327 IAC 15-3-3 - Deadline for submittal of an NOI; additional requirements

Current through March 30, 2022

Authority: IC 13-14-8; IC 13-14-9; IC 13-15-1-2; IC 13-15-2-1; IC 13-18-3

Affected: IC 13-11-2; IC 13-18-4

Sec. 3.

A person proposing a new discharge that will be subject to a general permit shall submit an NOI to the department along with additional information as required by the applicable general permit according to one (1) of the following:

(1) On or before the submission deadline prescribed by the applicable general permit.
(2) If no deadline is prescribed by the applicable general permit, submission must be at least one hundred eighty (180) days before the date when the discharge is to commence.
(3) At a later date if it has been granted by the commissioner or is established in the applicable general permit.

Notes

327 IAC 15-3-3
Water Pollution Control Board; 327 IAC 15-3-3; filed Aug 31, 1992, 5:00 p.m.: 16 IR 19; errata filed Sep 10, 1992, 12:00 p.m.: 16 IR 65; errata, 16 IR 898; readopted filed Jan 10, 2001, 3:23 p.m.: 24 IR 1518; filed Oct 27, 2003, 10:15 a.m.: 27 IR 832; readopted filed Nov 21, 2007, 1:16 p.m.: 20071219-IR-327070553BFA readopted filed Jul 29, 2013, 9:21 a.m.: 20130828-IR-327130176BFA; Filed 10/9/2015, 4:07 p.m.: 20151104-IR-327100659FRA Errata filed 12/30/2015, 12:37 p.m.: 20160113-IR-327150453ACA Filed 11/18/2021, 11:08 a.m.: 20211215-IR-327180238FRA