Ill. Admin. Code tit. 92, § 810.80 - Determination of Project Potential
Current through Register Vol. 46, No. 15, April 8, 2022
a) Following the thirty day review period,
the Department will use the line analysis and the record of written and oral
public comments to reevaluate and, if necessary, amend its project
analysis.
b) Eligible projects will
be contractually funded in the order that the applicant submits completed
acquisition of right-of-way agreements, railroad service agreements, and
additional funding agreements, if necessary, and as funds are available. No
eligible project will receive a loan or grant unless 100% funding is available
to ensure project completion.