Md. Code Regs. 20.50.09.01 - Scope
A. This chapter
applies to a small generator facility seeking to interconnect and operate in
parallel -with the electric distribution system . All small generator
facilities shall interconnect under requirements in this chapter or under the
physical interconnection requirements of the PJM Interconnection, LLC under the
authority of FERC.
B. A small
generator facility seeking to interconnect and operate in parallel with the
electric distribution system under this chapter shall meet one of the following
criteria:
(1) The small generator facility is
a qualifying facility pursuant to the Public Utility Regulatory Policies Act
that intends to make sales at a rate approved by the Maryland
Commission;
(2) The small generator
facility is not a qualifying facility pursuant to the Public Utility Regulatory
Policies Act and does not intend to make sales of wholesale electric energy
through the PJM Interconnection, LLC;
(3) The small generator facility intends to
make sales of wholesale electric energy through the PJM Interconnection, LLC at
an electric distribution interconnection facility where there has been no prior
FERC jurisdictional service;
(4)
The small generator facility intends to make sales of wholesale electric energy
through the PJM Interconnection, LLC only at an electric distribution
interconnection facility through participation in a distributed energy resource
aggregation; or
(5) The small
generator facility will be interconnected to an electric distribution circuit
and its energy will not be transmitted across state lines for a wholesale
customer other than the electric distribution owner.
C. Market processes under FERC jurisdiction
that are administered by the PJM Interconnection, LLC may not impede the
interconnection timeline requirements in this chapter unless the utility has
good cause to believe that equipment upgrades exceeding minor equipment
modifications and related modifications to the interconnection agreement will
be needed to facilitate these market processes. In these cases, the utility
shall notify the interconnection customer in writing of their rationale to
delay approval of the interconnection request until the conclusion of the PJM
Interconnection, LLC's market process study.
D. In situations where an interconnected
small generator facility project intends to change their energy sales strategy
from market processes under FERC jurisdiction to retail processes under this
chapter, the small generator facility shall submit an interconnection
request.