Ill. Admin. Code tit. 89, § 313.6 - Community Services Program Plan
a) Area Projects funded by the Department to
provide community services shall, within 180 days of notification of initial
funding and 45 days prior to contract renewal in subsequent years, submit a
community services program plan to the Department and the appropriate Regional
Youth Planning Committee.
b) Each
community services program plan shall incorporate the previously submitted
application and also include:
1)
Documentation as to how the services will achieve the program goals and
objectives in accordance with the community needs assessment and available
resources.
2) Procedures which
describe how the following functions will be carried out:
A) community organizing
B) advocacy services
C) direct services
3) A plan which details a time-line for
implementation of the procedures stated in subsection (b)(2) above.
4) Staffing patterns and job
descriptions.
5) Personnel
policies.
6) Procedures for
development, award and monitoring of subcontracts.
7) Fiscal record keeping.
8) Reporting procedures and documentation of
programs towards goals and objectives.
9) A plan for monitoring of working
agreements and network activities.
10) A plan to recruit, screen and train
volunteers accompanied by a method of record keeping for activities performed
by volunteers.
11) A financial
development and fund raising plan which ensures that on-going attempts are made
to generate resources from potential public and private sources.
12) An affirmative action plan, if
necessitated by state or federal statutes or regulations.
13) A plan for staff development including
staff training plans sponsored by the Area Project and participation in
Department/Division training workshops.
14) listings of the service brokerage
agreements for referral.
15)
listings of the criteria for admission/discharge of a youth from the
program.
16) appeal procedures for
clients which are clear and comprehensive.
c) Plans will be rejected which are not
clear, comprehensive, and sufficiently detailed relative to the components in
Section 313.6(b)(10)-(15). Area Projects will be allowed 90 days to revise the
plan for reconsideration. During this 90-day period the Department will not
award a grant to another entity as Area Project for the geographic area in
question, which award would preclude granting a subsequent award to the entity
granted the additional time to revise its plan.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.