A.
Applicability
(1) This section
applies to the replacement of a legally existing permanent structure in, on, or
over a coastal wetland, freshwater wetland, great pond, fragile mountain area,
or river, stream or brook. Some activities involving maintenance and repair of
a permanent structure may not require a permit (see Note at the end of this
section).
(2) In order to be
eligible for this section, the structure must have been in place and
functioning as intended within 24 months of the DEP's receipt of the
notification form. A permit by rule for replacement is valid for three years
from the date of approval.
(3) This
section does not apply to the replacement of a structure adjacent to a
protected natural resource, except for a structure that is partly in, on, or
over and partly adjacent to the resource and except for a legally existing
shoreline stabilization structure (e.g., riprap, vertical seawall or retaining
wall). (See Section 2: Activities adjacent to protected natural
resources.)
(4) This section does
not apply to structures located within a coastal sand dune system. (See Section
16: Development activities in coastal sand dunes.)
(5) This section does not apply to the
replacement of a dam or a tidal flood gate.
(6) This section does not apply to an
activity that is not or will not be in compliance with the terms and conditions
of permits issued under the Site Location of Development Law,
38 M.R.S.
Sections481 to
490, the Storm Water Management
Law, 38
M.R.S. Section420-D, or the Natural Resources
Protection Act,
38 M.R.S.
Sections480-A to
480-K K.
(7) This section does not apply to an
activity that will not conform to the local shoreland zoning ordinance.
NOTE: Contact the local Code Enforcement Officer for
information on local shoreland zoning requirements
B.
Submissions
(1) For an activity occurring in tidal
waters, notice of approval of timing of the activity from the Department of
Marine Resources must be submitted to the DEP with the notification
form.
(2) The applicant is required
to submit photographs of the area which will be affected by the activity
proposed.
(3) Photographs showing
the completed project and the affected area must be submitted within 20 days of
the activity's completion. The photographs must be sent with a copy of the
notification form or labeled with the applicant's name and the municipality in
which the activity took place.
(4)
A scaled plan or drawing of the structure to be replaced that includes at a
minimum the location, width, length and height of the existing structure.
It is not necessary to have the plan professionally prepared.
However, it must be legible and drawn to a scale that provides a clear
representation of distances and measurements on the plan.
C.
Standards
(1) A replaced structure that is located in,
on, or over a protected natural resource may not exceed the dimensions,
including height, of the previously existing structure, and may not extend any
further into the water body or wetland, except that retaining walls may be
reinforced with a facing material not exceeding 6 inches in width or may be
replaced with riprap, biodegradable stabilization materials or vegetation in
accordance with Section 8 "Shoreline stabilization".
NOTE: Vegetation is the preferred method of erosion control
near water bodies. Where the use of vegetation is not feasible, riprap is
preferred over retaining walls because it dissipates wave action and is a more
stable structure over the long term. The DEP encourages the replacement of
retaining walls with riprap, unless the presence of large trees or structures
makes its use impractical.
(2) A replaced structure may be relocated
landward during replacement so that its footprint covers less of the protected
natural resource.
(3)
Notwithstanding Section 4(C)(1), the height of a replaced pier, wharf or dock
in, on or over a coastal wetland may be increased by no more than the amount
necessary for the bottom of the lowest horizontal structural component of the
deck of the pier, wharf or dock to be 4 feet above the base flood elevation
mapped by the Federal Emergency Management Agency (FEMA). The deck of the pier,
wharf or dock may be extended into the upland only as necessary to accommodate
any height increase under this paragraph and an additional row of pilings may
be placed under the deck to facilitate that extension.
For the purposes of this section a "pier, wharf, or dock"
includes any permanent structures located on the pier, wharf or dock but does
not include a seawall, jetty, breakwater, or similar structure intended to
dissipate wave action.
NOTE: FEMA flood map information may be found at the FEMA
website or your municipal office: https://www.fema.gov/flood-maps
(4) Notwithstanding Section
4(C)(1), the height of an existing riprap stabilization structure, vertical
seawall or retaining wall located in and/or directly adjacent to a coastal
wetland may be increased up to one foot above the base flood elevation mapped
by FEMA in accordance with Section 8 or Section 8-A.
(5) Notwithstanding Sections 4(C)(1-4), the
height of another structure that is a legally existing nonconforming principal
or accessory structure under the local shoreland zoning ordinance may be
increased by no more than the amount necessary for the bottom of the lowest
horizontal structural component of the structure to be 3 feet above the base
flood elevation mapped by FEMA or to be the elevation necessary to be
consistent with the local floodplain management elevation requirement,
whichever is greater. The applicant must submit evidence that the municipality
has approved the elevation and location of the replacement structure.
(6) The following measures must be taken to
prevent erosion of soil or fill material from disturbed areas into the
resource:
(a) For any soil disturbance that is
limited to the upland and does not extend into the protected natural resource,
sediment controls such as trenched and anchored silt fence, an erosion control
mix berm at least 1 foot tall, staked straw bales, anchored erosion control
socks at least 12 inches in diameter, or a combination of these methods must be
properly installed between the area of soil disturbance and the resource before
the activity begins and maintained until the disturbed area is permanently
stabilized;
(b) Any soil
disturbance within a freshwater wetland, great pond, river, stream, or brook
must be done during periods of low water to minimize impacts (in-stream work
window, lake draw-down, etc.) and must be temporarily or permanently stabilized
daily. The placement of sediment barriers within the water would be ineffective
and could cause unnecessary damage to the resource;
(c) Any soil disturbance within a coastal
wetland must be done at or near low tide and must be temporarily or permanently
stabilized before being submerged. The placement of sediment barriers within
the tidal zone would be ineffective and could cause unnecessary damage to the
resource;
(d) Surface flows from
above the disturbed area must be diverted around the disturbed area until final
stabilization and any diverted runoff must be managed to prevent erosion;
examples of diversions include but are not limited to erosion control mix berms
or socks, sand bags, and shallow excavated trenches;
(e) Within 1 calendar day following the
completion of any soil disturbance, and prior to any storm event, temporary or
permanent stabilization must be implemented or spread on any exposed
soils;
(f) All disturbed soils must
be permanently stabilized; and
(g)
Within 30 days of final stabilization of the site, any silt fence, straw bales,
or temporary erosion or sediment controls containing plastic or other
non-biodegradable materials must be removed and erosion control mulch berms
must be raked to a depth of no more than 6 inches.
NOTE: For guidance on erosion and sedimentation controls,
consult the Maine Erosion and Sediment Control BMPs, dated October 2016. This
handbook and other references are available online at
https://www.maine.gov/dep/land/erosion/escbmps/
or by contacting the DEP.
(7) Disturbance of wetland vegetation must be
avoided if possible. If wetland vegetation must be disturbed during the
activity, it must be reestablished immediately upon completion of the activity
and must be maintained.
(8)
Non-native wetland plants may not be planted in disturbed areas.
(9) Work done in a river, stream or brook
must allow for fish passage and the maintenance of normal stream flows at all
times of year and may not impound water.
(10) No dredging may take place during the
activity and no material may be removed from the affected natural resource
except that rocks that were part of the original structure may be removed or
reused.
(11) Work below the high
water line of a great pond, river, stream or brook must be done at low water,
except as required for emergency flood control work. Measures, such as a silt
boom or staked fencing, must be employed to reduce and isolate
turbidity.
(12) If the activity
occurs within tidal waters, the activity must occur during the time period
approved by the Department of Marine Resources.
(13) If work is performed in a river, stream
or brook that is less than three feet deep at the time of the activity and at
the location of the activity, the applicant must provide for temporary
diversion of flow to the opposite side of the channel while work is in
progress.
(a) Diversion may be accomplished by
placing sandbags, timbers, sheet steel, concrete blocks, 6+ mil polyethylene or
geotextiles from the bank to midstream on the upstream side of the activity. No
more than two-thirds (2/3) or 25 feet of stream width, whichever is less, may
be diverted at one time.
(b) Any
material used to divert water flow must be completely removed upon completion
of the activity, and the stream substrate must be restored to its original
condition.
(c) A pump may be
operated, where necessary, for a temporary diversion. The pump outlet must be
located and operated such that erosion or the discharge of sediment to the
water is prevented.
(14)
Wheeled or tracked equipment may not be operated in the water. Equipment
operating on the shore may reach into the water with a bucket or similar
extension. Equipment may cross streams on rock, gravel or ledge
bottom.
(15) All wheeled or tracked
equipment that must travel or work in a vegetated wetland area must travel and
work on mats or platforms in order to protect wetland vegetation.
(16) All debris or excavated material must be
stockpiled either outside the wetland or on mats or platforms. Straw bales,
silt fence or mulch must be used, where necessary, to prevent sedimentation.
Any debris generated during the activity must be prevented from washing
downstream and must be removed from the wetland or water body. Disposal of
debris must be in conformance with Maine Hazardous Waste, Septage and Solid
Waste Management Act,
38 M.R.S.
Section1301 et seq.
(17) Uncured concrete may not be placed
directly into the water. Concrete must be pre-cast and cured at least three
weeks before placing in the water, or where necessary, must be placed in forms
and cured at least one week before the forms are removed. No washing of tools,
forms, etc. may occur in the waterbody or wetland.
(18) The use of untreated lumber is
preferred. Lumber pressure treated with chromated copper arsenate (CCA) may be
used only if necessary and only if use is allowed under federal law and not
prohibited from sale under
38 M.R.S.
§1682, and provided it is cured on dry
land in such a manner as to expose all surfaces to the air for a period of at
least 21 days prior to construction. Wood treated with creosote or
pentachlorophenol may not be used where the wood will come in contact with
water. Sawdust or other lumber waste materials may not be stored or placed in
such a manner that pollutants may be discharged into the resource.
(19) The replaced structure may not interfere
with, or reduce the opportunity for, existing navigational and recreational
uses of the site.
D.
Definitions. The following terms, as used in this chapter, have
the following meanings, unless the context indicates otherwise:
(1)
Dam. Any artificial barrier,
including appurtenant works, the site on which it is located and appurtenant
rights of flowage and access, that impounds or diverts a river, stream or brook
or great pond.
(2)
Dredge. To move or remove, by digging scooping or suctioning any
sand, silt, mud, gravel, rock, or other material from the bottom of a water
body or wetland surface.
(3)
Fill.
a. (verb) To put into or
upon, supply to, or allow to enter a water body or wetland any earth, rock,
gravel, sand, silt, clay, peat, or debris;
b. (noun) Material, other than structures,
placed in or adjacent to a water body or wetland.
(4)
Land adjacent to a protected
natural resource. Any land area within 75 feet, measured horizontally,
of the normal high water line of a great pond, river, stream or brook or the
upland edge of a coastal wetland or freshwater wetland.
(5)
Public works project. A
federal, state or local government, or state-regulated utility project for
public use or service including, but not limited to, highways, dams, bridges,
utility lines, water lines, sewerage, and recreational facilities such as boat
launch facilities.
(6)
Replacement. Any activity that results in more than 50% of a
structure being restored or reconstructed whether above or below the normal
high water line.
(7)
Retaining wall. A vertical or near vertical structure generally
constructed of wood, concrete or rock or a combination of these materials and
located at or below the normal high water line.
(8)
Riprap. Heavy,
irregularly-shaped rocks that are fit into place, without mortar, on a slope.
Square or rectangular rocks with flat faces, such as quarry stone or
manufactured blocks, do not qualify as "irregularly-shaped".
(9)
Structure. Anything built
for the support, shelter or enclosure of persons, animals, goods or property of
any kind, together with anything constructed or erected with a fixed location
on or in the ground. Examples of structures include buildings, utility lines
and roads.
(10)
Non-native
wetland plants. Wetland grasses, forbs, shrubs, or trees not native to
the State of Maine, for example, common reed (Phragmites
communis) and purple loosestrife (Lythrum salicaria).
NOTES:
(1) Section
480-Q(15-A) of the NRPA exempts the installation, removal or repair of a septic
system from permitting requirements as of March 1, 1995, as long as the system
complies with all requirements of the subsurface wastewater disposal rules
adopted by the Department of Health and Human Services under
22 M.R.S.
Section42, subsection
3.
(2) Section 480-Q(2) of the NRPA exempts from
permitting the maintenance and minor repair of structures in, on, over or
adjacent to a protected natural resource and maintenance and minor repair of
private crossings of a river, stream or brook provided:
(a) Erosion control measures are taken to
prevent sedimentation of the water;
(b) The crossing does not block fish passage
in the water course;
(c) There is
not additional intrusion into the protected natural resources; and
(d) The dimensions of the repaired structure
do not exceed the dimensions of the structure as it existed 24 months prior to
the repair.
Section 480-Q(2) of the NRPA does not apply to the repair of
more than 50% of a structure located in a coastal sand dune system; the repair
of more than 50% of a dam, unless that repair has been approved by a
representative of the United States Natural Resources Conservation Service; or
the repair of more than 50% of any other structure, unless the municipality in
which the proposed activity is located requires a permit for the activity
through an ordinance adopted pursuant to the mandatory shoreland zoning laws
and the application for a permit is approved by the municipality.
(3) Section 480-Q(2-B)
of the NRPA exempts from permitting the replacement of a floating dock with
another floating dock if the dimensions of the replacement dock do not exceed
those of the dock being replaced and the configuration of the replacement dock
is the same as the dock being replaced.
(4) Section 480-Q(2-F) of the NRPA exempts
from permitting the repair of a pier, wharf or dock located wholly or partially
in, on or over a coastal wetland if:
(a)
Erosion control measures are taken to prevent sedimentation of the
water;
(b) There is no additional
intrusion into the coastal wetland;
(c) Fill is not placed in or adjacent to the
coastal wetland; and
(d) The
dimensions of the repaired pier, wharf or dock do not exceed the dimensions of
the pier, wharf or dock as it existed 24 months prior to the repair, except
that the height of the pier, wharf or dock may be increased by no more than the
amount necessary for the bottom of the lowest horizontal structural component
of the deck of the pier, wharf or dock to be 4 feet above the base flood
elevation. The deck of the pier, wharf or dock may be extended into the upland
only as necessary to accommodate any height increase under this paragraph.
Section 480-Q(2-F) does not apply to the repair of more than
50% of a pier, wharf or dock located wholly or partially in, on or over a
coastal wetland unless the municipality in which the repair activity is located
requires a permit for the activity through an ordinance adopted pursuant to the
mandatory shoreland zoning laws and the application for a permit is approved by
the municipality.
For the purposes of Section 480-Q(2-F), "pier, wharf or dock"
includes any permanent structures located on the pier, wharf or dock. "Pier,
wharf or dock" does not include a seawall, jetty, breakwater or similar
structure designed to dissipate wave action.
(5) Section 480-Q(9) of the NRPA exempts from
permitting emergency repair or normal maintenance and repair of existing public
works which affect any protected natural resource. An activity which is exempt
under this subsection must employ erosion control measures to prevent
sedimentation of any surface water, may not block fish passage in any water
course and may not result in any additional intrusion of the public works into
the protected natural resource. This exemption does to apply to any activity on
an outstanding river segment as listed in section 480-P.