Basis and Purpose: The statutory authority
for this Rule is found in sections
37-91-101(1),
37-91-104(1)(c),
37-91-109(1)
& (2), 37-91-110(2), C.R.S. The purpose of this Rule is to establish the
minimum standards for installing pumping equipment and cisterns that are
connected to water well supply systems in order ensure that such installation
prevents harm to the public health, will not impair water quality or cause
contamination of shared groundwater resources, and will ensure the safety of
groundwater resources for Colorado's existing and future populations.
11.1
General Rules - All
permanent pump installations and cistern installations in or connected to a new
or existing water well supply system must be completed by a licensed pump
installation contractor or a private pump installer (see Sections
37-91-102 (12.5) and 37-91-109(2),
C.R.S.). Pumping equipment may be installed in wells constructed and used
solely for purposes of aquifer remediation (recovery well) or temporary
dewatering (dewatering well) by authorized individuals or anyone directly
employed by or under the supervision of an authorized individual. It is the
responsibility of the person installing the pumping equipment to ensure that a
valid well permit authorizing such installation exists in accordance with the
requirements of Rule 6.2.2.1 and 6.2.2.2.
11.1.1 Licensed water well construction
contractors who are not licensed as pump installation contractors may not
install pumping equipment in a well, except for temporary pumps used only for
well development and testing.
11.1.2 Licensed pump installation contractors
may not remove casing or install casing except for:
a. removal, alteration, or repair of casing
to install a pitless adapter or pitless unit,
b. the upward extension of existing casing
from the pitless adapter or pitless unit, or
c. the installation or replacement of casing
in a well constructed through a single aquifer where such installation or
replacement does not require the placement of grout in the annulus to meet the
standards of these Rules.
11.1.3 Licensed pump installation contractors
may not install grout in the annular space of a well or between well casing as
required by Rule 10. This prohibition does not apply to grout installation
associated with the installation of a pitless adapter, or grout installed in a
well to abandon the well pursuant to Rule 16.
11.1.4 Pumping systems may not be designed to
exceed the permitted pumping rate at the point of delivery when operating under
normal design conditions.
11.1.5
Pump installation contractors and private pump installers must submit a pump
installation report every time a pump is installed in a well or for any change
in the pump depth setting. The report must describe the pump, date of
installation, its depth setting, static water level, and the results from the
production equipment test required by Rule 12.
11.2
Installation Standards -
Pumps, cisterns, pitless units and adapters, and related equipment that will be
installed as part of, or connected to, a water well supply system must be
installed in such a manner that the well, pump, cistern, and surrounding area
will be kept in a sanitary condition, and will provide adequate protection
against contamination from any surface or subsurface source.
11.2.1 Pump installation contractors may not
cut off or penetrate well casing below ground level except to install a pitless
adapter or a pitless unit. Pitless adapters must be installed on steel casing
that extends to a minimum of one (1) foot above the finished ground level and
must be watertight. Pitless units must have steel extensions to a minimum of
one (1) foot above the finished ground level. All connections to the pitless
adapters or pitless units must be made with threaded, flanged, welded or
mechanical joints. Mechanical joints must be rodded across the connection and
secured to the body of the well casing or pitless assembly. In the event it is
necessary to cut off the outermost casing below ground level in order to
install a pitless unit on the inner casing, the contractor must comply with the
requirements of Rule 10.5.2.1.
11.2.2 A pump installation contractor may
only install a pitless adapter or pitless unit if, after such installation, the
minimum continuous grout interval required by Rule 10.4 and Rule 10.5 is
maintained.
11.2.3 Flowing wells
must be equipped so that the discharge can be controlled or stopped at all
times. It is the responsibility of the pump installation contractor or private
pump installer to install such equipment. Thereafter, it is the responsibility
of the well owner to ensure the equipment is maintained and
operational.
11.2.4 Pump
installation contractors may not cut off or penetrate cisterns below ground
level except to install watertight devices for water line or electrical
connections.
11.3
Cistern Installation and Location - When selecting a cistern
location, consideration must be given to topography, drainage, sources of
contaminants, and other onsite conditions in order to promote sanitary
conditions and prevent contamination of the well and aquifer.
11.3.1 A cistern installed below ground level
must be constructed and placed in such a manner to withstand saturated soil
pressures when empty.
11.3.2 A
cistern installed below ground level must be watertight and the access portal
must extend to at least one foot above the ground surface. The backfill
material must be sloped away from the access portal.
11.3.3 A cistern installed below ground level
must be buried to an adequate depth to prevent freezing.
11.3.4 A cistern installed below ground level
must be properly bedded and backfilled in accordance with the manufacturers
recommendation.
11.3.5 A cistern
placed in a building must be placed in an area that is adequate to support the
anticipated loads of the cistern, full of water, all pumping equipment, and
controls.
11.3.6 A cistern must be
placed in an area accessible to service.
11.3.7 When an existing cistern is connected
to a water well supply system, the installation or connection must be performed
by a licensed pump installation contractor. See ยง
37-91-109(2),
C.R.S. The cistern that is connected to the water well supply system must meet
all of the requirements of Rules 11.3 and 11.4 and any relevant local
regulation.
11.4
Location Variance - A cistern installed below ground level must
not be located closer than one hundred (100) feet horizontally to the nearest
existing source of contaminants or fifty (50) feet horizontally from a septic
tank, sewer line or other vessel containing contaminants. A request for
variance must be submitted and written approval from the Board must be obtained
prior to the construction of a cistern that cannot meet this spacing
requirement. The variance request must be prepared in accordance with Rule 18.2
by a pump installation construction contractor or authorized individual, and
must be based on hydrogeologic information.
11.5
Seals and Vents -
11.5.1
Well Seals - All pumping
equipment must be installed with an effective metal well seal at the top of the
casing that will prevent the entry of contaminants into the well. The pumping
equipment must be designed to allow for its installation and removal through an
approved well seal and to prevent unprotected openings from connecting with the
interior of the pump or well. Only metal well seals (with metal caps) are
approved well seals within the meaning of this Rule and section
37-91-102(18),
C.R.S.
11.5.2
Well and
cistern vents - When needed or used, well or cistern vents must be
connected with watertight joints and permit air to freely enter and exit the
well with changing water levels in the casing. Vents may be an integral part of
the well or cistern seal or be attached to the seal and terminate a minimum of
one (1) foot above the finished ground level, be turned down, and screened to
prevent entry of insects and rodents. Vents must be constructed to vent all
gases to the atmosphere outside of a building and to prevent gas accumulation
that could produce a health or explosion hazard.
11.6
Well Vaults - New well
vault installations are not permitted unless the Board approves a specific
variance request. If a variance is granted by the Board, provisions must be
made to prevent contaminants from entering the well and for gravity drainage of
the vault through a floor drain or by an automatic sump pump.
11.6.1
Existing Well Vaults The
vault must be structurally sound to support anticipated surface loads and the
top must be watertight, including any manhole covers. The well casing must
extend at least one (1) foot above the floor of the vault and must have a well
seal to prevent contaminants from entering the well. Provisions must be made
for gravity drainage of the vault through a floor drain or by an automatic sump
pump. All drain openings must be screened to prevent the entry of rodents and
insects.
11.6.2 Well construction
or pump installation contractors encountering unacceptable well vaults must
make every effort to bring the well vault into compliance with these Rules. If
it is not possible to correct the problems, the contractor must notify the
Board of Examiners.
11.7
Water Level Measurement Devices - A water level sounding tube must
be installed on all wells whenever the permit issued by the State Engineer
requires installation of water level measuring equipment. The water level
sounding tube must have a minimum inside diameter of 3/4 (.75) inch. It must
extend from the well head to the top of the pump discharge equipment and must
be securely attached to the column or drop pipe so that it hangs straight. All
tubes must be equipped with a removable cap or plug to prevent entry of foreign
material. The bottom of the tube must be constructed to allow the free entry
and exit of water and to prevent the measuring device from passing out of the
bottom of the tube.
11.8
Compliance with Applicable Law All persons authorized to install
pumps and cisterns must comply with applicable federal, state, county,
municipal and local laws, regulations, and codes.
11.8.1
Electrical Connection of Pumping
Equipment Only licensed pump installation contractors, private pump
installers, or licensed electrical contractors, using appropriately licensed or
supervised personnel, may install electrical materials and connections between
the well head junction box and the pump service disconnect box (see Figure 6).
The materials, fittings, and control assemblies used for this installation must
meet the standards of the NFPA 70: National Electric Code (2014), and are
subject to permitting and inspection by the Colorado State Electrical Board.
Electric power to the pump service disconnect box must be installed by either a
licensed electrical contractor or the property owner.
FIGURE 6
REQUIREMENTS FOR WELL WIRING
* Electrical permit required prior to
installation
* Inspection required before concealment
* Rejections require reinspection fee
* Residential, domestic use only
* Not over 300 volts single phase
* use approved Electrical fittings, materials,
and control assemblies
Click to view
image
1. Well
casing
2. Well head
3. Metal nipple
4. Approved weatherproof box
5. Approved electrical conduit
6. Conductors approved for direct burial.
Size of conductors to be determined by size of pump motor and distance. Well
casing shall be bonded to the pump circuit equipment grounding conductor in
junction box on well casing
7.
Controller- licensed electrical contractor or licensed well
contractor
8. Disconnect- installed
by licensed electrical contractor or licensed well contractor
9. Foundation- all wiring through or under
foundation, or under concrete floor, to be installed in approved electrical
conduit
Note: Conduit must extend 18 inches below finished grade from
well junction box
11.8.2
Plumbing Connection of the
Pumping Equipment Only persons authorized to install pumps may install
piping and connection between the well and the point of discharge from the
pressure tank, if such a tank is installed. All materials and fittings used to
connect the well to the pressure tank must meet the standards of the Rules and
Regulations of the Colorado State Plumbing Board, 3 CCR
720-1.
11.9
Pressure Relief
Valve All water well supply systems capable of producing pressures
greater than seventy-five (75) pounds per square inch must be equipped with a
pressure relief valve sized to discharge the production rate of the pumping
system.
11.10
Backflow
Prevention Pump installations and cistern installations must have check
valves, backflow prevention devices or suitable air gap cross-connection
controls, if necessary to prevent damage to the pumping equipment and
contamination of the aquifer.
11.10.1 Pump
installations and cisterns supplying irrigation water where fertilizers,
insecticides, herbicides, or other chemicals are injected into the water must
be equipped to prevent well or aquifer contamination. The installation must
comply with Section
35-11-107, C.R.S. and the Rules
and Regulations Pertaining to the Administration and Enforcement of the
Colorado Chemigation Act,
8 CCR
1203-8, promulgated by the Department of Agriculture
pursuant to the Colorado Chemigation Act, Article 11 of Title 35,
C.R.S.
11.11
Disinfection After installing a pump or cistern, and prior to
placing the well in service, the person authorized to install pumping equipment
must disinfect the well, all pumping equipment, and the water supply system up
to the pressure tank according to the provisions of Rule 15.