a)
Groundwater collected in the groundwater collection trench must be directed to
an outfall for which the Hutsonville Power Station has NPDES authorization or
to another option as approved by the Agency in the closure plan or post-closure
care plan in accordance with applicable law, including, but not limited to,
permit requirements.
b) The
groundwater discharge system must be constructed according to a construction
quality assurance program that meets the requirements of Section
840.146
of this Subpart.
c) Plans for the
groundwater discharge system, including, but not limited to, a plan for
operation and maintenance, must be approved by the Agency in the closure
plan.