C.M.R. 65, 407, ch. 332 - FILING REQUIREMENTS FOR PETITIONS OF PUBLIC CONVENIENCE AND NECESSITY FOR PURCHASES OF ENERGY OR FUEL CONVERSION OF GENERATING FACILITIES

  1. § 407-332-1 - APPLICATION OF RULE AND DEADLINES
  2. § 407-332-2 - NOTICE OF INTENT AND DETERMINATION OF COMPLIANCE WITH THE RULE
  3. § 407-332-3 - EXEMPTIONS
  4. § 407-332-4 - WAIVERS
  5. § 407-332-5 - FILING FEES
  6. § 407-332-6 - INFORMATION REQUIREMENTS TO SHOW NEED FOR POWER
  7. § 407-332-7 - SENSITIVITY ANALYSES
  8. § 407-332-8 - WAIVER OF INFORMATION REQUIREMENTS
  9. § 407-332-9 - FUEL CONVERSION
  10. § 407-332-10 - DELEGATION

SUMMARY: This rule establishes filing requirements for petitions of public convenience and necessity for purchases of generating capacity, energy or transmission capacity or fuel conversion of generating facilities of more than 1,000 kilowatts.

Notes

C.M.R. 65, 407, ch. 332
EFFECTIVE DATE: This rule was approved as to form and legality by the Attorney General on August 6, 1997. It was filed with the Secretary of State on August 8, 1997, and became effective on August 13, 1997.
CONVERTED TO MS WORD:
May 17, 2005

STATUTORY AUTHORITY: 35-A M.R.S.A. §§101, 103 , 104, 107 , 111, 112, 3131, 3133 and 3134.