Ill. Admin. Code tit. 44, § 8.3050 - Public Notice
a) With the
exception of contracts with an estimated basic professional fee of less than
$25,000, whenever CDB requires the services of an A/E or land surveyor, CDB
shall submit to the CPO a notice of the need for services, also known as an
RFP, for publication in the Bulletin. In addition, CDB may publish a list of
projects whose contract values do not exceed $25,000. The CPO shall publish in
the Bulletin any notice that meets the requirements of this Part.
b) When the services of a CM are required,
CDB shall publish a request for proposals setting forth the nature of the
projects.
c) The public notice
shall include an abstract of the services required for each project, a
description of each project, and the required expertise of the A/E or CM to be
considered. The public notice shall also include the statement of
qualifications form to be completed for each project, as well as the date and
time by which submittal of the statement of qualifications will be
accepted.
d) Notice shall be posted
in CDB's Procurement Bulletin and may be published in the official State
newspaper or otherwise made available in print. CDB may also publish the notice
in related construction industry service publications.
e) In addition to the other requirements of
this Section, a request for proposal for CM services will also be mailed to
each vendor prequalified under Section 33-10 of the Code. When CDB establishes
additional criteria for special projects under 44 Ill. Adm. Code
900.140
(Prequalification of Construction Managers), the notice shall be published at
least 30 days before the date the special prequalification application or the
statement of qualifications is due.
f) The public notice shall be published at
least 14 days prior to the date for submittal of the statement of
qualifications.
g) CM
prequalification standards may be revised to be more closely related to the
needs or environment of the special project, e.g., required vendor and/or
personnel experience may be limited to a particular size of project or to
experience in a particular environment, such as correctional facility
work.