Md. Code Regs. 20.50.09.05 - Interconnection Request Processing Fees
A. A utility may only charge a small
generator interconnection request fee for a Level 2, Level 3, or Level 4
interconnection request.
(1) No charge for
Level 1 applications;
(2) $50 plus
$1 per kW of rated generating facility output for Level 2 applications;
and
(3) $100 plus $2 per kW of
rated generating facility output for Level 3 and 4 applications.
B. A utility may not
charge interconnection request fees for interconnection requests determined to
be under PJM Interconnection, LLC jurisdiction pursuant to Regulation .01 of
this chapter.
C. The utility shall
specify the interconnection request fees charged under this regulation in its
tariff.