06-096 C.M.R. ch. 310, § 5-A - Shoreline Stabilization

This section applies to shoreline stabilization projects using riprap or other structural stabilization materials. This section does not apply to shoreline stabilization projects using only vegetation and/or biodegradable stabilization materials.

NOTE: Other laws and rules may apply to shoreline stabilization projects, including the Mandatory Shoreland Zoning Act, Title 38, Chapter 3, Article 2-B; Chapter 355, Coastal Sand Dune Rule s; Chapter 335, Significant Wildlife Habitat; and Chapter 305, Natural Resources Protection Act - Permit by Rule Standards.

A. General Standards. The project must meet the general standards contained in section 5.
B. Project Purpose. An applicant for a permit must demonstrate that the project is a health or safety project or designed to protect one of the following:
(1) A legally existing water-dependent structure such as a pier, wharf, dock, boat ramp, stormwater outfall, perimeter drain outfall or stairway to the water;
(2) A subsurface wastewater disposal system that is located 25 feet or less from the upland edge of an eroding bank, or that is more than 25 feet from the upland edge of an eroding bank if the Department determines the system is at risk of effluent breakout without immediate shoreline stabilization;
(3) A residential dwelling, commercial or public building or facility, driveway, road or other structure that is essential for the current use of the property, that legally existed on the parcel prior to January 1, 2026, or that is part of the permitted redevelopment of impervious area that existed on the parcel prior to January 1, 2026, if that structure is either:
(a) Located 100 feet or less from the upland edge of an eroding bank and cannot be practicably relocated farther than 100 feet from the bank, or
(b) At significant risk from a landslide as demonstrated by geotechnical analysis, and the applicant has demonstrated that the risk cannot be adequately mitigated by relocating the structure, if practicable, or by installing riprap toe protection allowed under subsection B(6), regrading the slope and planting vegetation, installing biodegradable stabilization materials, or a combination of these techniques. The Department may require the applicant to commission a third-party geotechnical analysis to confirm the need for structural stabilization for landslide prevention;
(4) An open space that serves the public, such as a municipal park or concert venue;
(5) Farmland as defined in 36 M.R.S. § 1102(4); or
(6) Any other area, provided the project is limited to no higher than 3 feet of riprap toe protection and will not inhibit the natural transfer of sediment from a bluff that is a significant source of sediment to a coastal wetland, as determined by the Maine Geological Survey.
C. Alternatives Analysis. As part of the alternatives analysis required under section 9(A) of this chapter, the applicant must demonstrate that the project purpose cannot be practicably achieved by the use of vegetation and/or biodegradable stabilization materials. There is a rebuttable presumption that vegetation and/or biodegradable stabilization materials can practicably stabilize a shoreline that is subject to erosion in a low-energy environment with little or no wave action, such as an open-water freshwater wetland, great pond, marshland, protected cove, or area of extensive mudflats. There is also a rebuttable presumption that vegetation and/or biodedgradable stabilization materials can practicably stabilize a shoreline that is classified as a stable bluff by the Maine Geological Survey. This subsection does not apply when the project is a health or safety project or designed to protect a water-dependent structure under subsection B(1) or a subsurface wastewater disposal system under subsection B(2).

NOTE: For high-energy environments, such as an area mapped as a high-velocity flood zone (VE zone) by FEMA or an area mapped as an unstable or highly unstable bluff by the Maine Geological Survey, there is not a rebuttable presumption that vegetation and/or biodegradable stabilization materials can practicably stabilize the shoreline.

The Maine Geological Survey has created a Living Shorelines Decision Support Tool to help applicants plan appropriate approaches for shoreline stabilization, available online at: https://www.maine.gov/dacf/mgs/hazards/living_shoreline/.

D. Limitations. Shoreline stabilization projects must be limited as follows:
(1) Actively eroding area. The project must be limited to the area(s) where soils are exposed due to erosion from wave action, currents, ice scouring or changes in water levels.
(2) Length. The length of the project may not be longer than necessary to protect the structure or space that the project is designed to protect under subsection B.
(3) Height. Unless the applicant provides evidence, and the Department determines, that some or all portions of a project must be built higher to achieve the project purpose, the project may not extend higher than the following elevations:
(c) A project along the shoreline of a great pond or open water wetland may not extend higher than 2 feet above the normal high water line.
(d) A project along the shoreline of a river, stream or brook may not extend higher than either the base flood elevation mapped by the Federal Emergency Management Agency (FEMA), or 2 feet above the normal high water line, whichever is higher.
(e) A project along the shoreline of a coastal wetland may not extend higher than one foot above the base flood elevation mapped by FEMA.
E. Vegetative Buffer. A vegetative buffer at least 10 feet wide as measured perpendicular to the shoreline and consisting of both native woody and herbaceous vegetation must be planted along the upland edge of the stabilization project. If the buffer is planted over a subsurface wastewater disposal system, the buffer may be comprised entirely of herbaceous vegetation. No non-native species may be planted. The Department may approve a reduction in the width of the vegetative buffer if:
(1) The full buffer width is not feasible due to the proximity of a structure to the upland edge of the eroding shoreline;
(2) The area is already well-vegetated with native woody vegetation or a mix of native woody and herbaceous vegetation; or
(3) The Department determines that the full buffer width is not practicable.

The buffer must be monitored and replanted as necessary to achieve 85 percent survival after three growing seasons. The applicant must submit photos to the Department documenting vegetative buffer survival or re-planting annually for three years.

F. Additional Standards. The following additional standards apply.
(1) A yard or other developed area may not be extended closer to the water as part of a shoreline stabilization project.
(2) Rocks used for stabilization may not be obtained from the shoreline or a protected natural resource, unless the rocks are from a previously failed stabilization project.
(3) When sediment is excavated to allow for stabilization in or adjacent to a coastal wetland, the excavated sediment must be evenly distributed across the stabilization structure, if determined to be feasible by the Department without increasing the area of the structure in the coastal wetland.

NOTE: Evenly distributing the sediment on the stabilization structure allows the sediment to naturally transfer to the wetland over time, mimicking the natural transfer of sediment from the terrestrial to the marine environment.

Nothing in this subsection shall prohibit the Department from establishing any additional reasonable requirement as a term or condition of approval under Section 8 of this Chapter.

G. Additional Application Requirements. In addition to other application subsmissions required by this Chapter, the application must include:
(1) A minimum of one photograph in an orientation parallel to the shoreline and one photograph in an orientation perpendicular to the shoreline from the resource landward along each 25-foot section of shoreline where the activity is proposed, including a person or another object in each photograph for scale. Photographs along a coastal shoreline must be taken at or near low tide.
(2) Photographs and site plans showing the structure(s) or space that the structural stabilization measure is designed to protect.
(3) A scaled drawing and at least two cross-sections of the proposed stabilization measure. The drawing must clearly depict the property boundaries, the normal high water line or the boundary o the coastal wetland, and the extent of any soil disturbance, grading, vegetated areas, and stabilization measures to be installed, such as the length along the shoreline, square footage of fill below the normal high water line or within the coastal wetland, and height above and below the normal high water line the boundary of the coastal wetland. The drawing must be legible and drawn to a scale that provides a clear representation of distances and measurements on the plan.
(4) A plan for how machinery will access the project site. If work will be done below the normal high water line or within the coastal wetland, the plan must describe how machinery will access these areas.
(5) An analysis of the practicably of relocating a structure if applicable pursuant to subsection B(3), including an analysis of cost, technology, and logistics.
(6) An analysis of the practicability of achieving the project purpose by using vegetation and/or biodegradable stabilization materials, if applicable pursuant to subsection C, including an analysis of cost, technology, and logistics.

Nothing in this subsection prohibits the Department from requiring additional information from the applicant or imposing additional conditions as set forth in Section 9 of this Chapter.

Notes

06-096 C.M.R. ch. 310, § 5-A

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.