4 CCR 723-3-3603 - Resource Plan Filing Requirements
(a)
Jurisdictional electric utilities shall file a resource plan pursuant to these
rules every four years beginning October 31, 2015. In addition to the required
four-year cycle, a utility may file an interim plan, pursuant to rule 3604. If
a utility chooses to file an interim plan more frequently than the required
four-year cycle, its application must state the reasons and changed
circumstances that justify the interim filing.
(b) Each jurisdictional electric utility
shall contemporaneously file with its resource plan submitted under paragraph
3603(a), a motion or motions seeking extraordinary protection of information
listed as highly confidential pursuant to paragraph 3604(j) and consistent with
rule 1101 of the Commission's Rules of Practice and Procedure. The utility
shall specifically address appropriate confidentiality protections and
nondisclosure requirements for modeling inputs and assumptions that may be used
to evaluate a potential resource and that reasonably relate to that facility.
The utility's motion or motions shall specify that response time shall run
concurrently with the intervention deadline established in the resource plan
proceeding. Finally, during the course of the resource plan proceeding, a
utility may file additional motions seeking extraordinary protection of
information for good cause shown.