326 IAC 6-5-6 - Commencement of plans

Authority: IC 13-1-1-4; IC 13-7-7

Affected: IC 13-1-1

Sec. 6.

All sources subject to this rule (326 IAC 6-5) shall have an approved control plan and shall start said plan:

(a) Within twelve (12) months after December 13, 1985, or as otherwise specified in the approved plan, by sources located in primary nonattainment areas for total suspended particulate matter.
(b) As expeditiously as possible, but no later than December 31, 1989, or as otherwise specified in the approved plan, by sources located in secondary nonattainment areas for total suspended particulate matter.
(c) The date operation commences for new sources.

Notes

326 IAC 6-5-6
Air Pollution Control Board; 326 IAC 6-5-6; filed Mar 10, 1988, 1:20 pm: 11 IR 2504; readopted filed Jan 10, 2001, 3:20 p.m.: 24 IR 1477

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.