Fla. Admin. Code Ann. R. 64E-5.211 - Special Requirements for Issuance of Specific Licenses for Source Material Milling
In addition to the requirements set forth in Rule 64E-5.208, F.A.C., a specific license for source material milling will be issued if the applicant submits to the Department an application as described herein and meets the other conditions specified below:
(1) An application for a license to receive
title to, receive, possess and use source material for milling or by product
material as defined in Part I shall address the following:
(a) Description of the proposed project or
action;
(b) Area or site
characteristics including geology, topography, hydrology and
meteorology;
(c) Radiological and
nonradiological impacts of the proposed project or action, including waterway
and groundwater impacts;
(d)
Environmental effects of accidents;
(e) Long-term impacts including
decommissioning, decontamination and reclamation; and
(f) Site and project alternatives.
(2) The applicant shall not
commence construction of the project until the Department has weighed the
environmental, economic, technical and other benefits against the environmental
costs and has concluded that the issuance of the license is
appropriate.
(3) At least 1 full
year prior to any major site construction, a preoperational monitoring program
shall be conducted to provide complete baseline data on a milling site and its
environs. Throughout the construction and operating phases of the mill, an
operational monitoring program shall be conducted to measure or evaluate
compliance with applicable standards and regulations; to evaluate performance
of control systems and procedures; to evaluate environmental impacts of
operation; and to detect potential longterm effects.
(4) Prior to issuance of the license, the
applicant shall establish financial surety arrangements consistent with the
requirements of Rule
64E-5.217,
F.A.C.
(a) The amount of funds to be insured
by financial surety arrangements shall be based on cost estimates which are
furnished by the licensee and which the Department shall evaluate to determine
that the cost estimates are reasonably comparable to other decontamination or
decommissioning estimates in a plan for decontamination and decommissioning of
mill buildings and the milling site to levels which would allow unrestricted
use of these areas upon decommissioning, and the reclamation of tailings and
waste disposal areas. The licensee shall submit this plan in conjunction with
an environmental report that addresses the expected environmental impacts of
the milling operation, decommissioning and tailings reclamation, and that
evaluates alternatives for mitigating these impacts. In establishing specific
surety arrangements, the licensee's cost estimates shall take into account
total costs that would be incurred if an independent contractor were hired to
perform the decommissioning and reclamation work. In order to avoid unnecessary
duplication and expense, the Department may accept financial sureties that have
been consolidated with financial surety arrangements established to meet
requirements of other Federal or state agencies or local governing bodies for
such decommissioning, decontamination, reclamation and long-term site
surveillance, provided such arrangements are considered adequate to satisfy
these requirements and that portion of the surety which covers the
decommissioning and reclamation of the mill, mill tailings site and associated
areas, and the long-term funding charge are clearly identified. The licensee's
surety mechanism will be reviewed annually by the Department to assure that
sufficient funds will be available for completion of the reclamation plan if
the work had to be performed by an independent contractor. The amount of surety
liability should be adjusted to recognize any increases or decreases resulting
from inflation, changes in engineering plans, activities performed and any
other conditions affecting costs. Regardless of whether reclamation is phased
through the life of the operation or takes place at the end of operations, an
appropriate portion of surety liability shall be retained until final
compliance with the reclamation plan is determined. This will yield a surety
that is at least sufficient at all times to cover the costs of decommissioning,
decontamination and reclamation of the areas that are expected to be disturbed
before the next license renewal. The term of the surety mechanism must be open
ended, unless it can be demonstrated that another arrangement would provide an
equivalent level of assurance. This assurance could be provided with a surety
instrument which is written for a specified period of time which must be
automatically renewed unless the surety agent notifies the beneficiary, the
Department and the licensee prior to the renewal date of their intention not to
renew. In such a situation, the surety requirement still exists and the
licensee would be required to submit an acceptable replacement surety within a
brief period of time to allow at least 60 days for the Department to
collect.
(b) The total amount of
funds for reclamation or long term surveillance and control shall be
transferred to the United States if title and custody of such material and its
disposal site is transferred to the United States upon termination of a
license. Such funds include sums collected for long term surveillance and
control. Such funds do not, however, include monies held as surety where no
default has occurred and the reclamation or other bonded activity has been
performed.
(5) The
applicant shall provide procedures describing the means employed to meet the
following requirements during the operational phase of any project.
(a) Milling operations shall be conducted so
that all effluent releases are below the limits of Part III and are as low as
is reasonably achievable.
(b) The
mill operator shall conduct daily inspections of any tailings or waste
retention systems. Such inspections shall be conducted by a licensed engineer.
Records of such inspections shall be maintained for review by the
Department.
(c) The mill operator
shall immediately notify the Department of the following:
1. Any failure in a tailings or waste
retention system which results in a release of tailings or waste into
unrestricted areas, and
2. Any
unusual condition not contemplated in the design of the retention system which,
if not corrected, could lead to failure of the system and result in a release
of tailings or waste into unrestricted areas.
(6) Continued Surveillance Requirements for
Source Material Mills Having Reclaimed Residues.
(a) The final disposition of tailings or
wastes at source material milling sites should be such that the need for
ongoing active maintenance is not necessary to preserve isolation. As a
minimum, annual site inspections shall be conducted by the government agency
retaining ultimate custody of the site where tailings or wastes are stored to
confirm the integrity of the stabilized tailings or waste systems and to
determine the need, if any, for maintenance and monitoring. Results of the
inspection shall be reported to the U.S. Nuclear Regulatory Commission within
60 days following each inspection. The U.S. Nuclear Regulatory Commission may
require more frequent site inspections, if, on the basis of a site-specific
evaluation, such a need appears necessary due to the features of a particular
tailings or waste disposal system.
(b) A minimum charge of $405,000 to cover the
costs of long-term surveillance shall be paid by each mill operator to the
Department prior to the termination of a uranium or thorium mill license. If
site surveillance or control requirements at a particular site are determined,
on the basis of a site-specific evaluation, to be significantly greater than
those specified in (6)(a), above, additional funding requirements may be
specified by the Department. The total charge to cover the cost of long-term
surveillance shall be such that, with an assumed 1 percent annual real interest
rate, the collected funds will yield interest in an amount sufficient to cover
the annual costs of site surveillance. The charge will be assessed quarterly
and will be reviewed annually by the Department to recognize or adjust for
inflation.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.