11 AAC 83.343 - Unit plan of development
(a) A unit plan of
development must be filed for approval as an exhibit to the unit agreement if a
participating area is proposed for the unit area under
11 AAC 83.351, or when a reservoir
has become sufficiently delineated so that a prudent operator would initiate
development activities in that reservoir. All development operations must be
conducted under an approved plan of development. A unit plan of development
must contain sufficient information for the commissioner to determine whether
the plan is consistent with the provisions of
11 AAC 83.303. The plan must
include a description of the proposed development activities based on data
reasonably available at the time the plan is submitted for approval as well as
plans for the exploration or delineation of any land in the unit not included
in a participating area. The plan must include, to the extent available
information exists
(1) long-range proposed
development activities for the unit, including plans to delineate all
underlying oil or gas reservoirs, bring the reservoirs into production, and
maintain and enhance production once established;
(2) plans for the exploration or delineation
of any land in the unit not included in a participating area;
(3) details of the proposed operations for at
least one year following submission of the plan; and
(4) the surface location of proposed
facilities, drill pads, roads, docks, causeways, material sites, base camps,
waste disposal sites, water supplies, airstrips, and any other operation or
facility necessary for unit operations.
(b) The commissioner will approve the unit
plan of development if it complies with the provisions of
11 AAC 83.303. If the proposed
unit plan of development is disapproved, the commissioner will, in his
discretion, propose modifications which, if accepted by the unit operator,
would qualify the plan for approval.
(c) The unit plan of development must be
updated and submitted to the commissioner for approval at least 90 days before
the expiration date of the previously approved plan, as set out in that plan.
The update must describe the extent to which the requirements of the previously
approved plan were achieved; if actual operations deviated from or did not
comply with the previously approved plan, an explanation of the deviation or
noncompliance must be included in the update. The commissioner will approve the
updated unit plan of development if it complies with the provisions of
11 AAC 83.303. If the proposed
update of a unit plan of development is disapproved, the commissioner will, in
his discretion, propose modifications which, if accepted by the unit operator,
would qualify the plan for approval. Within 10 days after receipt of an updated
unit plan of development, the commissioner will inform the unit operator as to
whether the proposed unit plan of development is complete. After the
commissioner has determined that an updated unit plan of development is
complete as submitted, or as modified by the unit operator following the
commissioner's suggestions, the commissioner will have an additional 60 days in
which to approve or disapprove the plan; if no action is taken by the
commissioner, the update of the unit plan of development is approved.
(d) The unit operator shall submit an annual
report to the commissioner describing the operations conducted under the unit
plan of development during the preceding year.
(e) The unit operator may, with the approval
of the commissioner, amend an approved plan of development.
Notes
Authority:AS 38.05.020
AS 38.05.145
AS 38.05.180