65-407 C.M.R. ch. 330, § 8 - REBUILDING AND RELOCATION OF TRANSMISSION LINES
A.
Annual report. Each
transmission and distribution utility shall submit by April 1 of each year to
the Director of Electric and Gas Utility Industries a schedule of transmission
line rebuilding or relocation projects and minor transmission line construction
projects which it intends to carry out during the next 5 years concerning
transmission lines that will become, or will remain at, voltages of 69
kilovolts or more. The utility shall also identify in the schedule the planned
construction of any transmission lines which will be capable of initially
carrying 69 kilovolts or more, even if it is not expected to carry 69 kilovolts
or more. The failure of a utility to file a schedule shall constitute an
affirmative statement by the utility that it has no projects which it intends
to carry out during the next 5 years. A waiver of any provision of this section
may be requested from, and granted by, the Director of Electric and Gas Utility
Industries for good cause shown. Requests must be in writing and state the
basis for the requested waiver. Requests must be provided to the Office of the
Public Advocate.
B.
Content
of report. The contents of the annual schedule must include the
following information on each proposed project:
1. Identification (e.g. "Section 35
")
2. Location
3. Length
4. Year Originally Constructed
5. Voltage Level
6. Existing Conductor (e.g. "266.8 KCM
ACSR")
7. Existing Structure
Material and Design (e.g. "Wood H-Frame")
8. Peak Load
9. A copy of the most recent depreciation
study conducted by the company which includes the useful lives of the poles and
conductors which constitute the existing transmission system.
10. Estimated cost of the rebuilding or
relocation project in nominal dollars.
C.
Notification to submit
petition. If the Director of Electric and Gas Utility Industries
notifies the transmission and distribution utility within 60 days of the annual
filing that an investigation of any transmission line rebuilding or relocation
or minor transmission line construction project is warranted, the utility must
submit a petition for public convenience and necessity pursuant to section
3 of this rule. The absence of
Commission notification requiring the utility to file a petition does not
preclude such notification in subsequent years.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.