2 CCR 402-1-8 - Construction Requirements
8.1
Pre-Construction
8.1.1
Water Diversion Plan.
8.1.1.1 A
plan to control surface water during construction shall be developed by the
construction contractor based on information and requirements provided by an
Engineer. The plan shall state the return interval or annual exceedance
probability for the storm event the system is designed to protect against. The
plan shall be prepared under the direction of an Engineer meeting the
requirements of Rule 4.10.
8.1.1.2
The plan shall be approved by the Engineer and submitted to the State Engineer
in advance of construction of the diversion facilities.
8.1.1.3 A hazard classification evaluation
shall be performed by an Engineer based on consequences to the public for any
proposed cofferdam. If the water diversion system is found to be High or
Significant Hazard, the design shall meet the requirements of Rule 7.
8.1.1.4 The water diversion plan shall
address the removal or abandonment of cofferdams, spillways, conduits, or other
temporary features after construction is complete.
8.1.2
Construction Observation
Plan. Not less than thirty (30) days prior to construction, the Engineer
shall submit a construction observation plan to the State Engineer. The
construction observation plan shall include, at a minimum:
A. The anticipated date of the start of
construction;
B. Names and resumes
of the Engineer and staff to be used on the project;
C. A construction observation schedule for
the Engineer and staff;
D. For dams
on rock foundations, a schedule for observations of the foundation by a
Geologist;
E. A quality assurance
plan including a schedule of the construction material tests; and
F. Identification of the firm and
qualifications of the personnel that will conduct the construction material
tests in the field and in the laboratory.
8.1.2.1
Approval. Within
fourteen (14) days of receipt, the State Engineer shall provide written
comments and approval, or conditions for approval, of the construction
observation plan. Construction shall not commence without approval of the
observation plan by the State Engineer.
8.1.3
Pre-Construction Meeting.
Prior to commencement of construction, a meeting shall be held between the
Engineer, Owner, State Engineer, and contractor. The State Engineer shall be
notified at least fourteen (14) days prior to the meeting. The contractor shall
present and thoroughly explain its construction work plan along with any
anticipated construction difficulties. The name of the subcontractors shall be
furnished to the State Engineer at the meeting. Project communication protocol
between the Owner, Engineer, and the State Engineer shall be established at the
pre-construction meeting.
8.2
Construction.
8.2.1
Engineer's Observation.
The Engineer shall observe the progress and quality of the construction in
accordance with the approved construction observation plan. The Engineer shall
endeavor to prevent defects and deficiencies in the construction of the dam and
appurtenant structures, and shall disapprove or reject work failing to conform
to the approved plans and specifications. In cases where the Engineer has a
contractual relationship with the contractor to provide engineering services,
the Owner shall provide an independent, third-party engineer to perform the
engineering quality assurance observations.
8.2.2
Construction Records. The
Engineer shall maintain a record of construction that, at a minimum, shall
include daily activity and progress reports, design change orders, all
materials testing results, gate and valve installation certifications,
photographs sufficient to provide a record of foundation conditions and various
stages of the construction through completion, all geologic information
obtained, and documentation of any construction problems and
remedies.
8.2.3
Progress
Reports. Progress reports summarizing the status of the work shall be
submitted to the State Engineer during the project at a minimum frequency and
in a format agreed upon during the pre-construction meeting. The progress
report shall include the contractor's three-week look-ahead schedule.
8.2.4
Notice for Inspection. The
Engineer shall give the State Engineer at least five (5) days advance notice of
any work items listed by the State Engineer in the pre-construction meeting, to
allow for observation by the State Engineer.
8.2.5
Design Change Order. When
unforeseen site conditions or material availability require that the
construction work differ significantly from the approved plans and
specifications, a design change order, including details, shall be provided by
the Engineer to the State Engineer. No change shall be executed until approved
by the State Engineer. Major changes shall be submitted in writing with
supporting documentation, and approved in writing by the State Engineer. Minor
changes, as determined by the State Engineer, may be approved verbally and
documented in the final construction documents.
8.2.6
Final Inspection. The
Engineer shall give the State Engineer at least fourteen (14) days advance
notice prior to the project's final construction inspection. The Engineer shall
document the completion of any punch list items.
8.3
Acceptance of Construction.
Construction shall not be deemed complete nor shall storage of water be
permitted until the State Engineer furnishes to the Owner a written statement
of acceptance. The acceptance shall state the as-constructed dam dimensions,
the capacity of the reservoir, and any limitations upon or requirements for the
use of the dam. The State Engineer shall furnish the acceptance or denial
within sixty (60) days of receipt of construction completion documents as
outlined below.
8.3.1
Construction
Completion Documents. The Engineer shall provide the following
construction documentation within sixty (60) days of the final construction
inspection:
8.3.1.1 A written notification
that the project is complete and in general conforms with the approved plans,
specifications, and design change orders.
8.3.1.2 A schedule for the first filling of
the reservoir specifying fill rates, water level elevations to be held for
observation, and a schedule for inspecting and monitoring the dam.
8.3.1.3 As-constructed plans showing the
original approved plans amended to include any major or minor
changes.
8.3.1.4 A final
construction report summarizing construction, problems encountered and
solutions implemented to resolve the problems, and compiling the construction
records as identified in Rule 8.2.2.
8.3.1.5 A record of the location of permanent
monuments and instrumentation as well as installation details and initial
surveys and readings, if applicable.
8.3.1.6 The approved dam observation and
monitoring plan in accordance with Rule 13.4.
8.3.1.7 A new or updated Emergency Action
Plan including current inundation map in accordance with Rule 13.7.
8.3.2 For new dams and
enlargements, the Engineer shall provide periodic review of the data included
in the dam observation and monitoring plan on at least an annual basis for the
first five years following construction completion. The Engineer shall submit
the data and a written assessment of the dam's performance to the State
Engineer annually.
8.3.3
Temporary Approval. Upon written request by the Owner and for good
cause shown, the State Engineer may temporarily approve storage of water prior
to submitting the construction completion documents. Only a partial reservoir
filling will be granted under this Rule. Final acceptance of the construction
for full use of the reservoir will not be granted until the requirements of
Rule 8.3 have been satisfactorily completed. The written request shall include,
at a minimum:
A. A schedule for compliance
with Rule 8.3;
B. A notification
letter signed and sealed by the Engineer in accordance with Rule
8.3.1.1;
C. A schedule for the
first filling of reservoir in accordance Rule 8.3.1.2;
D. A monitoring plan for observing the
behavior of the dam and appurtenances during the initial filling or refilling
of the reservoir; and
E. A new or
updated EAP prepared in accordance with Rule 13.7.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.