Authority: IC 13-14-8; IC
13-17-3-4; IC
13-17-3-11
Affected: IC 13-15; IC 13-17
Sec. 4.
(a) Except as
provided in sections 3(d) and 8.5 of this rule, the owner or operator shall
meet the monitoring system certification and other requirements of section 3(b)
or 8.5(e) of this rule on or before the applicable dates in this section. The
owner or operator shall record, report, and quality assure the data from the
monitoring systems under section 3(b)(1) or 8.5(e) of this rule on and after
the following dates:
(1) For units that
commenced operation before August 26, 2018, by August 26, 2018.
(2) For the owner or operator of a large
affected unit that commences operation after August 26, 2018, and that reports
on an annual basis under section 8(b) of this rule, by one hundred eighty (180)
calendar days after the date on which the unit commences commercial
operation.
(3) For the owner or
operator of a large affected unit that commences operation after August 26,
2018, and that reports on a control period basis under section 8(b) of this
rule, by the later of the following dates:
(A)
One hundred eighty (180) calendar days after the date on which the unit
commences commercial operation.
(B)
If the compliance date under clause (A) is not during an ozone control period,
then by May 1 immediately following the compliance date under clause
(A).
(4) For the owner
or operator of a large affected unit for which construction of a new stack or
flue or installation of add-on NO
x emission controls is
completed after August 26, 2018, and that reports on an annual basis under
section 8(b) of this rule, by the earlier of the following dates:
(A) One hundred eighty (180) calendar days
after the date on which emissions first exit to the atmosphere through the new
stack or flue or add-on NOx emissions
controls.
(B) Ninety (90) unit
operating days after the date on which emissions first exit to the atmosphere
through the new stack or flue or add-on NOx emissions
controls.
(5) For the
owner or operator of a large affected unit for which construction of a new
stack or flue or installation of add-on NO
x emission
controls is completed after August 26, 2018, and that reports on a control
period basis under section 8(b) of this rule, by the later of the following
dates:
(A) The earlier of:
(i) one hundred eighty (180) calendar days
after the date on which emissions first exit to the atmosphere through the new
stack or flue or add-on NOx emissions controls;
or
(ii) ninety (90) unit operating
days after the date on which emissions first exit to the atmosphere through the
new stack or flue or add-on NOx emissions
controls.
(B) If the
compliance date under clause (A) is not during an ozone control period, May 1
immediately following the compliance date under clause (A).
(b) The owner or
operator of a large affected unit that does not meet the applicable compliance
date set forth in subsection (a) for any monitoring system under section 3 of
this rule shall, for each monitoring system, determine, record, and report
maximum potential or, as appropriate, minimum potential, values for the
following:
(1) NOx
emission rate.
(2)
NOx concentration.
(3) Stack gas moisture content.
(4) Stack gas flow rate.
(5) Fuel flow rate.
(6) Any other parameters required to
determine NO
x mass emissions and heat input in
accordance with the following, as applicable:
(C) 40 CFR
75, Appendix D, Section
2.4*.
(D) 40 CFR
75, Appendix E,
Section 2.5*.
*These documents are incorporated by reference. Copies may be
obtained from the Government Publishing Office, www.gpo.gov, or are available for review at the
Indiana Department of Environmental Management, Office of Legal Counsel,
Indiana Government Center North, 100 North Senate Avenue, Thirteenth Floor,
Indianapolis, Indiana 46204.