Ala. Admin. Code r. 335-11-2-.11 - Application Procedures
(1)
Pre-Applications for DWSRF assistance may be submitted at any time during the
year. Projects subject to subsidy must submit applications on or before the
date established by the Department.
(2) Full applications for DWSRF assistance
shall be submitted by the deadline established each year by the Department or
by the date agreed upon by the Department and the applicant. The application
shall include full and complete documentation and any supplementary materials
that the Department may require.
(3) Submissions that do not substantially
comply with this chapter shall not be processed, and shall be returned to the
applicant.
(4) The following shall
be submitted when applying for DWSRF assistance:
(a) A complete application form, with
supporting documents;
(b) A
resolution passed by the public body authorizing the filing of an application
for assistance, specifying the individual authorized to sign. the application
on behalf of the applicant. If two or more public bodies are involved in the
project, a resolution is required from each, indicating the lead applicant and
the authorized representative;
(c)
Statement of assurances as provided by the Department;
(d) Plans and specifications for the
project;
(e) Project cost
breakdown;
(f) Projected cash flow
schedule;
(g) Construction
schedule;
(h) Site certificate from
the applicant's legal counsel and the authorized representative as to title or
mechanism to obtain title necessary for project sites and easements;
(i) Certification that the applicant has
received any required permits from the Department for operation of the
project;
(j) A statement from the
applicant indicating that it has not violated any federal, state, or local law
pertaining to fraud, bribery, graft, kickback, collusion, or conflicts of
interest relating to or in connection with the planning, design, and
construction of the project;
(k) An
environmental information document in such format as the Department may
require;
(l) A statement from the
applicant which indicates if it used the services of a person for planning or
design of the project whose name appears on the Federal list of debarments,
suspensions and voluntary exclusions;
(m) Executed intermunicipal agreements, if
required;
(n) Draft engineering
agreements for construction services which specify engineering and inspection
costs to be funded by DWSRF Funds;
(o) A description of how the applicant plans
to repay the fund loan with supporting documentation as required by the
Department; and,
(p) Any other
information the Department may require to ensure the eligibility of the project
and to evaluate the financial, technical, and managerial capacity of the
applicant.
(5)
Applicants shall obtain all necessary federal, state and local permits and
approvals prior to the award of an assistance agreement. Excluded from prior
acquisition are permits and approvals that are impractical to obtain prior to
execution of the assistance agreement (e.g., construction permit, road opening
permit, blasting permit, etc.).
Notes
Authors: Aubrey H. White III, Kris Berry