Idaho Admin. Code r. 13.01.19.101 - APPLICATION
01.
Form. Applications will be
on a form prescribed by the Department. (3-31-22)
02.
Department Review. (3-31-22)
a. Application Review. The Department will
evaluate and determine approval or denial of vendor applications quarterly, on
or before March 1, June 1, September 1, and December 1. The Department will
have thirty (30) calendar days after receipt of all necessary forms to review
and investigate the application. The date received plus thirty (30) days will
determine into which quarterly evaluation each vendor application will be
considered. Applications from the same area will be compared to determine which
will best meet vendorship needs in that area. Exceptions may be made by the
Department when there are overriding needs for an immediate replacement of a
license vendor in an area. This will primarily occur where there would be no
vendor services available to the public within a twenty-five (25) mile radius.
(3-31-22)
b. Field Review. After
the License Section has received the application form and all other required
information from an applicant, they will contact the Regional Conservation
Officer for a recommendation on the application. The Regional Conservation
Officer will have ten (10) days to provide the License Section with a
recommendation on the application. (3-31-22)
03.
Applicant. (3-31-22)
a. Application. The Department will only
consider license vendorship applications completed in their entirety and
accompanied by an original copy of a current credit rating from a recognized
credit bureau. The Department will only consider completed applications
received by the License section no later than sixty (60) days after the date of
the application transmittal letter. The Department may grant an applicant's
request to extend this period for up to thirty (30) additional days. Any false
or misleading response will void the application. (3-31-22)
b. Approved Application. If the Department
approves an application, the applicant will have sixty (60) days from the date
of the applicant's approval letter to provide the Department with a signed
vendorship contract, and any bond, deposit, or documentation the Department may
require. Failure to meet this deadline will void the approval except for
extenuating circumstances approved by the Department.
(3-31-22)