Kan. Admin. Regs. § 5-43-2 - Sand dredging; buffer zone

Current through Register Vol. 40, No. 39, September 30, 2021

There shall be a buffer zone of not less than 500 feet between dredging operations, and between dredging operations and all bridges. There shall be a buffer zone of 300 feet between dredging operations and buried pipeline or cable crossings. There shall be a buffer zone of 200 feet between dredging operations and levees, or other features subject to damage by undercutting.

Notes

Kan. Admin. Regs. § 5-43-2
Authorized by K.S.A. 82a-303a; implementing K.S.A. 82a-303; effective May 1, 1987.