(a) Alternatives to
the Proposed Project. An EIR shall describe a range of reasonable alternatives
to the project, or to the location of the project, which would feasibly attain
most of the basic objectives of the project but would avoid or substantially
lessen any of the significant effects of the project, and evaluate the
comparative merits of the alternatives. An EIR need not consider every
conceivable alternative to a project. Rather it must consider a reasonable
range of potentially feasible alternatives that will foster informed
decisionmaking and public participation. An EIR is not required to consider
alternatives which are infeasible. The lead agency is responsible for selecting
a range of project alternatives for examination and must publicly disclose its
reasoning for selecting those alternatives. There is no ironclad rule governing
the nature or scope of the alternatives to be discussed other than the rule of
reason. (Citizens of Goleta Valley v. Board of Supervisors
(1990) 52 Cal.3d 553 and Laurel Heights Improvement Association v.
Regents of the University of California (1988) 47 Cal.3d
376).
(b) Purpose. Because an EIR
must identify ways to mitigate or avoid the significant effects that a project
may have on the environment (Public Resources Code Section 21002.1), the
discussion of alternatives shall focus on alternatives to the project or its
location which are capable of avoiding or substantially lessening any
significant effects of the project, even if these alternatives would impede to
some degree the attainment of the project objectives, or would be more
costly.
(c) Selection of a range of
reasonable alternatives. The range of potential alternatives to the proposed
project shall include those that could feasibly accomplish most of the basic
objectives of the project and could avoid or substantially lessen one or more
of the significant effects. The EIR should briefly describe the rationale for
selecting the alternatives to be discussed. The EIR should also identify any
alternatives that were considered by the lead agency but were rejected as
infeasible during the scoping process and briefly explain the reasons
underlying the lead agency's determination. Additional information explaining
the choice of alternatives may be included in the administrative record. Among
the factors that may be used to eliminate alternatives from detailed
consideration in an EIR are:
(i) failure to
meet most of the basic project objectives,
(ii) infeasibility, or
(iii) inability to avoid significant
environmental impacts.
(d)
Evaluation of alternatives. The EIR shall include sufficient information about
each alternative to allow meaningful evaluation, analysis, and comparison with
the proposed project. A matrix displaying the major characteristics and
significant environmental effects of each alternative may be used to summarize
the comparison. If an alternative would cause one or more significant effects
in addition to those that would be caused by the project as proposed, the
significant effects of the alternative shall be discussed, but in less detail
than the significant effects of the project as proposed. (County of
Inyo v. City of Los Angeles (1981) 124 Cal.App.3d 1).
(e) "No project" alternative.
(1) The specific alternative of "no project"
shall also be evaluated along with its impact. The purpose of describing and
analyzing a no project alternative is to allow decisionmakers to compare the
impacts of approving the proposed project with the impacts of not approving the
proposed project. The no project alternative analysis is not the baseline for
determining whether the proposed project's environmental impacts may be
significant, unless it is identical to the existing environmental setting
analysis which does establish that baseline (see Section
15125).
(2) The "no project" analysis shall discuss
the existing conditions at the time the notice of preparation is published, or
if no notice of preparation is published, at the time environmental analysis is
commenced, as well as what would be reasonably expected to occur in the
foreseeable future if the project were not approved, based on current plans and
consistent with available infrastructure and community services. If the
environmentally superior alternative is the "no project" alternative, the EIR
shall also identify an environmentally superior alternative among the other
alternatives.
(3) A discussion of
the "no project" alternative will usually proceed along one of two lines:
(A) When the project is the revision of an
existing land use or regulatory plan, policy or ongoing operation, the "no
project" alternative will be the continuation of the existing plan, policy or
operation into the future. Typically this is a situation where other projects
initiated under the existing plan will continue while the new plan is
developed. Thus, the projected impacts of the proposed plan or alternative
plans would be compared to the impacts that would occur under the existing
plan.
(B) If the project is other
than a land use or regulatory plan, for example a development project on
identifiable property, the "no project" alternative is the circumstance under
which the project does not proceed. Here the discussion would compare the
environmental effects of the property remaining in its existing state against
environmental effects which would occur if the project is approved. If
disapproval of the project under consideration would result in predictable
actions by others, such as the proposal of some other project, this "no
project" consequence should be discussed. In certain instances, the no project
alternative means "no build" wherein the existing environmental setting is
maintained. However, where failure to proceed with the project will not result
in preservation of existing environmental conditions, the analysis should
identify the practical result of the project's non-approval and not create and
analyze a set of artificial assumptions that would be required to preserve the
existing physical environment.
(C)
After defining the no project alternative using one of these approaches, the
lead agency should proceed to analyze the impacts of the no project alternative
by projecting what would reasonably be expected to occur in the foreseeable
future if the project were not approved, based on current plans and consistent
with available infrastructure and community
services.
(f)
Rule of reason. The range of alternatives required in an EIR is governed by a
"rule of reason" that requires the EIR to set forth only those alternatives
necessary to permit a reasoned choice. The alternatives shall be limited to
ones that would avoid or substantially lessen any of the significant effects of
the project. Of those alternatives, the EIR need examine in detail only the
ones that the lead agency determines could feasibly attain most of the basic
objectives of the project. The range of feasible alternatives shall be selected
and discussed in a manner to foster meaningful public participation and
informed decision making.
(1) Feasibility.
Among the factors that may be taken into account when addressing the
feasibility of alternatives are site suitability, economic viability,
availability of infrastructure, general plan consistency, other plans or
regulatory limitations, jurisdictional boundaries (projects with a regionally
significant impact should consider the regional context), and whether the
proponent can reasonably acquire, control or otherwise have access to the
alternative site (or the site is already owned by the proponent). No one of
these factors establishes a fixed limit on the scope of reasonable
alternatives. (Citizens of Goleta Valley v. Board of
Supervisors (1990) 52 Cal.3d 553; see Save Our Residential
Environment v. City of West Hollywood (1992) 9 Cal.App.4th 1745, 1753,
fn.1).
(2) Alternative locations.
(A) Key question. The key question and first
step in analysis is whether any of the significant effects of the project would
be avoided or substantially lessened by putting the project in another
location. Only locations that would avoid or substantially lessen any of the
significant effects of the project need be considered for inclusion in the
EIR.
(B) None feasible. If the lead
agency concludes that no feasible alternative locations exist, it must disclose
the reasons for this conclusion, and should include the reasons in the EIR. For
example, in some cases there may be no feasible alternative locations for a
geothermal plant or mining project which must be in close proximity to natural
resources at a given location.
(C)
Limited new analysis required. Where a previous document has sufficiently
analyzed a range of reasonable alternative locations and environmental impacts
for projects with the same basic purpose, the lead agency should review the
previous document. The EIR may rely on the previous document to help it assess
the feasibility of potential project alternatives to the extent the
circumstances remain substantially the same as they relate to the alternative.
(Citizens of Goleta Valley v. Board of Supervisors (1990) 52
Cal.3d 553, 573).
(3) An
EIR need not consider an alternative whose effect cannot be reasonably
ascertained and whose implementation is remote and speculative.
(Residents Ad Hoc Stadium Committee v. Board of Trustees
(1979) 89 Cal. App.3d 274).