06-096 C.M.R. ch. 526, § 11 - Application Processing Procedures for New Facilities. [See 40 CFR Section 125.89]
A.
Permit
application. The Department will review materials submitted by the
applicant under sections 18 and 8 at the time of the initial permit application
and before each permit renewal or reissuance.
(1) After receiving the initial permit
application from the Owner or Operator of a new facility, the Department will
determine applicable standards in section 6 to apply to the new facility. In
addition, the Department will review materials to determine compliance with the
applicable standards.
(2) For each
subsequent permit renewal, the Department will review the application materials
and monitoring data to determine whether requirements, or additional
requirements, for design and construction technologies or operational measures
should be included in the permit.
(3) For Track II facilities, the Department
may review the information collection proposal plan required by section
8.C(2)(c). The facility may initiate sampling and data collection activities
prior to receiving comment from the Department.
B.
Permitting requirements. The
requirements of this Chapter are implemented for a facility through a MEPDES
permit. The Department will determine, based on the information submitted by
the new facility in its permit application, the appropriate requirements and
conditions to include in the permit based on the track (Track I or Track II)
the new facility has chosen to comply with. The following requirements must be
included in each permit:
(1)
Cooling
water intake structure requirements. At a minimum, the permit
conditions must include the performance standards that implement the
requirements of section 6, paragraphs B(1), (2), (3), (4) and (5); C(1), (2),
(3) and (4); or D(1) and (2). In determining compliance with proportional flow
requirement in sections 6.B(3)(b); C(2)(b); and D(2)(b), the Department will
consider anthropogenic factors (those not considered "natural") unrelated to
the new facility's cooling water intake structure that can influence the
occurrence and location of a thermocline. These include source water inflows,
other water withdrawals, managed water uses, wastewater discharges, and
flow/level management practices (e.g., some reservoirs release water from below
the surface, close to the deepest areas).
(i)
If an Owner or Operator of a facility chooses Track I, the Department will
review the Design and Construction Technology Plan required in section 8.B(4)
to evaluate the suitability and feasibility of the technology proposed to
minimize impingement mortality and entrainment of all life stages of fish and
shellfish. In the first permit issued, the Department will include a condition
requiring the facility to reduce impingement mortality and entrainment
commensurate with the implementation of the technologies in the permit. Under
subsequent permits, the Department will review the performance of the
technologies implemented and require additional or different design and
construction technologies, if needed to minimize impingement mortality and
entrainment of all life stages of fish and shellfish. In addition, the
Department will consider whether more stringent conditions are reasonably
necessary in accordance with section 6.E.
(ii) If an Owner or Operator of a facility
chooses Track II, the Department will review the information submitted with the
Comprehensive Demonstration Study required in section 8.C(2) and evaluate the
suitability of the proposed design and construction technologies and
operational measures to determine whether they will reduce both impingement
mortality and entrainment of all life stages of fish and shellfish to 90
percent or greater of the reduction that could be achieved through Track I. In
addition, the Department will review the Verification Monitoring Plan in
section 8.C(2)(d)(iv) and require that the proposed monitoring begin at the
start of operations of the cooling water intake structure and continue for a
sufficient period of time to demonstrate that the technologies and operational
measures meet the requirements in section 6.D(1). Under subsequent permits, the
Department will review the performance of the additional and/or different
technologies or measures used and determine that they reduce the level of
adverse environmental impact from the cooling water intake structures to a
comparable level that the facility would achieve were it to implement the
requirements of section 6.B(1) and (2).
(2)
Monitoring conditions.
At a minimum, the permit must require the permittee to perform the monitoring
required in section 9. The Department may modify the monitoring program when
the permit is reissued and during the term of the permit based on changes in
physical or biological conditions in the vicinity of the cooling water intake
structure. The Department may require continued monitoring based on the results
of the Verification Monitoring Plan in section 8.C(2)(d)(iv).
(3)
Record keeping and
reporting. At a minimum, the permit must require the permittee to
report and keep records as required by section 10.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.