Md. Code Regs. 20.50.09.11 - Level 3 Review
A. The utility
shall use the Level 3 review procedure for an interconnection request that
meets the Level 3 criteria in Regulation .08 of this chapter.
B. Queue Position.
(1) Once the interconnection request is
considered complete by the utility, the utility shall assign a queue position
based upon the date and time the interconnection request is determined to be
complete.
(2) The queue position of
each interconnection request shall be used to determine the potential adverse
system impact of the small generator facility based on the relevant screening
criteria.
(3) The utility shall
notify the applicant of any other higher queue position applicants on the same
radial line or area network that the applicant is seeking to interconnect
to.
(4) Queue position may not be
forfeited or otherwise impacted by any pending dispute submitted under the
provisions of Regulation .13 of this chapter.
C. Interconnection requests meeting the
requirements set forth in Regulation .08 of this chapter for nonexporting small
generator facilities interconnecting to an area network shall be presumed by
the utility to be appropriate for interconnection. The utility shall process
the interconnection request to area networks using the following procedures:
(1) The utility shall evaluate the
interconnection request under Level 2 interconnection review procedures as set
forth in Regulation .10 of this chapter, except that the utility shall have 25
business days to conduct an area network impact study to determine any
potential adverse system impact of interconnecting to the utility's area
network;
(2) If the area network
impact study identifies potential adverse system impacts, the utility may
determine at its sole discretion that it is inappropriate for the small
generator facility to interconnect to the area network, in which case the
interconnection request shall be denied; however, the applicant may elect to
submit a new interconnection request for consideration under Level 4
procedures, in which case the queue position assigned to the Level 3
interconnection request will be retained provided the request is made within 15
business days of notification that the current application is denied;
(3) The utility shall conduct the area
network impact study at its own expense; and
(4) In the event the utility denies the
interconnection request, the utility shall provide the applicant with a copy of
its area network impact study and written justification for denying the
interconnection request.
D. When an interconnection request meets the
requirements of Regulation .08 of this chapter for nonexporting small generator
facilities interconnecting to a radial distribution circuit, the utility shall:
(1) Evaluate the interconnection request
using the Level 2 review in Regulation .10 of this chapter; and
(2) Approve the interconnection request if
all of the applicable Level 2 screens are satisfied, except that the peak line
section value indicated in Regulation .10A(1(a) shall be 25 percent instead of
15 percent.
E.
Interconnection Agreement.
(1) If a small
generator facility satisfies the criteria in §C or D of this regulation,
the utility shall approve the interconnection request and provide an
interconnection agreement for the applicant to sign.
(2) The applicant shall have 30 calendar
days, or other mutually agreeable time frame after receipt of the
interconnection agreement, to sign and return the interconnection
agreement.
(3) If the applicant
does not sign the interconnection agreement within 30 calendar days, the
interconnection request shall be considered withdrawn unless the applicant and
utility mutually agree to extend the time period for executing the
interconnection agreement prior to the expiration of the 30-calendar-day
period. A request for extension may not be unreasonably denied by the
utility.
(4) After the
interconnection agreement is signed by the applicant and utility,
interconnection of the small generator facility shall proceed according to any
milestones agreed to by the applicant and utility in the interconnection
agreement.
(5) The utility shall
approve the interconnection request and provide a permission to operate notice
within 20 business days of receipt of acceptable documents, subject to the
following conditions:
(a) All milestones
agreed to in the interconnection agreement are satisfied;
(b) The small generator facility is approved
by electric code officials with jurisdiction over the
interconnection;
(c) The applicant
provides a certificate of completion to the utility;
(d) Upon request of the utility, the
applicant provides one or more photographs of the small generator facility site
location, components, metering equipment, and other related facilities and
equipment; and
(e) There is a
successful completion of the witness test, if conducted by the
utility.
F.
Level 3 Review Failure.
(1) If the small
generator facility is not approved under a Level 3 review, the utility shall
provide the applicant written notification explaining its reasons for denying
the interconnection request.
(2) If
the small generator facility is not approved under a Level 3 review, the
applicant may submit a new interconnection request for consideration under the
Level 4 procedures; however, the queue position assigned to the Level 3
interconnection request shall be retained provided the request is submitted
within 15 business days of the notice that the current Level 3 request was not
approved.