312 IAC 22.5-2-5 - Completion of review and effective date of authorization
Authority: IC 14-21-1-25; IC 14-21-1-31
Affected: IC 4-21.5; IC 14-9-4; IC 14-21-1
Sec. 5.
(a) The
division shall conclude its review of the development plan within sixty (60)
days of the receipt of a completed application. Upon the conclusion of review,
the division may approve, condition, or deny the application.
(b) The effective date and administrative
review of an authorization under this rule are governed by IC 4-21.5 and
312 IAC
3-1.