(1) Applicability.
(a) No person shall construct, operate or
close an off-site construction and demolition debris disposal facility without
a permit issued by the Department. All holders of construction or operation
permits issued prior to January 6, 2010, that contain conditions not in
conformance with this chapter shall apply for modification of the permit to
conform to this chapter to the District Office of the Department that issued
the permit. The submission shall occur at the time of application for renewal
of an existing permit, or before July 5, 2010, whichever is earlier. For
purposes of this paragraph, a permit issued prior to January 6, 2010, is deemed
to include a completed permit application received by the Department prior to
January 6, 2010. However, the provisions of paragraph (4)(d) of this rule, will
not apply to any disposal units of a facility that have received a Department
permit authorizing construction or operation prior to January 6,
2010.
(b) After the applicable
compliance deadline specified above, facilities shall operate only in
accordance with the provisions of this section. However, any
disposal unit that
received a significant amount of waste in accordance with the conditions of its
permit prior to the applicable compliance deadline is not required to comply
with any siting or
construction design requirements of this chapter that were
not in effect prior to the applicable compliance deadline. For purposes of this
subsection:
1. A "significant amount of waste"
means that the disposal unit has received sufficient waste for disposal, in
accordance with its normal operational plan, so that it is impractical to
remove that waste or to relocate or reconstruct the disposal unit.
2. "Siting or
construction design
requirements" do not include the hydrogeological investigation required by
subparagraph
62-701.730(2)(a)
3., F.A.C., or the water quality monitoring plan required by subsection
62-701.730(8),
F.A.C.
(2)
Application. A permit application for an off-
site construction and demolition
debris disposal facility,
disposal unit, or
lateral expansion shall be
submitted on Form
62-701.900(6),
Application to Construct, Operate, or Modify a
Construction and Demolition
Debris Disposal or
Disposal with
Recycling Facility,
http://www.flrules.org/Gateway/reference.asp?No=Ref-05029,
effective date June 11, 2015, hereby adopted and incorporated by reference.
Copies of this form are available from a local District Office or by writing to
the
Department of Environmental Protection,
Solid Waste Section, MS #4565, 2600
Blair Stone Road, Tallahassee, Florida 32399-2400. The application shall be in
conformance with the requirements of subsections
62-701.320(5), (6),
(7), and paragraph (8)(a), F.A.C. All
applications shall include the information in paragraphs (b) through (f), of
this subsection, and applications to construct or laterally expand a
disposal
unit shall also include the information in paragraph (a), of this subsection.
(a) An engineering report, signed and sealed
by a
professional engineer, that includes:
1.
A site plan, of a scale not greater than 200 feet to the inch, which shows the
project location and identifies the proposed disposal units, total acreage of
the site and of the proposed disposal units, and any other relevant features
such as water bodies or wetlands on or within 200 feet of the site, and potable
water wells on or within 500 feet of the site,
2. A geotechnical investigation which meets
the criteria of rule
62-701.410, F.A.C.,
4. An estimate of the planned active life of
the facility, the design of the disposal areas, the final design height of the
facility, and the maximum height of the facility during its
operation,
5. Documentation that
the
facility location will comply with the requirements of paragraphs
62-701.730(4)(c) and
(d), F.A.C.
(b) A boundary survey, legal description, and
topographic survey of the property;
(c) An operation plan which describes how the
applicant will comply with subsection
62-701.730(7),
F.A.C., which must include procedures for emergency preparedness and response
as required in subsection
62-701.320(16),
F.A.C.;
(d) A
closure plan that
describes how the applicant will comply with subsections
62-701.730(9) and
(10), F.A.C.;
(e) The financial assurance documentation
required by subsection
62-701.730(11),
F.A.C.; and,
(f) The
CCA treated
wood management plan as required in subsection
62-701.730(20),
F.A.C.
(3) Certification.
Certification of
construction completion shall be done in accordance with
paragraph
62-701.320(9)(b),
F.A.C.
(4) General requirements.
Except as specified in this section, the requirements of rules
62-701.330 through
62-701.630, F.A.C., do not apply
to
construction and demolition debris disposal facilities.
(a) No solid waste other than construction
and demolition debris shall be disposed of at a construction and demolition
debris disposal facility.
(b) Waste
material from a waste processing facility which is mixed with Class I or Class
III waste, either before or after processing, is not considered construction
and demolition debris and may not be accepted for disposal at a construction
and demolition debris disposal facility.
(c) No solid waste disposal unit shall be
located in the 100-year floodplain where it will restrict the flow of the
100-year flood, reduce the temporary water storage capacity of the floodplain
unless compensating storage is provided, or result in a washout of solid
waste.
(d) For an above-grade
disposal facility, the minimum horizontal separation between the waste disposal
area and the site property boundary shall be 100 feet, measured from the toe of
the proposed final cover slope.
(e)
The horizontal boundaries of the waste disposal area authorized in the
construction or operation permit shall be clearly delineated with permanent or
semi-permanent markers, such as bollards, posts, fencing, or signs, so that the
operators can determine on a daily basis whether or not the facility is
exceeding its permitted dimensions.
(5) Stormwater. For aboveground disposal
units, the design of any features intended to convey stormwater to a permitted
or exempted treatment system shall be included in the solid waste construction
permit.
(6) Design requirements.
(a) Each new disposal unit, as well as each
lateral expansion of an existing disposal unit, that has not received a
Department permit authorizing construction or operation prior to July 1, 2010,
shall be constructed with a liner and leachate collection system, unless the
applicant demonstrates, based upon the types of waste received, methods for
controlling the types of waste disposed of, the proximity of ground water and
surface water, and the results of the hydrogeological and geotechnical
investigations including any ground water monitoring analyses, the operation of
the facility is not expected to result in violations of ground water standards
and criteria otherwise.
(b) The
liner system shall consist of at least a single 60-mil minimum average
thickness HDPE
geomembrane. In the sumps located inside the
disposal facility
footprint and in the
leachate collection trenches, the
geomembrane shall be
placed on a GCL with a saturated hydraulic conductivity of less than or equal
to 1 x 10-
7 cm/sec, or on a compacted clay
liner
which is a minimum six inches thick with a saturated hydraulic conductivity of
less than or equal to 1 x 10-
7 cm/sec. The
liner
shall be placed on a prepared
subgrade that will not damage the
geomembrane
liner or the GCL. A primary
leachate collection and removal system and a
drainage layer shall be installed above the
geomembrane liner. Except in sumps
and
leachate collection trenches, the system shall be designed to limit
leachate head above the
liner during routine
facility operation after placement
of
initial cover to no greater than 12 inches. The
liner system and
leachate
collection system must be constructed in accordance with the requirements of
paragraphs 701.400(3)(a), (d), (e), and (f), and subsections
62-701.400(4), (7), and
(8), F.A.C. Any alternative
liner system
shall be approved only in accordance with the provisions of rule
62-701.310, F.A.C.
(c) Leachate shall be managed in accordance
with subsection
62-701.500(8),
F.A.C. Any
leachate storage tanks or surface impoundments constructed or
operated at the
facility shall comply with the requirements of subsection
62-701.400(6),
F.A.C.
(7) Operation
requirements. Owners and operators of
construction and demolition debris
disposal facilities shall comply with the following requirements:
(a) An operation plan describing the facility
operations and maintenance, emergency and contingency plans, and types of
equipment that will be used shall be kept at the facility at all times and made
available for inspection. The operation plan shall describe the method and
sequence of filling waste and shall state the maximum allowed lift depth. Lift
depth shall not exceed 10 feet unless authorized in the operation plan. Lift
depths greater than 10 feet may be allowed depending on specific operations,
daily volume of waste, width of working face, and good safety practices. All
activities at the facility shall be performed in accordance with this plan and
the permit conditions. The plan shall be updated as operations change but no
less frequently than every five years. The operation permit shall be modified
to reflect any substantive changes to the plan, other than those required for
routine maintenance.
(b)
Construction and demolition debris shall be compacted and sloped during the
life of the facility to assure that the requirements of subsection (9) of this
rule can be met. A schedule for compaction and grading shall be included in the
operation plan. The external slopes of all disposal units shall be no greater
than three feet horizontal to one foot vertical rise. The working face and
internal slopes of all disposal units shall not be greater than three feet
horizontal to one foot vertical rise unless reasonable assurance is provided in
the operation plan that fires can be controlled in steeply sloped
areas.
(c) Access to the disposal
facility shall be controlled during the design period of the facility by
fencing or other effective barriers to prevent disposal of solid waste other
than construction and demolition debris. Signs indicating the name of the
operating authority, traffic flow, hours of operations and restrictions or
conditions of disposal shall be posted.
(d) Operators and spotters employed at the
facility shall be properly trained in accordance with subsection
62-701.320(15),
F.A.C. A trained
operator shall be on duty at the
facility at all times that
the
facility is operating. In addition, a sufficient number of spotters shall
be on duty at the
working face to inspect the incoming waste at all times waste
is being accepted at the
site. Waste shall be inspected after it is removed
from the transport vehicle and prior to placement for final
disposal. Any
unauthorized waste shall be removed from the waste stream and placed into
appropriate containers or secure storage areas for
disposal or
recycling at a
facility authorized by the
Department to receive such waste.
(e) The
facility shall be operated to control
objectionable odors in accordance with subsection
62-296.320(2),
F.A.C. If
objectionable odors are detected off-
site, the owner or
operator
shall comply with the requirements of paragraph
62-701.530(3)(b),
F.A.C.
(f) Fuels, solvents,
lubricants, and other maintenance materials shall be stored in secure areas
separate from the disposal or sorting areas.
(g) Plastic buckets may be accepted at the
facility unless they contain liquids other than water when they arrive;
however, they may contain hardened paint, tar, cement or similar non-hazardous
materials.
(h) Carpet remnants that
are from a construction or demolition project or from a carpet manufacturer may
be accepted at the facility.
(i)
CCA treated wood shall be managed as provided in subsection (20) of this
rule.
(j) If any regulated
hazardous wastes are discovered to be improperly deposited at the facility, the
facility operator shall promptly notify the Department, the person responsible
for shipping the wastes to the facility, and the generator of the wastes, if
known. The area where the wastes are deposited shall immediately be cordoned
off from public access. If the generator or hauler cannot be identified, the
facility operator shall assure the cleanup, transportation, and disposal of the
waste at a permitted hazardous waste management facility.
(k) The owner or operator shall make
arrangements or shall have equipment for temporary storage, handling and
transport to an authorized disposal or recycling facility for solid waste,
other than construction and demolition debris, that is inadvertently accepted
by the facility. Such solid waste that is accepted by the facility shall be
segregated and disposed of in accordance with chapter 62-701, F.A.C. Unless an
alternate schedule is included in an operation plan submitted with the permit
application, which provides for the control of odors and vectors, putrescible
waste shall not be stored for longer than 48 hours and non-putrescrible waste
shall not be stored for longer than 30 days. Any hazardous waste that is
received by the facility shall be managed in accordance with the provisions of
chapter 62-730, F.A.C.
(l) If a
disposal unit is constructed with a liner and leachate collection system, the
first layer of waste placed above the liner shall be a minimum of four feet in
compacted thickness and consist of selected wastes containing no large rigid
objects that may damage the liner or leachate collection
system.
(8) Water quality
monitoring. A water quality monitoring plan that meets the criteria set forth
in rule
62-701.510 and chapter 62-520,
F.A.C., shall be included with the permit application. This plan shall be
implemented and maintained by the owner or
operator, and shall include
provisions to provide the reports required by subsection
62-701.510(8),
F.A.C., with the following exceptions:
(a)
Unless a disposal unit is constructed or operated within 200 feet of a surface
water body, or unless site-specific conditions could reasonably be expected to
result in contaminants entering a surface water body, surface water sampling is
not required. For purposes of this paragraph, a surface water body does not
include a body of water contained completely within the property boundaries of
the disposal site that does not discharge from the site to surface
waters.
(b) The well spacing
requirements of subparagraph
62-701.510(3)(d)
3., F.A.C., do not apply. A minimum of one upgradient and two downgradient
wells is required, as specified in chapter 62-520, F.A.C.
(c) Detection wells, and compliance wells if
applicable, shall be sampled and analyzed at least semi-annually for the
following parameters:
Field Parameters
|
Laboratory Parameters
|
pH
|
Aluminum
|
Turbidity
|
Chlorides
|
Temperature
|
Nitrate
|
Specific conductivity
|
Sulfate
|
Dissolved oxygen
|
Total dissolved solids (TDS)
|
Water elevations
|
Iron
|
Colors and sheens
|
Sodium
|
(by observation)
|
Arsenic
|
|
Cadmium
|
Chromium
|
Lead
|
Mercury
|
Total ammonia - N
|
Xylenes
|
Those parameters listed in EPA Methods 601 and
602
|
(d)
Background water quality shall be established in accordance with the provisions
of paragraph
62-701.510(5)(b),
F.A.C., except that the analysis shall also include sulfate and aluminum. In
addition, all background and detection wells shall be sampled and analyzed at
least once every five years for those parameters listed in paragraph
62-701.510(7)(a),
F.A.C., as well as sulface and aluminum.
(e) The owner or operator of the facility may
request a permit modification from the appropriate District Office of the
Department to delete specific laboratory parameters or field parameters from
routine analyses of detection or compliance wells and surface water. The
Department will grant a request for a permit modification upon a demonstration
that these parameters are not reasonably expected to be in or derived from the
waste which ws received or disposed of at the facility.
(f) If monitoring parameters are detected in
monitoring wells in concentrations which are significantly above background
water quality, or which are at levels above the
Department's water quality
standards or criteria specified in chapter 62-520, F.A.C., the provisions of
subsection
62-701.510(6),
F.A.C., shall apply.
(9)
Closure.
(a) At least 90 days prior to the
date when wastes will no longer be accepted, the owner or operator of the
construction and demolition debris disposal facility shall submit an updated
closure plan to the Department to reflect any changes in the closure plan due
to actual operational conditions at the facility. If unforeseen circumstances
do not allow the notification within 90 days prior to ceasing to receive
wastes, then notice shall be provided as soon as the need to close the facility
becomes apparent. The updated and approved closure plan shall be incorporated
into and made part of the permit.
(b) Final cover and seeding or planting of
vegetative cover shall be placed on each
disposal unit within 180 days after it
has reached its final grade or ceased receiving wastes.
Final cover shall
consist of a 24-inch-thick soil layer, or a 30-inch thick layer consisting of
approximately 50 percent soil and 50 percent ground or chipped
yard trash by
volume, the upper six inches of which shall be capable of supporting
vegetation, and shall be graded and compacted as necessary to eliminate
ponding, promote drainage, and minimize erosion. If any
disposal unit has been
constructed with a
liner system, the
final cover must include a barrier layer
with a permeability that is substantially equivalent to, or less than, the
permeability of the bottom
liner system or meets the alternative barrier layer
design requirements in subparagraph
62-701.600(3)(g)
6., F.A.C. The side slopes of all above-grade
disposal units shall be no
greater than three feet horizontal to one foot vertical rise. If the
disposal
unit is lined, the
closure design shall include a barrier layer or other
measures to ensure that the design
leachate head over the
liner is not exceeded
after
closure. The
final cover shall be vegetated to control erosion.
Disposal
units that are aboveground shall be designed to control the flow of stormwater,
such as building reverse sloping benches or terraces into the side slopes of
the
disposal units and shall contain down slope drainage ways with water flow
energy dissipaters unless
reasonable assurance is provided that adequate
erosion control will be achieved in the absence of such measures.
(c) Any disposal unit designed with a
geomembrane as part of the barrier layer shall have a gas management system
installed during closure that is designed to reduce gas pressure in the
interior of the disposal unit and to prevent failure of the final cover. The
gas management system may be active or passive. An active system shall be
designed and operated in a manner that prevents intrusion of ambient air into
the disposal unit.
(d) Placement of
final cover may be delayed if additional waste will be deposited on the
disposal unit within five years, but only if the
disposal unit is temporarily
closed in accordance with an approved
closure plan. Conditions of temporary
closure shall include:
1. The disposal unit
was constructed in compliance with its permit conditions,
2. A schedule for temporary and final closure
is shown in the closure plan,
3.
Final cover is installed on side slopes of each completed disposal unit which
will not receive additional waste,
4. Odors and runoff are controlled,
5. The closure cost estimate takes
into account the costs of temporary closure as well as the costs of the final
closure; and,
6. An intermediate
cover is installed on the disposal unit within 30 days after the unit stops
accepting waste. The intermediate cover may be removed before placing
additional waste or installing final cover.
(e) The owner or
operator shall provide a
certification of
closure construction completion to the
Department within 30
days after
closing, covering, and seeding the
disposal unit. The owner or
operator shall also provide a final survey report done by a professional
surveyor, in accordance with paragraph
62-701.600(6)(b),
F.A.C., if
disposal operations have raised the final elevations higher than 20
feet above the natural land surface.
(f) Upon receipt and approval of the
documents required in paragraph (d), of this subsection, the
Department shall,
within 30 days, acknowledge by letter that notice of termination of operations
and
closing of the
facility has been received. The date of this letter shall be
the official date of
closing for the purpose of determining the long-term care
period, in accordance with subsection
62-701.600(8),
F.A.C.
(g) Declaration to the
public. After closing operations are approved by the Department, the facility
owner or operator shall file a declaration to the public in the deed records in
the office of the county clerk of the county in which the facility is located.
The declaration shall include a legal description of the property on which the
facility is located and a site plan specifying the area actually filled with
construction and demolition debris. The declaration shall also include a notice
that any future owner or user of the site should consult with the Department
prior to planning or initiating any activity involving the disturbance of the
facility's cover, monitoring system or other control structures. A certified
copy of the declaration shall be filed with the Department.
(10) Long-term care. The owner or
operator of
the
construction and demolition debris disposal facility shall continue to
monitor and maintain the integrity and effectiveness of the
final cover as well
as other appurtenances of the
facility, control erosion,
fill subsidences,
control
objectionable odors, implement an odor remedication plan that meets the
requirements of paragraph
62-701.530(3)(b),
F.A.C., if required, and comply with the water quality monitoring plan for five
years from the date of
closing. Before the expiration of the long-term care
monitoring and
maintenance period, the
Department may extend the time period if
the water quality monitoring system indicates that the
facility continues to
impact water quality at concentrations which may be expected to result in
violations of
Department water quality standards or criteria; if
site-specific
conditions make it likely that any contamination that may emanate from the
disposal area would not be detected within the long-term care period; if the
final cover does not have well established vegetation or is showing signs of
continuing significant erosion problems; or if the permittee has not performed
all required monitoring or
maintenance.
(11) Financial assurance.
(a) Closure cost estimates, estimate updates
and financial mechanisms shall comply with the provisions of subsections
62-701.630(1) through
(4), F.A.C., except that the cost of
long-term care shall be based upon a five-year period, and the costs shall be
based upon compliance with this section.
Landfill shall mean
facility.
(b) If a local government
requires financial assurance for closure, which is at least as stringent as
that required by this rule, the Department will attempt to establish a
cooperative mechanism with the local government and thereby avoid duplicative
financial requirements.
(c) Owners
or operators of facilities that are required to undertake a corrective action
program in accordance with paragraph
62-701.730(8)(f),
F.A.C., shall submit proof of financial assurance to the
Department in
accordance with subsections
62-701.630(7), (8) and
(9), F.A.C., no later than 120 days after the
corrective action remedy has been selected.
(d) If long-term care is extended because the
permittee has failed to perform all required monitoring and maintenance, during
the long-term care period, financial assurance shall continue to be required
during the extended long-term care. If the long-term care is extended for any
other reason, financial assurance is not required during the extended long-term
care period, except as may be required in paragraph (c), of this
subsection.
(12) Annual
Reports. The owner or
operator of the
facility shall submit an annual report to
the
Department on Form
62-701.900(7).
This report shall include a summary of the amounts and types of wastes disposed
of or recycled. The county of origin of materials that are recycled, or a
statement that the county of origin is unknown, shall be included in the
report. The report shall be submitted no later than February 1 of each year and
shall cover the preceding calendar year.
(13) Recycling.
(a) The owner or
operator of a
facility that
accepts
construction and demolition debris for
disposal and that also recovers
materials from the
construction and demolition debris waste stream for purposes
of
recycling shall meet the requirements of this section as well as the
requirements of rule
62-701.710, F.A.C. If there is a
conflict between this section and rule
62-701.710, F.A.C., this section
shall govern. It is not necessary for the owner or
operator to apply for a
separate permit as a waste
processing facility or to pay an additional
fee.
(b) The owner or
operator of a
facility that recovers materials from the
construction and demolition debris
waste stream for purposes of
recycling but that does not dispose of any wastes
on-
site shall apply for a permit on Form
62-701.900(4),
and shall comply with the provisions of rule
62-701.710, F.A.C.
(c) In order to reuse recovered screened
material other than clean debris from the construction and demolition debris
waste stream, an owner or operator shall demonstrate that this material will be
managed and reused in a manner that will pose no significant threat to public
health or the environment. In making this demonstration, the owner or operator
may consider background levels of receiving soils, whether the material will be
blended with other materials, and the likelihood that the material may have
unlimited distribution or come into direct contact with the public. Examples of
management practices which would not require analysis for health-based criteria
include permanent encapsulation, use as initial or intermediate cover or
subsurface construction at a permitted landfill, or use under at least two feet
of clean cover material.
(d) Metal,
paper, glass, plastic, textile, or rubber materials that have been diverted and
source separated or have been removed from the construction and demolition
debris waste stream for sale, use, or reuse as raw materials may be managed as
recovered materials. Other materials that have been diverted and source
separated or have been removed from the construction and demolition debris
waste stream may be sold, used, or reused as raw materials upon a demonstration
that the material will pose no significant threat to public health or the
environment.
(e) The owner or
operator of any permitted
materials recovery or
disposal facility that accepts
dedicated loads of
construction and demolition debris shall ensure that such
materials are processed, to the extent economically feasible, to remove
recyclable materials prior to
disposal. The owner or
operator of such a
facility shall evaluate the economic feasibility of
processing to remove
recyclable materials prior to
disposal, and shall certify that they have
evaluated the economic feasibility for
processing construction and demolition
debris. The certification shall indicate the economic factors that were
considered in the evaluation, the types of
construction and demolition debris
materials that were evaluated, and whether it was determined that
processing to
remove recyclable materials prior to
disposal was economically feasible. The
evaluation and certification shall be documented on Form
62-701.900(36),
Certification of Economic Feasibility to Process C&D Debris Prior to
Disposal, effective date March 13, 2016,
http://www.flrules.org/Gateway/reference.asp?No=Ref-06527,
hereby adopted and incorporated by reference. Copies of this form are available
from a local District Office or by writing to the
Department of Environmental
Protection,
Solid Waste Section, MS #4565, 2600 Blair Stone Road, Tallahassee,
Florida 32399-2400. This certification shall be completed no later than
September 9, 2016 for existing facilities, or prior to operating a new
facility
on or after March 13, 2016. Thereafter, the evaluation and certification shall
be completed at least annually. Where an owner or
operator becomes aware of
changed conditions that they believe warrant discontinuing
processing to remove
recyclable materials prior to
disposal, the owner or
operator may temporarily
discontinue such
processing for a period of up to 12 months; however, such
changed conditions shall be incorporated in the next evaluation and
certification on Form
62-701.900(36).
Documentation of each evaluation and certification shall be kept at the
facility and made available to the
Department upon request, along with
supporting documentation for the items considered in the course of the economic
evaluation. If the owner or
operator determines that it is economically
feasible to process some or all of a material being accepted, but the material
currently is not being processed, then such material shall be processed prior
to
disposal to remove the fraction of the
recyclable material to the extent
economically feasible no later than three months after completion of any
process changes that were identified by the owner or
operator as part of the
associated economic feasibility evaluation. Reporting the amounts of any
recovered materials separated from the waste stream shall continue to be
provided in accordance with the requirements of chapter 62-722, F.A.C. Other
than the referenced provisions of chapter 62-722, F.A.C., this paragraph does
not apply to:
1. Recovered
materials,
2. Materials that have
previously been source-separated and offered for recycling,
3. Materials that have been previously
processed to remove recyclable materials, or
4. Off-
site disposal of
yard trash authorized
in accordance with rule
62-701.803,
F.A.C.
(14)
Incineration. A
facility that employs an air curtain incinerator and that also
stores or disposes of
construction and demolition debris at the
site shall meet
the permitting requirements of rule
62-256.700, F.A.C., as well as
this section.
(15) Clean debris.
Clean debris may be used as fill or raw material in any area, including waters
of the State, subject to receipt of an environmental resource permit from the
Department where applicable. Clean debris used as fill material is not solid
waste, and such use does not require a solid waste permit under this
rule.
(16) Landfill disposal.
Construction and demolition debris may be disposed of in a permitted
landfill.
However, each county must maintain segregated
disposal areas for
construction
and demolition debris. The cover requirements for a segregated
construction and
demolition debris disposal area within a permitted
landfill shall be those in
subsection (9) of this rule. Landfills permitted in accordance with rule
62-701.330, F.A.C., which have
construction and demolition debris disposal units or
recycling facilities
included as part of their permit conditions, are not required to submit
separate permit applications or financial assurance documents under this
section.
(17) Onsite disposal.
Construction and demolition debris that is disposed of on the property where it
is generated, or on property that is adjacent or contiguous to and under common
ownership and control as that property where the waste is generated, is exempt
from the requirements of this section and rule
62-701.330, F.A.C. However, such
disposal is subject to the prohibitions of rule
62-701.300, F.A.C. All waste
shall be inspected by the generator or a spotter prior to
disposal, either at
the point of
generation or at the
disposal site, to ensure that any
unauthorized waste is removed from the waste stream prior to
disposal and
managed in accordance with
Department rules.
Final cover and seeding or
planting of vegetative cover shall be placed on each
disposal unit within 180
days after final receipt of waste.
Final cover shall consist of a 24-inch-thick
soil layer, the upper six inches of which shall be capable of supporting
vegetation, and shall be graded and compacted as necessary to eliminate
ponding, promote drainage, and minimize erosion. The side slopes of all
above-grade
disposal areas shall be no greater than three feet horizontal to
one foot vertical rise.
(18)
Disposal restrictions. Construction and demolition debris may be disposed of
only in accordance with one of the methods authorized above. In addition,
disposal areas shall be operated so that adverse environmental and public
health impacts, such as blowing litter and vectors, are minimized. Upon
discovery that a permitted facility has disposed of solid waste outside of its
permitted dimensions, the owner or operator shall notify the Department within
three working days of this discovery. If all waste is not relocated within the
permitted dimensions of the facility within 30 days of discovery, upon order of
the Department the facility shall not accept any waste until the facility is in
compliance with its permitted dimensions.
(19) Asbestos waste
disposal.
Asbestos-containing waste materials regulated pursuant to 40 C.F.R. Part
61, Subpart M, shall not be disposed of in a
construction and demolition debris
disposal unit.
(20) CCA treated
wood. The owner or operator of a facility, except for a disposal facility with
a constructed liner system, shall design and implement a CCA treated wood
management plan. The plan shall be designed to minimize the amount of CCA
treated wood that is delivered to the facility, and must describe procedures
the operator will use to make a reasonable effort to separate any CCA treated
wood from other wastes at the facility. CCA treated wood that is separated from
other wastes at the facility shall not be disposed of at an unlined solid waste
disposal facility.
(21) Alternate
procedures. The owner or
operator of a
facility may request alternate
procedures and requirements in accordance with rule
62-701.310, F.A.C. However, if
such request is based upon the nature of the
construction and demolition debris
accepted at the
facility (for example, if a
facility accepts only segregated
wastes which are expected to have a minimal environmental impact), the request
will be submitted to and acted on by the appropriate District office of the
Department, and need not be accompanied by any additional
fee.