Idaho Admin. Code r. 58.01.01.225 - PERMIT TO CONSTRUCT PROCESSING FEE
A permit to construct processing fee, calculated by the
Department pursuant to the categories provided in the following table, must be
paid to the Department by the person receiving the permit. The applicable
processing fee category is determined by adding together the amount of
increases of regulated pollutant emissions and subtracting any decreases of
regulated pollutant emissions as identified in the permit to construct. The fee
calculation does not include
PERMIT TO CONSTRUCT CATEGORY |
FEE |
|
$500 |
New |
$1,000 |
New |
$2,500 |
New |
$5,000 |
Nonmajor new |
$7,500 |
New major |
$10,000 |
Permit modifications where no engineering analysis is required |
$250 |
Application submittals for exemption applicability determinations, typographical errors, and name and ownership changes as described in Subsections 224.01, 224.02, 224.03 |
$0.00 |
(3-28-23)