Md. Code Regs. 20.50.09.05 - Interconnection Request Processing Fees

A. A utility may only charge a small generator interconnection request fee for a Level 2, Level 3, or Level 4 interconnection request.
(1) No charge for Level 1 applications;
(2) $50 plus $1 per kW of rated generating facility output for Level 2 applications; and
(3) $100 plus $2 per kW of rated generating facility output for Level 3 and 4 applications.
B. A utility may not charge interconnection request fees for interconnection requests determined to be under PJM Interconnection, LLC jurisdiction pursuant to Regulation .01 of this chapter.
C. The utility shall specify the interconnection request fees charged under this regulation in its tariff.

Notes

Md. Code Regs. 20.50.09.05
Regulation .05 amended effective 45:20 Md. R. 920, eff. 10/8/2018; amended effective 47:8 Md. R. 436, eff. 4/20/2020