2 CCR 402-1-4 - Definitions
4.1
Alteration, Modification, Repair, or Enlargement of an Existing Dam
and/or Appurtenant Structures. Construction that could affect the safety
of the dam.
4.2
Annual
Exceedance Probability (AEP). The probability of occurrence in any one
year.
4.3
Appurtenant
Structure. Component other than the material structure of the dam itself
such as the outlet works and controls, spillways and controls, access
structures, bridges, and other systems directly related to the safe operation
of a dam.
4.4
Breach
Order. An order issued by the State Engineer, or the State Engineer's
designee, for removal of all or part of a dam to permanently reduce the maximum
storage level, minimize the risk of failure, and/or the potential of damage
downstream due to the failure of the dam.
4.5
Capacity. As used in section
37-87-105(1),
C.R.S., the volume of water impounded by a dam at the high water line. Storage
below the natural surface of the ground and low-level outlet is generally
excluded.
4.6
Dam. A
constructed barrier, together with appurtenant structures, constructed above
ground surface for the purpose of impounding water. Flood control and storm
runoff detention dams are included.
4.6.1
Jurisdictional Size Dam. A dam creating a reservoir with a
capacity of more than one hundred (100) acre-feet, or a surface area in excess
of twenty (20) acres at the high water line, or where the jurisdictional height
exceeds ten (10) feet. Jurisdictional height is defined in Rule
4.7.1.
4.6.2
Non-Jurisdictional Size Dam. A dam creating a reservoir with a
capacity of one hundred (100) acre-feet or less, and a surface area of twenty
(20) acres or less, and a jurisdictional height of ten (10) feet or less.
Non-jurisdictional size dams are regulated and subject to the authority of the
State Engineer.
4.6.3
Diversion Dam. A dam constructed for the primary purpose of
diverting water from a natural watercourse into a canal, tunnel, ditch, or
pipeline.
4.6.4
Flood Control
Dam. A dam that is normally dry and has an ungated outlet structure for
the controlled release of water impounded during and subsequent to a flood
event.
4.7
Dam
Height. (See Figure 4.1)
4.7.1
Jurisdictional Height. The vertical dimension measured from the
lowest point of the natural surface of the ground or the invert of the outlet
pipe, whichever is lower, where the low point occurs along the longitudinal
centerline of the dam crest, to the emergency spillway crest.
4.7.2
Hydraulic Height. The
vertical dimension measured from the lowest point of the upstream toe of the
dam to the emergency spillway crest.
4.7.3
Structural Height. The
vertical dimension measured from the lowest point of the excavated foundation
to the crest of the dam.
Figure 4.1: Determination of Dam Heights
Click to view image
4.8
Inundation Map. A map
depicting the area downstream from a dam that would reasonably be expected to
be flooded in the event of a dam failure.
4.9
Emergency Action Plan (EAP).
A living document containing a written plan of actions used by an emergency
response team to minimize property damage and loss of life in an area affected
by a dam failure or large flood.
4.10
Engineer. An Engineer
registered and licensed in Colorado in accordance with article 12-120, Part 2,
C.R.S. The Engineer will be in "responsible charge," as defined in section
12-120-202, C.R.S., of the design
and of the observation of construction. In general, the Engineer is responsible
for the following:
A. Demonstrating a minimum
of five years of experience as a registered Engineer in the design,
construction, and safety evaluation of the type of dam under review;
B. Understanding all applicable regulatory
requirements of the project and the required work, analyses, and oversight
needed to complete a safe design and to observe construction to evaluate
compliance with plans and specifications of the project;
C. Using current state of the practice
methods and means to site and design dams with safety as the primary goal and
to complete engineering methodology that represents the professional level of
care exercised by qualified engineers; and
D. If necessary, assembling and supervising a
team of qualified engineers, geologists, geological engineers, and other
professionals as required to address all of the disciplines for the design and
the observation of construction of a dam.
4.11
Freeboard.
4.11.1
Normal Freeboard. The
vertical dimension between a spillway crest and the lowest point on the dam
crest.
4.11.2
Residual
Freeboard. The vertical dimension between the maximum water surface
elevation during a flood event and the lowest point on the dam crest.
4.12
Geologist. An
individual possessing specific knowledge of the geological sciences and the
principles of engineering analysis and design acquired by professional
education or demonstrated experience related to dams, and qualified to apply
such knowledge to ensure geologic elements affecting the dam are adequately
accounted for in design and construction.
4.13
Hazard Classification. One
of four categories defined below as determined by analysis of potential
consequences from a sunny day failure of the dam. Conditions for evaluation are
absent flooding and the reservoir is assumed to be full to the high water line
at the time of failure. The hazard classification establishes all the design
criteria for a dam except for spillway size, which is controlled by the
Hydrologic Hazard defined in Rule 4.15.
4.13.1
High Hazard. A dam for which life loss is expected to result from
failure of the dam.
4.13.2
Significant Hazard. A dam for which significant damage, but no
life loss is expected to result from failure of the dam. Significant damage is
defined as damage to structures where people generally live, work, or recreate,
including public and private facilities. Significant damage is determined to be
damage sufficient to render structures or facilities uninhabitable or
inoperable.
4.13.3
Low
Hazard. A dam for which neither life loss nor significant damage as
defined for a Significant Hazard dam are expected to result from failure of the
dam.
4.13.4
No Public Hazard
(NPH). A dam for which minimal damage, with no life loss, is expected to
result from failure of the dam.
4.14
High Water Line. The
elevation of the emergency spillway crest. If no emergency spillway exists, the
elevation of the dam crest.
4.15
Hydrologic Hazard. Potential consequences downstream of a dam
caused by floodwaters released by overtopping failure of the dam. Hydrologic
hazard establishes design criteria for spillway size.
4.15.1
Extreme. Life loss
potential of 1 or more.
4.15.2
High. Life loss potential of less than 1.
4.15.3
Significant. No life loss
potential but significant damage is expected to occur.
4.15.4
Low. No life loss
potential or significant damage is expected to occur.
4.16
Incremental Consequences.
The difference in impacts that would occur due to failure or misoperation of
the dam over those that would have occurred without failure or misoperation of
the dam or appurtenances.
4.17
Inflow Design Flood (IDF). The flood hydrograph used to determine
if the emergency spillway's hydraulic capacity meets the safety standards as
defined in Rule 7.2.
4.18
Natural Surface of the Ground. The undisturbed ground surface
before excavation, or the undisturbed bed of a natural watercourse.
4.19
Normal Water Line. The
elevation of the service spillway crest. If there is no service spillway, the
normal water line and high water line are the same.
4.20
Outlet. A conduit (usually
regulated by gates or valves) used for releasing impounded water from the
reservoir.
4.21
Owner.
The person or persons in control of the physical structure of any dam in
accordance with section
37-87-104.5, C.R.S. Person or
persons refers to any individual, private or non-profit company, special
district, federal, state, or local government agency, or any other entity in
direct routine control of a dam and reservoir, and/or directly involved in the
physical operation and maintenance of a dam, and/or proposes to construct a
dam.
4.22
Plans. All
necessary drawings, cross-sections, tables, notes, maps and other information
necessary to accompany the construction specifications for design review and
approval, and construction of a dam.
4.23
Potential Failure Mode
(PFM). A physically plausible process for dam failure resulting from an
existing inadequacy or defect related to a natural foundation condition, the
design or construction of the dam or appurtenant structures, the materials
incorporated, the operations and maintenance, or the aging process, which can
lead to an uncontrolled release of the reservoir.
4.24
Potential Failure Modes Analysis
(PFMA). The process by which the site-specific PFMs are identified,
described in detail, and evaluated to determine the likelihood and confidence
of occurrence.
4.25
Probable
Maximum Flood (PMF). The flood that may be expected from the most severe
combination of critical meteorologic and hydrologic conditions that are
reasonably possible in the drainage basin under study.
4.26
Probable Maximum Precipitation
(PMP). The theoretically greatest depth of precipitation for a given
duration that is physically possible over a drainage basin.
4.27
Reservoir. A body of water
impounded by a dam.
4.28
Restriction Order. An order issued by the State Engineer to limit
the water surface elevation of a reservoir to no greater than the safe storage
level.
4.29
Risk. The
product of (1) the likelihood of a structure being loaded, (2) the likelihood
of adverse structural performance, and (3) the magnitude of the resulting
consequences.
4.29.1
Risk
Management. Action implemented to communicate the risks and either
accept, avoid, transfer, or control the risks to an acceptable level
considering associated costs and benefits of any action taken.
4.29.2
Risk Analysis.
Qualitative or quantitative procedures that consider likelihood of failure and
magnitude of resulting consequences to evaluate the significance of
PFMs.
4.30
Safe
Storage Level. The maximum reservoir water surface elevation at which
the State Engineer has determined that the dam is safe to impound water based
on the safety inspection and/or evaluations.
4.31
Safety Inspection. An
evaluation by an Engineer in accordance with section
37-87-107, C.R.S., used by the
State Engineer to set the safe storage level. The inspection shall include a
review of the Emergency Action Plan and the hazard classification of the
dam.
4.32
Spillway. An
overflow structure through which inflow is discharged from a reservoir.
4.32.1
Service Spillway. The
overflow structure designed to limit or control the operating level of a
reservoir.
4.32.2
Emergency
Spillway. The overflow structure designed to pass the Inflow Design
Flood.
4.32.3
Spillway
Crest. The elevation of the spillway at which uncontrolled discharge
begins.
4.33
Storage.
4.33.1
Normal
Storage. Volume of the reservoir impounded by a dam below the normal
water line.
4.33.2
Maximum
Storage. Volume of the reservoir impounded by a dam below the dam
crest.
4.33.3
Flood
Storage. Volume of water temporarily stored within a reservoir between
the normal water line and the crest of the dam.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.