620.250 - Groundwater Management Zone
a)
Within any class of groundwater, a groundwater management zone (GMZ) may be
established as a three-dimensional region containing groundwater being managed
to mitigate impairment caused by the release of one or more contaminants that
is subject to a corrective action process approved by the Agency.
b) Before a GMZ may be established, the owner
or operator of a site at which there has been a release of one or more
contaminants to groundwater must submit to the Agency a GMZ application. The
application must contain the information required by Section 620.Appendix D,
Parts I, II, and III, as well as any other information requested in writing by
the Agency that is relevant to its review under subsection (c).
1) If the GMZ would extend off-site, the GMZ
application must include each off-site property owner's written permission to
the establishment of the GMZ on its property. If effectively implementing the
off-site portion of the GMZ requires accessing an off-site property, the GMZ
application must also include the off-site property owner's written permission
for that access. If the applicable written permission or permissions from an
off-site property owner are not obtained - whether permission to establish the
GMZ off-site, access the off-site property, or both - the GMZ will not include
that off-site property.
2) Nothing
in this subsection (b) precludes the owner or operator from including
additional information in its GMZ application.
3) Nothing in this subsection (b) requires
that a GMZ application be in the form specified in Section 620.Appendix D,
Parts I, II, and III.
c)
The Agency must review each GMZ application submitted under subsection (b) and
issue a written determination approving or rejecting the GMZ.
1) In determining whether to approve a GMZ,
the Agency must consider the substantive information provided in support of the
GMZ, the technical sufficiency of the GMZ, the likelihood that the GMZ will
protect public health and the environment, and the likelihood that the GMZ's
corrective action process will, in a timely manner, result in compliance with
the applicable standards specified in Section
620.410,
620.420,
620.430, or
620.440 or otherwise minimize
exceedances to restore beneficial use as appropriate for the class or classes
of groundwater. If the Agency rejects a GMZ, the Agency must, in its written
determination, specify the reasons for the rejection.
2) A GMZ is established when the Agency
issues a written determination approving the GMZ, including its corrective
action process. Once a GMZ is established and before the corrective action is
complete, the Agency may, as new information warrants and subject to the
standards of subsection (c)(1), issue written determinations amending any part
of the GMZ, including its size, the contaminants that are subject to it, and
its corrective action process, as provided in this subsection (c)(2). A GMZ is
amended when the Agency issues a written determination amending the GMZ. If the
Agency rejects a submittal of the site owner or operator to amend the GMZ under
subsection (c)(2)(i) or (c)(2)(ii), the Agency must do so in a written
determination that specifies the reasons for the rejection.
i) The Agency may issue a written
determination directing that the site owner or operator submit to the Agency a
written proposal to amend the GMZ, consistent with subsection (b). The Agency's
determination must identify the amendment to be proposed and specify the
reasons why the amendment is necessary. If the owner or operator fails to
submit a proposal or the Agency rejects the proposal, the Agency may terminate
the GMZ under subsection (f) either on its own initiative or at the written
request of the owner or operator.
ii) If it wishes to have the Agency amend the
GMZ, the site owner or operator must submit to the Agency a written proposal to
amend the GMZ, consistent with subsection (b). If the Agency rejects the
proposal, the Agency may terminate the GMZ under subsection (f) either on its
own initiative or at the written request of the owner or operator.
d) When it completes
the corrective action under subsection (c)(2), the site owner or operator must
submit to the Agency a written demonstration that complies with subsection
(d)(1) or (d)(2) and contains the information required by the completion
certification specified in Section 620.Appendix D, Part IV. The Agency must
review this demonstration and issue a written determination approving or
rejecting the demonstration. Nothing in this subsection (d) requires the owner
or operator to make the demonstration using any specific type of documentation
or precludes the owner or operator from including additional information in the
demonstration.
1) The owner or operator must
demonstrate that it has completed the corrective action under subsection (c)(2)
and the applicable standards of Subpart D, as specified in Section
620.450(a)(4)(A),
have been attained in groundwater within the GMZ. If the Agency approves this
demonstration, the Agency must issue a written determination to that effect in
which the Agency terminates the GMZ. The termination takes effect when the
Agency issues this determination. If the Agency rejects this demonstration, the
Agency must, in its written determination, specify the reasons for the
rejection, which may include the Agency's basis for amending the GMZ to require
additional corrective action under subsection (c)(2).
2) The owner or operator must demonstrate
that it has completed the corrective action under subsection (c)(2) and
concentrations of released chemical constituents, as specified in Section
620.450(a)(4)(B),
remain in groundwater within the GMZ. The owner or operator must also
demonstrate compliance with Section
620.450(a)(4)(B)(i) and
(ii), as well as the on-going adequacy of
controls, management, or both, as applicable, to maintain compliance with
Section 620.450(a)(4)(B)(i) and
(ii). If the Agency approves this
demonstration, the Agency must issue a written determination to that effect in
which the Agency states that the GMZ remains in effect. If the Agency rejects
this demonstration, the Agency must, in its written determination, specify the
reasons for the rejection, which may include the Agency's basis for amending
the GMZ to require additional corrective action under subsection
(c)(2).
e) Within five
years after the Agency issues a written determination approving a demonstration
under subsection (d)(2), the site owner or operator must submit a report to the
Agency demonstrating the on-going adequacy of controls, management, or both, as
applicable, to maintain compliance with Section
620.450(a)(4)(B)(i) and
(ii). The Agency must review the report and
issue a written determination approving or rejecting the demonstration.
1) The submittal of these reports by the
owner or operator and the corresponding issuance of these written
determinations by the Agency must occur at least every five years while the GMZ
remains in effect. If the Agency rejects a demonstration, the Agency must, in
its written determination, specify the reasons for the rejection, which may
include the Agency's basis for amending the GMZ to require additional controls
or management under this subsection (e).
2) Any amendment to controls or management
under this subsection (e) is subject to the amendment provisions of subsection
(c)(2), except that the standard for the Agency's determination is whether the
controls or management, as amended, would be adequate to maintain compliance
with Section 620.450(a)(4)(B)(i) and
(ii)
f) Without limiting any other legal authority
of the Agency to terminate a GMZ, the Agency may issue a written determination
terminating a GMZ based on any of the grounds specified in this subsection (f).
The determination must specify the grounds for terminating the GMZ. The
termination takes effect when the Agency issues this determination. The Agency
may terminate a GMZ if:
1) The site owner or
operator fails to perform or comply with the schedule for any part of the GMZ,
including its corrective action under subsection (c)(2) or its controls or
management under subsection (d)(2) or (e);
2) The Agency rejects a proposal to amend the
GMZ under subsection (c)(2) or a demonstration under subsection (d) or
(e);
3) The site owner or operator
commits fraud or misrepresentation in any submittal under subsection (b),
(c)(2), (d), or (e);
4) The site
owner or operator submits to the Agency a written request to terminate the GMZ
under subsection (c)(2); or
5) The
Agency, after issuing a written determination approving a demonstration under
subsection (d)(2), determines that
i) The
applicable standards specified in Section
620.410,
620.420,
620.430, or
620.440 have been attained in
groundwater within the GMZ; or
ii)
Additional corrective action is necessary because controls and management are
no longer adequate to maintain compliance with Section
620.450(a)(4)(B)(i) and
(ii).
g) Upon GMZ termination under subsection (f),
the groundwater within the three-dimensional region formerly encompassed by the
GMZ becomes both designated as one of the four classes of groundwater specified
in Section 620.201(a) and
subject to the standards for the applicable class of groundwater specified in
Section 620.410,
620.420,
620.430, or
620.440.
h) Regardless of subsections (a) through (c),
a "groundwater management zone", as defined in 35 Ill. Adm. Code
740.120, may be established
under 35 Ill. Adm. Code
740.530 for sites in the Site
Remediation Program (35 Ill. Adm. Code 740). A GMZ established under 35 Ill.
Adm. Code 740.530 remains in effect until
any condition of 35 Ill. Adm. Code
740.530(c) is
met.
i) While a GMZ established
under 35 Ill. Adm. Code
740.530 is in effect, the
otherwise applicable standards of Subpart D of this Part do not apply to the
"contaminants of concern", as defined in 35 Ill. Adm. Code
740.120, for which groundwater
remediation objectives have been approved under 35 Ill. Adm. Code
740.
j) Regardless of subsection
(d), that subsection's submittal and review requirements concerning the
demonstration when corrective action is complete do not apply to a GMZ under 35
Ill. Adm. Code 740.530. Regardless of
subsection (e), that subsection's submittal and review requirements concerning
the on-going adequacy of controls and management do not apply to groundwater
within a three-dimensional region formerly encompassed by a GMZ established
under 35 Ill. Adm. Code
740.530 while a No Further
Remediation Letter issued under 35 Ill. Adm. Code 740 is in effect.
k) The Agency must develop and maintain a
list of all GMZs that have not been terminated. The list must identify the
location of each GMZ. On its website (https://epa.illinois.gov), the Agency
must post the list and, at least annually, update it. In addition, at least
annually, the Agency must submit the list to the Board for publication in the
Environmental Register.
l) In
groundwater regulated under 35 Ill. Adm. Code 845, a GMZ is not available to
address any exceedance of a groundwater protection standard specified in 35
Ill. Adm. Code 845.600(a) or
(b) (see 35 Ill. Adm. Code
845.600(c)).
Notes
Amended at 21 Ill. Reg. 7869, effective July 1, 1997
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.