17 AAC 35.020 - Industrial use highway permits
(a) A vehicle whose
length exceeds the limitations of 17 AAC 25 but whose length is not more than
90 feet, including load, or whose weight exceeds the gross vehicle weight
limitations of
17 AAC 25.060 but whose gross
vehicle weight is not more than 200,000 pounds, will, in the department's
discretion, be issued an industrial use highway permit to operate on an
industrial use highway if the length and weight do not exceed those specified
by the department for the industrial use highway.
(b) Subject to (c) of this section, an
overweight or oversize permit referred to in
17 AAC 25.010, and issued under 3
AAC 35, is not required for a vehicle for which an industrial use highway
permit has been issued under
17 AAC 35.030.
(c) A vehicle whose gross vehicle weight or
whose length exceeds the weight or length limits specified for a particular
industrial use highway may not operate on that industrial use highway unless it
has a valid overweight or oversize permit issued under 3 AAC 35 and the permit
fee, as calculated under
17 AAC 35.050, has been
paid.
(d) A vehicle used on an
industrial use highway which has neither an industrial use highway permit nor
an overweight or oversize permit issued under 3 AAC 35, is subject to the
weight and size limitations of
17 AAC
25.010(a).
(e) Application for an industrial use highway
permit for a single trip must be made at least 24 hours before the applicant
intends to move the vehicle on the highway. Application for an industrial use
highway permit allowing multiple movements must be made at least 14 days before
the applicant intends to commence operations. A permit will not be issued until
the department has reviewed the permit application. In reviewing the permit
application, the department will, in its discretion, conduct extensive analyses
and will, in its discretion, solicit public comment.
(f) A permit application form may be obtained
at the department office designated for the specific industrial use highway,
and a completed application must be submitted to the department. However, if
the commissioner has delegated authority to issue industrial use highway
permits to another state agency under
17 AAC 35.030(f),
a permit application form may also be obtained from that state agency and the
completed application must be submitted to that state agency as described in
(e) of this section rather than to the department.
Notes
See the editor's note following 17 AAC 35.030 regarding the designation of another state agency for industrial use highway permit issuance.
Authority:AS 19.05.010
AS 19.05.020
AS 19.05.040
AS 19.05.125
AS 19.10.060
AS 44.42.020
AS 44.42.030
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.