326 IAC 6-5-7 - Approval of plans
Authority: IC 13-1-1-4; IC 13-7-7
Affected: IC 4-21.5
Sec. 7.
(a) Within
three (3) months of receiving a control plan, the commissioner shall notify the
source of:
(1) the approval of the control
plan or request for an exemption;
(2) improvements that the commissioner deems
necessary to the control plan; or
(3) disapproval of the control plan or
request for an exemption.
(b) If the commissioner finds a control plan
or request for an exemption from the control plan to be incomplete, the
applicant shall provide the board the required additional
information.
(c) The commissioner
shall approve control plans which contain any RCM specified in
326 IAC 6-5-4. In determining if
(i) an alternate control measure represents a RCM, or (ii) exemptions from
control plans are acceptable, the source shall submit and the commissioner
shall consider information pertaining to factors, including, but not limited to
the following:
(1) the impact on the
environment in terms of any increase in water, air, or solid waste pollution
emissions;
(2) the energy
requirements of the selected control measure;
(3) the capital expenditure, impact on
production, and operating costs to implement the selected control
measure;
(4) the impact of these
costs on the source; and
(5) any
adverse worker or product safety implications of the selected control
measure.
(d) Sources
that demonstrate to the satisfaction of the commissioner either that their
fugitive emissions are not significantly impacting the air quality outside
their property line or that the cost of controlling their fugitive emissions is
not commensurate with the degree of air quality improvement to be achieved by
implementing control measures pursuant to this rule (326 IAC
6-5) shall be exempted from implementing such
controls.
(e) If a control plan or
request for an exemption from the plan is disapproved by the commissioner, the
applicant shall have up to fifteen (15) days from the date of receipt of the
disapproval letter to request, in writing, a hearing on the matter. In the
event a hearing is requested, it shall be held in accordance with the
requirements set forth in IC 4-22-1 or IC 4-21.5 and the burden of proof shall
lie with the applicant to demonstrate why the control plan or request for an
exemption from the plan is appropriate.
(f) The control plan or exemption approved by
the commissioner shall become part of the source's operation permit.