312 IAC 29-33-19 - Approved materials for filling intervals between plugs

Authority: IC 14-10-2-4; IC 14-37-3

Affected: IC 14-37

Sec. 19.

(a) This section establishes requirements for filling intervals between plugs required under this rule.
(b) Unless specified otherwise, the uncemented intervals between any plugs required under this rule may be filled with:
(1) pea gravel;
(2) crushed rock;
(3) mud or bentonite gel; or
(4) water.

Notes

312 IAC 29-33-19
Natural Resources Commission; 312 IAC 29-33-19; filed 12/1/2017, 10:35 a.m.: 20171227-IR-312160230FRA Readopted filed 1/17/2023, 1:53 p.m.: 20230215-IR-312220328RFA

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.