Ill. Admin. Code tit. 35, § 704.188 - Plugging and Abandonment
Any permit must include a requirement that, after a cessation
of operations of two years, the owner or
a) It provides notice to the Agency;
and
b) It describes actions or
procedures satisfactory to the Agency that the owner or operator will take to
ensure that the well will not endanger USDWs during the period of temporary
abandonment. These actions and procedures must include compliance with the
technical requirements applicable to active injection wells, unless waived by
the Agency.
BOARD NOTE: Derived from 40 CFR 144.52(a)(6) (2005).