2 CCR 402-1-5 - Determination of Safe Storage Level
5.1
Authority to Determine Safe Storage Level. The State Engineer is
assigned the responsibility to determine the safe storage level for every
reservoir in the state in accordance with section
37-87-107, C.R.S. The Owner shall
not store water in excess of the amount so determined by the State Engineer to
be safe.
5.2
Methods to
Determine Safe Storage Level. The State Engineer will use the following
methods to determine the safe storage level:
5.2.1
Safety Inspection. The
State Engineer shall perform regular dam safety inspections at a frequency
appropriate to the hazard classification of the dam. These inspections will be
performed using current observation methods and tools, and adhere to current
standards. Observations will be recorded in a standardized report format, and
provided to the Owner following the inspection. Interim dam safety inspections
may also be performed between regular inspection cycles when warranted by
either the condition of the dam or events impacting the safety of the
dam.
5.2.2
Potential Failure
Modes Analysis. Potential Failure Modes Analysis may be performed
following identification of a concerning issue during the regular or interim
inspection and/or as part of a periodic comprehensive dam safety
evaluation.
5.3
Restriction of Storage. If problems affecting the safe storage
level of the reservoir are discovered, the State Engineer will issue a
restriction order as an interim measure until the problems have been resolved.
The Owner shall comply with the restriction order at all times. The restriction
order will be removed or revised by the State Engineer only after acceptance of
repairs or approval of engineering evaluations indicating the problems have
been adequately resolved.
5.4
Review of Hazard Classification. As part of the determination of
the safe storage level, the State Engineer will periodically review the hazard
classification of existing dams by evaluating the consequences of failure
applying the definitions of Rule 4.13 . If the State Engineer's review
indicates the consequences of failure have changed within the dam failure
inundation area, the State Engineer will assign an appropriate new hazard
classification. The State Engineer will require the dam to meet the
requirements of these Rules as they apply to the new hazard classification
within a reasonable period of time.