Sec. 19.
(a) This
section establishes requirements for filling intervals between plugs required
under this rule.
(b) Unless
specified otherwise, the uncemented intervals between any plugs required under
this rule may be filled with:
(1) pea
gravel;
(2) crushed rock;
(3) mud or bentonite gel; or
(4) water.