Part 467 - ELECTRIC INTERCONNECTION OF LARGE DISTRIBUTED GENERATION FACILITIES
- § 467.10 - Scope
- § 467.20 - Definitions and Incorporations by Reference
- § 467.30 - Waiver
- § 467.40 - Technical Standards
- § 467.45 - Pre-Application Report
- § 467.50 - Interconnection Request Review
- § 467.60 - General Requirements
- § 467.70 - Interconnection Review Procedures
- § 467.80 - Disputes
- § 467.90 - Records
- Appendix A - Certificate of Completion, version 9
- Appendix B - Application, version 5
- Appendix C - Contract, version 3
- Appendix D - Interconnection Feasibility Study Agreement, version 3
- Appendix E - Interconnection System Impact Study Agreement, version 2
- Appendix F - Interconnection Facilities Study Agreement, version 2
Current through Register Vol. 45, No. 52, December 27, 2021
Notes
Adopted at 34 Ill. Reg. 3515, effective March 1, 2010.
AUTHORITY: Implementing Section 16-107.5 of the Public Utilities Act [ 220 ILCS 5/16-107.5] and authorized by Sections 16-107.5 and 10-101 of the Public Utilities Act [ 220 ILCS 5/16-107.5 and 10-101].