Md. Code Regs. 20.50.09.09 - Level 1 Review
A. The utility
shall evaluate a Level 1 small generator facility for the potential for adverse
system impacts using net system capacity, pursuant to Regulation .06A and B of
this chapter, unless nameplate capacity is specifically required using the
following:
(1) For interconnection of a
proposed small generator facility:
(a) To a
radial distribution circuit, the aggregate generation on the circuit, including
the proposed small generator facility, may not exceed 15 percent of the line
section annual peak load as most recently measured at the substation or
calculated for the line section; or
(b) To a spot network:
(i) On the load side of spot network
protectors, the proposed small generator facility shall utilize an
inverter-based equipment package;
(ii) The interconnection equipment proposed
for the small generator facility is lab-certified; and
(iii) The aggregate generation of all
interconnected small generator facilities may not exceed 5 percent of the spot
network's maximum load if the spot network serves more than one
customer;
(2)
When a proposed small generator facility is to be interconnected on a
single-phase shared secondary line, the aggregate generation on the shared
secondary line, including the proposed small generator facility, may not exceed
20 kW;
(3) When a proposed small
generator facility is single-phase and is to be interconnected on a center tap
neutral of a 240 volt service, its addition may not create an imbalance between
the two sides of the 240 volt service of more than 20 percent of the nameplate
rating of the service transformer;
(4) As an alternative non-mandatory method to
evaluate the adverse system impacts of a proposed Level 1 small generator
facility on the distribution system, as described in §A(1)-(3) of this
regulation, or as a mandatory next step prior to rejecting an interconnection
request, pursuant to §E of this regulation, for Level 1 Review Failure, a
utility may use a power-flow based analysis system with modeling of IEEE
1547-2018 inverter capabilities as follows, if its use may change the analysis
result as determined by the utility:
(a) For
primary voltage systems, within 6 months of the effective date of this
regulation; and
(b) For secondary
voltage systems, within 2 years of the effective date of this
regulation;
(5)
Modification or construction of additional interconnection facilities by the
utility on its distribution system, except for metering or a minor system
modification, is not required to accommodate the small generator facility;
and
(6) If the proposed
interconnection requires a minor system modification, the utility shall notify
the applicant of that requirement when it provides the Level 1 evaluation
result, as follows:
(a) The applicant shall
inform the utility within 10 business days if the applicant elects to continue
the application;
(b) If the
applicant makes such an election, the utility shall provide an interconnection
agreement, along with a non-binding good faith cost estimate and construction
schedule for those upgrades, to the applicant within 30 calendar days after the
utility receives such an election; and
(c) The applicant shall have 30 calendar
days, or other mutually agreeable time frame after receipt of the
interconnection agreement, to sign and return such agreement.
B. The utility in
conducting a Level 1 interconnection review shall:
(1) Within 5 business days after receipt of
the interconnection request, inform the applicant that the interconnection
request is:
(a) Complete; or
(b) Incomplete and what materials are
missing; and
(2) Within
15 business days after the utility notifies the applicant that the application
is complete under §B(1) of this regulation, verify that the small
generator facility can be interconnected safely and reliably under §A of
this regulation.
C.
Unless the utility determines and demonstrates that a small generator facility
cannot be interconnected safely or reliably to its electric distribution
system, the utility shall approve the interconnection request and provide a
permission to operate notice within 20 business days of receipt of acceptable
documents, subject to the following conditions:
(1) The small generator facility has been
approved by local or municipal electric code officials with jurisdiction over
the interconnection;
(2) A
certificate of completion has been returned to the utility;
(3) The witness test has been successfully
completed or waived by the utility; and
(4) The applicant has signed an
interconnection agreement.
D. If an applicant does not sign the
interconnection agreement within 30 calendar days after receipt from the
utility, the interconnection request is considered withdrawn unless the
applicant requests to have the deadline extended. A request for extension may
not be unreasonably denied by the utility.
E. Level 1 Review Failure.
(1) If the small generator facility is not
approved under a Level 1 review, the utility shall provide the applicant a
letter explaining its reasons for denying the interconnection
request.
(2) If a small generator
facility fails a Level 1 review, the utility may approve the interconnection
request if the small generator facility can be interconnected safely and
reliably to the utility's electric distribution system.
(3) When a small generator facility is not
approved under a Level 1 review, the applicant may submit a new interconnection
request for consideration under Level 2, Level 3, or Level 4
procedures.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.