Ala. Admin. Code r. 335-6-12-.05 - General Provisions
(1) The
operator , registrant, developer, onsite contractors, home builder(s), utility
installers, or property owners association, separately or collectively, shall
maintain valid registration for an NPDES construction site/activity, including
subdivision developments or other linear or phased projects, until disturbance
activity is complete and all disturbed areas have been reclaimed or effective
stormwater quality remediation has been achieved in accordance with the
requirements of this Chapter or another operator(s) has registered.
(2) The operator of construction activity
defined or designated as NPDES construction under this Chapter shall maintain
adequate records to document compliance with this Chapter and shall fully
implement and regularly maintain effective BMPs to the maximum extent
practicable, and in accordance with the operator's CBMPP. Appropriate,
effective pollution abatement/prevention facilities, structural and
nonstructural BMPs, and management strategies shall be fully implemented prior
to and concurrent with commencement of regulated activities and regularly
maintained during construction as needed at the site to meet or exceed the
requirements of this Chapter until construction is complete, effective
reclamation and/or stormwater quality remediation is achieved, and if
registration is required, the registration is terminated. Failure to fully
implement and regularly maintain effective BMPs for the protection of water
quality to the maximum extent practicable is a violation of this
Chapter.
(3) Operators shall ensure
that their construction activities are regularly evaluated to ensure compliance
with the provisions of this Chapter. All NPDES construction site operators
shall ensure that their construction activities are regularly inspected by a
QCI, QCP, or a qualified person under the direct supervision of a QCP, as
applicable, to ensure compliance with the provisions of this Chapter. Each
NPDES construction site operator shall implement and maintain a comprehensive
CBMPP in accordance with the requirements of this Chapter and submit reports
and certifications as required by this Chapter.
(4) The NOR and CBMPP, prepared in accordance
with the Alabama Handbook and the requirements of this Chapter by the QCP prior
to commencing construction at a new NPDES construction site, and prior to
continued construction at an existing NPDES construction site, or as otherwise
required by the Director , are incorporated into the requirements of any NPDES
registration under this Chapter.
(5) The operator shall post and maintain
sign(s) at the front gate/entrance, and if utility installation, where project
crosses paved county, State, or federal highways/roads, and/or at other easily
accessible location(s) to adequately identify the site prior to commencement of
and during NPDES construction until registration is properly terminated. Such
sign shall display the name of the registrant, "ADEM Registration" followed by
the ADEM NPDES registration number, and facility or site name.
(6) The operator retains full responsibility
for the design, construction , operation and maintenance of BMPs to protect
water quality to the maximum extent practicable. In recognition that
construction activities and noncoal mining activities are site specific in
nature and conditions can change as the site develops, the Department may
require the submission of additional information or require additional
management measures to be implemented, as necessary.
(7) The Director may require the operator to
modify existing registrations, require any CBMPP to be updated, require
additional BMPs, and/or restrict discharges, if needed, based on implementation
of an applicable, approved total maximum daily load.
Author: Richard Hulcher
Notes
Statutory Authority: Code of Ala. 1975, §§ 22-22-1 to 22-22-14; 22-22A-1 to 22-22A-16 et seq., as amended.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.