4 CCR 723-3-3615 - Exemptions and Exclusions
(a) The
following resources need not be included in an approved resource plan prior to
acquisition.
(I) Emergency maintenance or
repairs made to utility-owned generation facilities.
(II) Capacity and/or energy from
newly-constructed, utility-owned, supply-side resources with a nameplate rating
of not more than 30 MW.
(III)
Capacity and/or energy from the generation facilities of other utilities or
from non-utility generators pursuant to agreements for not more than a two year
term (including renewal terms) or for not more than 30 MW of
capacity.
(IV) Improvements or
modifications to existing utility generation facilities that change the
production capability of the generation facility site in question, by not more
than 30 MW, based on the utility's share of the total power generation at the
facility site and that have an estimated cost of not more than $30
million.
(V) Interruptible service
provided to the utility's electric customers.
(VI) Modification to, or amendment of,
existing power purchase agreements provided the modification or amendment does
not extend the agreement more than four years, does not add more than 30 MW of
capacity to the utility's system, and is cost effective in comparison to other
supply-side alternatives available to the utility.
(VII) Utility investments in emission control
equipment at existing generation plants.
(VIII) Utility administered demand-side
programs implemented in accordance with ยง
40-3.2-104, C.R.S.
(b) If the utility evaluates an
existing or proposed electric generation facility offered in a competitive
bidding process conducted outside of an approved resource plan, the utility
shall provide the owner or developer of the electric generation facility in
writing by e-mail the modeling inputs and assumptions that reasonably relate to
the facility or to the transmission of electricity from that facility to the
utility within 14 calendar days of the utility's decision to advance the
potential resource to computer-based modeling.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.