Cal. Code Regs. Tit. 14, § 15221 - NEPA Document Ready Before CEQA Document
(a) When a project will require compliance
with both CEQA and NEPA, state or local agencies should use the EIS or finding
of no significant impact rather than preparing an EIR or negative declaration
if the following two conditions occur:
(1) An
EIS or finding of no significant impact will be prepared before an EIR or
negative declaration would otherwise be completed for the project;
and
(2) The EIS or finding of no
significant impact complies with the provisions of these
guidelines.
(b) Because
NEPA does not require separate discussion of mitigation measures or growth
inducing impacts, these points of analysis will need to be added, supplemented,
or identified before the EIS can be used as an EIR.
Notes
Note: Authority cited: Section 21083, Public Resources Code. Reference: Sections 21083.5 and 21083.7, Public Resources Code; Section 102(2)(C) of NEPA, 43 U.S.C.A. 4322(2)(C).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.