3 AAC 50.795 - Reporting

(a) Within seven calendar days, an electric utility shall file with the commission in writing
(1) notification of a period in which purchases of power from a qualifying facility are curtailed under 3 AAC 50.770(b)(1);
(2) notification of a system emergency in which purchases of power from a qualifying facility are curtailed under 3 AAC 50.770(b)(2);
(3) notification of an agreement in which an electric utility transmits power from a qualifying facility under 3 AAC 50. 770(b)(3);
(4) notification of a request for interconnection with an entity claiming qualifying facility rights under 3 AAC 50.750- 3 AAC 50.820;
(5) notification of denial of interconnection with an entity claiming qualifying facility rights under 3 AAC 50.750- 3 AAC 50.820.
(b) A qualifying facility shall comply with the state commission service requirement of 18 C.F.R. 292.207(c)(1) by concurrently filing with the commission an explanatory cover letter accompanied by a copy of all forms and documents filed with the Federal Energy Regulatory Commission under either 18 C.F.R. 292.207(a) or 18 C.F.R. 292.207(b)(1) and (2).

Notes

3 AAC 50.795
Eff. 3/11/2016, Register 217, April 2016

Authority:AS 42.05.141

AS 42.05.151

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.