4 CCR 723-3-3613 - Bid Evaluation and Selection
(a) Upon
the receipt of bids in its competitive acquisition process, the utility shall
investigate whether each potential resource meets the requirements specified in
the resource solicitation and shall perform an initial assessment of the bids.
Within 45 days of the utility's receipt of bids, the utility shall provide
notice in writing by e-mail to the owner or developer of each potential
resource stating whether its bid is advanced to computer-based modeling to
evaluate the cost or the ranking of the potential resource, and, if not
advanced, the reasons why the utility will not further evaluate the bid using
computer-based modeling. If, after the utility issues notice to an owner or
developer that the potential resource was not advanced to computer-based
modeling, the utility subsequently advances that potential resource to
computer-based modeling, the utility shall provide notice in writing by e-mail
to the owner or developer of that potential resource within three business days
of the utility's decision to advance the potential resource to computer-based
modeling.
(b) For bids advanced to
computer-based modeling, the utility shall, contemporaneously with the
notification in paragraph 3613(a), also provide to the owner or developer the
modeling inputs and assumptions that reasonably relate to that potential
resource or to the transmission of electricity from that facility to the
utility. The utility shall provide such information so that modeling errors or
omissions may be corrected before the competitive acquisition process is
completed. Such information shall explain to the owner or developer how its
facility will be represented in the computer-based modeling and what costs, in
addition to the bid information, will be assumed with respect to the potential
resource. In the event that this information contains confidential or highly
confidential information, the owner or developer shall execute an appropriate
nondisclosure agreement prior to receiving this information.
(c) Within seven calendar days after
receiving the modeling inputs and assumptions from the utility pursuant to
paragraph 3613(b), the owner or developer of a potential resource shall notify
the utility in writing by electronic mail the specific details of any potential
dispute regarding these modeling inputs and assumptions. The owner or developer
shall attempt to resolve this dispute with the utility. However, if the owner
or developer and utility cannot resolve the dispute within three calendar days,
the utility shall immediately notify the Commission with a filing in the
resource plan proceeding. If the owner or developer is not already a party to
the proceeding, the owner or developer shall file a notice of intervention as
of right pursuant to paragraph 1401(b) of the Commission's Rules of Practice
and Procedure, within one business day of the utility's filing of its notice of
dispute to the Commission, for the limited purpose of resolving the disputed
modeling inputs and assumptions related to the potential resource. An
Administrative Law Judge (ALJ) will expeditiously schedule a technical
conference at which the utility and the owner or developer shall present their
dispute for resolution. The ALJ will enter an interim order determining whether
corrections to the modeling inputs and assumptions are necessary. If the ALJ
determines that corrections to the modeling inputs and assumptions are
necessary, the utility shall, within three business days of the issuance of the
ALJ's interim decision, provide the corrected information to both the owner or
developer and the independent evaluator. In its report submitted under
paragraph 3613(d), the utility shall also confirm by performing additional
modeling as necessary, that the potential resource is fairly and accurately
represented.
(d) Within 120 days of
the utility's receipt of bids in its competitive acquisition process, the
utility shall file a report with the Commission describing the cost-effective
resource plans that conform to the range of scenarios for assessing the costs
and benefits from the potential acquisition of increasing amounts of renewable
energy resources, demand-side resources, energy storage systems, or Section 123
resources as specified in the Commission's decision approving or rejecting the
utility plan developed under rule 3604. In the event that the utility's
preferred cost-effective resource plan differs from the Commission-specified
scenarios, the utility's report shall also set forth the utility's preferred
plan. The utility's plan shall also provide the Commission with the best value
employment metrics information provided by bidders under rule 3616 and by the
utility pursuant to rule 3611.
(e)
Within 30 days after the filing of the utility's 120-day report under paragraph
3613(d), the independent evaluator shall separately file a report that contains
the independent evaluator's analysis of whether the utility conducted a fair
bid solicitation and bid evaluation process, with any deficiencies specifically
reported. The independent evaluator shall provide confidential versions of
these reports to Commission staff and the UCA.
(f) Within 45 days after the filing of the
utility's 120-day report under paragraph 3613(d), the parties in the resource
plan proceeding may file comments on the utility's report and the independent
evaluator's report.
(g) Within 60
days after the filing of the utility's 120-day report under paragraph 3613(d),
the utility may file comments responding to the independent evaluator's report
and the parties' comments.
(h)
Within 90 days after the receipt of the utility's 120-day report under
paragraph 3613(d), the Commission shall issue a written decision approving,
conditioning, modifying, or rejecting the utility's preferred cost-effective
resource plan, which decision shall establish the final cost-effective resource
plan. The utility shall pursue the final cost-effective resource plan either
with a due diligence review and contract negotiations, or with applications for
CPCNs (other than those CPCNs provided in paragraph 3611(e)), as necessary. In
rendering the decision on the final cost-effective resource plan, the
Commission shall weigh the public interest benefits of competitively bid
resources provided by other utilities and non-utilities as well as the public
interest benefits of resources owned by the utility as rate base investments.
In accordance with ยงยง
40-2-123,
40-2-124,
40-2-129, and
40-3.2-104, C.R.S, the Commission
shall also consider renewable energy resources; resources that produce minimal
emissions or minimal environmental impact; energy-efficient technologies; and
resources that affect employment and the long-term economic viability of
Colorado communities. The Commission shall further consider resources that
provide beneficial contributions to Colorado's energy security, economic
prosperity, environmental protection, and insulation from fuel price
increases.
(i) The utility must
complete the competitive acquisition process by executing contracts for
potential resources within 18 months after the utility's receipt of bids in its
competitive acquisition process. The utility may file a motion in the resource
plan proceeding requesting to extend this deadline for good cause. The utility
must execute final contracts for the potential resources prior to the
completion of the competitive acquisition process to receive the presumption of
prudence afforded by paragraph 3617(d).
(j) Upon completion of the competitive
acquisition process pursuant to paragraph 3613(i), and consistent with the
subsequent requirement for website posting of bids and utility proposals as
required in paragraph 3613(k), protected information that was filed in the
resource plan proceeding will be refiled as non-confidential or public
information as specified in the Commission order described below. To satisfy
this requirement the utility shall file a proposal that addresses the public
release of all confidential and highly confidential information related to bids
for potential resources and resources the utility proposed to build and own as
a rate base investment. At a minimum the utility shall address its 120-day
report in paragraph 3613(d), the independent evaluator's report in paragraph
3613(e), and all documents related to these reports filed by the utility,
parties, or the independent evaluator. The utility shall file its proposal in
the resource plan proceeding within 14 months after the receipt of bids in its
competitive acquisition process. Parties will have 30 calendar days after the
utility files its proposal to file responses. The utility then may reply to any
responses filed within ten calendar days. The Commission shall issue an order
specifying to the utility and other parties the documents that shall be refiled
as public information.
(k) Upon
completion of the competitive acquisition process under paragraph 3613(i), the
utility shall post on its website the following information from all bids and
utility proposals: bidder name; bid price and utility cost, stated in terms
that allow reasonable comparison of the bids with utility proposals; generation
technology type; size of facility; contract duration or expected useful life of
facility for utility proposals; and whether the proposed power purchase
contract includes an option for the utility to purchase the facility during or
at the end of the contract term.