(a) After funds have been appropriated by the legislature for a project, the sponsor shall submit to the commission a phase III application. The application shall be submitted on a form furnished by the commission.
(b) The sponsor shall be responsible for securing all required permits before a state contract may be authorized. A copy of each required permit shall be furnished to the commission before any construction or renovation reimbursements are made.
(c) In addition to meeting the other requirements of this regulation, the sponsor of each renovation project shall submit a pre-excavation bathymetric survey estimating the volume of sediment to be excavated and a plan to address the safe handling and disposing of contaminants.
(d) The contractor selection committee shall include a representative of the commission.

Notes

Kan. Admin. Regs. § 11-4-6
Authorized by K.S.A. 2005 Supp. 82a-1602 and K.S.A. 82a-1607; implementing K.S.A. 82a-1607; effective, T-86-43, Dec. 18, 1985; effective May 1, 1986; amended Sept. 22, 2006.

The following state regulations pages link to this page.



State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.