4 CCR 723-3-3608 - Transmission Resources
(a) The
utility shall report its existing transmission capabilities, and future needs
during the planning period, for facilities of 115 kilovolts and above,
including associated substations and terminal facilities. The utility shall
generally identify the location and extent of transfer capability limitations
on its transmission network that may affect the future siting of
resources.
(b) With respect to
future needs, the utility shall submit a description of all transmission lines
and facilities appearing in its most recent report filed with the Commission
pursuant to ยง
40-2-126, C.R.S., that, as
identified in that report, could reasonably be placed into service during the
resource acquisition period.
(c)
For each transmission line or facility identified in paragraph (b), the utility
shall include the following information detailing assumptions to be used for
resource planning and bid evaluation purposes:
(I) length and location;
(II) estimated in-service date;
(III) injection capacity and locations for
generation facilities;
(IV)
injection capacity and locations for energy storage systems;
(V) estimated costs;
(VI) terminal points; and
(VII) voltage and megawatt rating.
(d) In order to equitably compare
possible resource alternatives, the utility shall consider the transmission
costs required by, or imposed on the system by, and the transmission benefits
provided by a particular resource as part of the bid evaluation
criteria.
(e) The resource plan
shall describe and shall estimate the cost of all new transmission facilities
associated with any specific resources proposed for acquisition other than
through a competitive acquisition process.