush, and
make clear that an article 78 proceeding brought to annul a
zoning change may be commenced within four months of the time the
change is adopted. This does not mean that, in every case where
a SEQRA process precedes a rezoning, the statute of limitations
runs from the latter event, for in some cases it may be the SEQRA
process, not the rezoning, that inflicts the injury of which the
petitioner complains. This might be a different case if, for
example, the Galloglys or others were contending that mitigation
measures required by the final GEIS and adopted in the Findings
Statement unlawfully burdened their right to develop their
property. In that hypothetical case, the injury complained of
would not be a consequence of the rezoning, but of the SEQRA
process, and it would make little sense either to require or to
permit the person injured to await the enactment of zoning
changes before bringing a proceeding. But that is not the case
before us: these petitioners are complaining about the zoning
change. We thus agree with Supreme Court on the statute of
limitations issue. We also agree with Supreme Court on an issue
the Appellate Division did not reach: the necessary-parties
defense asserted by the Town and the Galloglys is without merit.
We must therefore address the substance of petitioners' surviving
SEQRA claims.
III
Petitioners complain of two alleged SEQRA violations.
First, they argue that the Town has not adequately mitigated the
adverse effects on traffic, identified in the DGEIS and the final
GEIS, that will result from the rezoning. While the final GEIS
describes the improvements that the access management plan will
entail, petitioners say the Town has "failed to enact the
mechanism" -- meaning, apparently, that the Town has not
committed itself to undertake specific mitigating measures on a
firm schedule. Secondly, petitioners argue that the access
management plan so changes the proposed action in question that a
Supplemental Environmental Impact Statement (SEIS) should have
been prepared before the rezoning was adopted. In both of these
contentions, the petitioners essentially ask us to substitute our
judgment for that of the Town's governing body. This we may not
do. Where an agency has followed the procedures required by
SEQRA, a court's review of the substance of the agency's
determination is limited. The question is "whether the agency
identified the relevant areas of environmental concern, took a
'hard look' at them, and made a 'reasoned elaboration' of the
basis for its determination" ( Matter of Jackson v New York State
Urban Dev. Corp., , 67 NY2d 400, 417 [1986]). The agency's
"substantive obligations under SEQRA must be viewed in light of a
rule of reason" and agencies have "considerable latitude in
evaluating environmental effects and choosing among alternatives"
( id.). Also, "[t]he degree of detail with which each alternative
must be discussed will . . . vary with the circumstances and
nature of the proposal" ( Webster Assocs. v Town of Webster, , 59 NY2d 220, 228 [1983]). Here, the DGEIS, the final GEIS and the
Findings Statement show that the Town took a "hard look" at the
traffic problems that could be anticipated from its proposed
rezoning. The Town's explanations of its proposed courses of
action are well within a rule of reason. Specifically, there is
nothing unreasonable about the Town's comment, in its Findings
Statement, that a more precise plan for traffic mitigation was
impractical until the Town could know "which parcels will be
developed and when."
The document in question here is a generic
environmental impact statement. Department of Environmental
Conservation regulations permit a GEIS to be used to assess the
environmental impacts of "an entire program or plan having wide
application or restricting the range of future alternative
policies or projects, including new or significant changes to . .
. zoning regulations . . . ." (6 NYCRR § 617.10 [a] [4]). The
regulations provide that "[g]eneric EISs may be broader, and more
general than site or project specific EISs" (6 NYCRR § 617.10
[a]). There is no merit to petitioners' contention that the Town
violated SEQRA by failing, as part of approval of an "entire
project or plan," to commit with greater specificity to some
details of access management. Nor was the Town required under SEQRA to prepare an
SEIS before adopting the rezoning. DEC regulations state that,
where a GEIS is used, an SEIS must be prepared in connection with
a "subsequent proposed action" that was "not addressed or was not
adequately addressed" in the GEIS (6 NYCRR § 617.10 [d] [4]).
But the regulations do not say or imply that every possible
subsequent action must be analyzed in an SEIS before a "program
or plan having wide application" is adopted. It was for the Town
to decide, subject to a rule of reason, how detailed an analysis
to perform, before rezoning was enacted, of all projects that
might result from it. The Town's decision that the analysis in
its final GEIS was adequate was not arbitrary and capricious.
IV
Accordingly, the order of the Appellate Division should
be affirmed, with costs.