2 CCR 402-1-9 - Requirements for Removing or Breaching an Existing Dam
9.1
Breach Plan and Application.
An Owner proposing to permanently remove or breach a dam shall submit an
application package to be approved by the State Engineer prior to commencing
work. The application shall be completed on a form provided by the State
Engineer and shall include the following:
9.1.1 Documentation demonstrating that notice
has been given to land owners and agencies potentially impacted by removal or
breach of the dam.
9.1.2
Documentation showing that all permitting requirements by local, state and
federal agencies have been satisfied.
9.1.3 A breach plan meeting the following
requirements:
9.1.3.1 The breach shall be
designed to prevent silt previously deposited in the reservoir and material
excavated for the breach from washing downstream.
9.1.3.2 Water impounded in the reservoir area
shall be released in a controlled manner that will not endanger lives or damage
downstream properties.
9.1.3.3 The
minimum bottom width of the breach shall be one-half the height of the dam or
10 feet, whichever is greater.
9.1.3.4 The sides of the breach shall be
excavated to a slope that is stable, but not steeper than 2H:1V
(horizontal:vertical). A slope stability analysis that demonstrates an adequate
factor of safety for slopes steeper than 2H:1V may be accepted by the State
Engineer. The breach dimensions shall meet water administration requirements of
the Division Engineer. The dam shall be excavated down to the level of the
natural ground at the maximum section, or as otherwise necessary to comply with
Rule 9.1.3.
9.1.3.5 The excavated
material shall not be placed in the stream channel.
9.1.3.6
High and Significant Hazard
Dams. The breach plan for High and Significant Hazard dams shall meet
the following additional requirements:
9.1.3.6.1 The plan shall be prepared by an
Engineer.
9.1.3.6.2 The breach
shall be of sufficient width to pass the twenty four (24) hour, one percent AEP
flood with a maximum increase in reservoir depth of five (5) feet. However, the
maximum breach width shall not be required to exceed the width of the original
natural channel before the dam was constructed, regardless of the one percent
AEP flood.
9.1.3.6.3 Breach side
slope and channel protection may be required to prevent erosion and provide
long-term stability.
9.1.3.6.4
Remaining infrastructure shall be left in a safe condition.
9.1.3.6.5 Construction plans shall meet the
requirements of Rule 6 that are applicable to support the scope of work as
described on the application.
9.1.3.6.6 The dewatering and removal or
breaching of the dam shall be overseen by an Engineer.
9.1.3.6.7 A written notification that the
project is complete and in general conformance with the approved breach plan
shall be provided within sixty (60) days of completion of construction. The
State Engineer will provide acceptance upon review and receipt of these
documents.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.