Md. Code Regs. 20.50.09.12 - Level 4 Study Review
A. A utility shall
use the Level 4 study review procedure for an interconnection request that
meets the Level 4 criteria in Regulation .08 of this chapter.
B. Interconnection Request.
(1) Within 5 business days from receipt of an
interconnection request, the utility shall notify the applicant whether the
request is
(a) Complete; or
(b) Incomplete.
(2) If the interconnection request is not
complete:
(a) The utility shall provide the
applicant a written list detailing information that shall be provided to
complete the interconnection request;
(b) The applicant shall have 10 business
days, which may be extended at the request of the applicant and not
unreasonably denied by the utility, to provide appropriate data in order to
complete the interconnection request, or the interconnection request shall be
considered withdrawn; and
(c) The
interconnection request shall be considered complete:
(i) If the required information has been
provided by the applicant; or
(ii)
The utility and applicant have agreed that the applicant may provide additional
information at a later time.
C. Queue Position.
(1) When an interconnection request is
complete, the utility shall assign a queue position.
(2) The utility shall use the queue position
of an interconnection request to determine the cost responsibility necessary
for the facilities to accommodate the interconnection.
(3) The utility shall notify the applicant of
other higher-queued applicants on the same line section of the new
interconnection request.
(4) Any
required interconnection studies may not begin until the utility has completed
its review of all other interconnection requests that have a higher queue
position.
(5) Queue position is not
forfeited or otherwise impacted by any pending dispute submitted under the
provisions of Regulation .13 of this chapter.
D. Scoping Meeting.
(1) By mutual agreement of the utility and
applicant, the scoping meeting may be waived and the interconnection
feasibility study, interconnection impact study, or interconnection facilities
studies provided for in a Level 4 review and discussed in this section may be
waived or combined.
(2) If agreed
to by the utility and applicant, a scoping meeting shall be held within 10
business days, or other mutually agreed to time, after the utility has notified
the applicant that the interconnection request is considered complete, or the
applicant has requested that its interconnection request proceed after failing
the requirements of a Level 2 review or Level 3 review.
(3) The purpose of the meeting is to review
the interconnection request, existing studies relevant to the interconnection
request, and the results of the Level 1, Level 2, or Level 3 screening
criteria.
(4) If the utility and
applicant agree at a scoping meeting that an interconnection feasibility study
shall be performed, the utility shall provide to the applicant, not later than
5 business days after the scoping meeting:
(a)
An interconnection feasibility study agreement;
(b) An outline of the scope of the study;
and
(c) A nonbinding, good faith
estimate of the cost to perform the study.
(5) If the applicant and utility agree at a
scoping meeting that an interconnection feasibility study is not required, the
utility shall provide to the applicant, not later than 5 business days after
the scoping meeting:
(a) An interconnection
system impact study agreement;
(b)
An outline of the scope of the study; and
(c) A nonbinding, good faith estimate of the
cost to perform the study.
(6) If the utility and applicant agree at the
scoping meeting that an interconnection feasibility study and system impact
study are not required, the utility shall provide to the applicant, not later
than 5 business days after the scoping meeting:
(a) An interconnection facilities study
agreement;
(b) An outline of the
scope of the study; and
(c) A
nonbinding, good faith estimate of the cost to perform the study.
E. Interconnection
Feasibility, Interconnection System Impact, and Interconnection Facilities
Studies.
(1) Interconnection Feasibility
Study,
(a) An interconnection feasibility
study shall include any necessary analyses for the purpose of identifying a
potential adverse system impact to the utility's electric distribution system
that would result from the interconnection from among the following:
(i) Initial identification of any circuit
breaker short circuit capability limits exceeded as a result of the
interconnection;
(ii) Initial
identification of any thermal overload or voltage limit violations resulting
from the interconnection;
(iii)
Initial review of grounding requirements and system protection; and
(iv) Description and nonbinding estimated
cost of facilities required to interconnect the small generator facility to the
utility's electric distribution system in a safe and reliable manner.
(b) If an applicant requests that
the interconnection feasibility study evaluate multiple potential points of
interconnection, additional evaluations may be required. Additional evaluations
shall be conducted at the expense of the applicant.
(c) An interconnection system impact study is
not required if the interconnection feasibility study concludes there is no
adverse system impact, or if the study identifies an adverse system impact and
the utility is able to identify a remedy without the need for an
interconnection system impact study.
(d) The utility and applicant shall use an
interconnection feasibility study agreement form.
(e) The utility shall avoid duplicating
previously conducted interconnection studies to the extent possible.
(f) The utility may require a study deposit
of the lesser of 100 percent of estimated nonbinding good faith study costs or
$1,000.
(g) The interconnection
feasibility study shall be completed and the results shall be transmitted to
the interconnection customer within 30 calendar days after the interconnection
feasibility study agreement is signed by the parties.
(2) Interconnection System Impact Study.
(a) A distribution interconnection system
impact study shall be performed when a potential distribution system adverse
system impact is identified in the interconnection feasibility study.
(b) Scope of Interconnection System Impact
Study,
(i) An interconnection system impact
study shall evaluate the impact of the proposed interconnection on both the
safety and reliability of the utility's electric distribution system.
(ii) The interconnection system impact study
shall identify and detail the system impacts that result when a small generator
facility is interconnected without project or system modifications, focusing on
the adverse system impacts identified in the interconnection feasibility study,
or potential impacts including those identified in the scoping
meeting.
(iii) The interconnection
system impact study shall consider all small generator facilities that, on the
date the interconnection system impact study is commenced, are directly
interconnected with the utility's electric distribution system, have a pending
higher queue position to interconnect to the system, or have signed an
interconnection agreement.
(iv) As
part of its impact study, the utility shall agree to evaluate and consider any
separate studies prepared by the applicant that evaluate alternatives for
interconnecting the small generator facility, including the applicant's
assessment of potential impacts of the small generator facility on the electric
distribution system.
(v) The
utility shall provide the applicant with the utility's final impact study
evaluation, including a comparison of the results of its own analyses with
those provided by the applicant.
(c) Within 5 business days of transmittal of
the interconnection feasibility study report, the utility shall send the
applicant:
(i) An interconnection system
impact study agreement using a form;
(ii) An outline of the scope of the
interconnection system impact study; and
(iii) A good faith estimate of the cost to
perform the study.
(d)
The interconnection system impact study shall include any necessary elements
from among the following:
(i) A load flow
study;
(ii) Identification of
affected systems;
(iii) An analysis
of equipment interrupting ratings;
(iv) A protection coordination
study;
(v) Voltage drop and flicker
studies;
(vi) Protection and set
point coordination studies;
(vii)
Grounding reviews; and
(viii)
Impact on system operation.
(e) An interconnection system impact study
shall consider any necessary criteria from among the following:
(i) A short circuit analysis;
(ii) A stability analysis;
(iii) Alternatives for mitigating adverse
system impacts on affected systems;
(iv) Voltage drop and flicker
studies;
(v) Protection and set
point coordination studies; and
(vi) Grounding reviews.
(f) The final interconnection system impact
study shall provide the following:
(i) The
underlying assumptions of the study;
(ii) The results of the analyses;
(iii) A list of any potential impediments to
providing the requested interconnection service;
(iv) Required distribution upgrades;
and
(v) A nonbinding good faith
estimate of cost and time to construct any required distribution
upgrades.
(g) The utility
may require a study deposit of the lesser of 50 percent of estimated nonbinding
good faith study costs or $3,000.
(h) The interconnection system impact study,
if required, shall be completed and the results transmitted to the
interconnection customer within 45 calendar days after the interconnection
system impact study agreement is signed by the parties.
(3) Interconnection Facilities Study.
(a) Within 5 business days of completion of
the interconnection system impact study, the utility shall provide to the
applicant:
(i) A report of the
interconnection system impact study;
(ii) An interconnection facilities study
agreement;
(iii) An outline of the
scope of the interconnection facilities study; and
(iv) A nonbinding good faith estimate of the
cost to perform the facilities study.
(b) The interconnection facilities study
shall identify:
(i) The electrical switching
configuration of the equipment, including transformer, switchgear, meters, and
other station equipment;
(ii) The
nature and estimated cost of the utility's interconnection facilities and
distribution upgrades necessary to accomplish the interconnection, including
engineering, procurement, construction, and overhead; and
(iii) An estimate of the time required to
complete the construction and installation of the facilities.
(c) Third-Party Design or
Construction of Interconnection Facilities.
(i) The applicant and utility may agree to
permit an applicant to separately arrange for a third party to design and
construct the required interconnection facilities.
(ii) The utility may review and approve the
design of the facilities under the interconnection facilities study
agreement.
(iii) If the applicant
and utility agree to separately arrange for design and construction, the
utility, consistent with security and confidentiality requirements, shall make
all relevant information and required specifications available to the applicant
to permit the applicant to obtain an independent design and cost estimate for
the interconnection facilities.
(iv)
The interconnection facilities shall be built in accordance with the
specifications in the interconnection facilities study.
(d) Upon completion of the interconnection
facilities study, and with the agreement of the applicant to pay for the
interconnection facilities and distribution upgrades identified in the
interconnection facilities study, the utility shall provide the applicant with
an interconnection agreement within 5 business days.
(e) The utility may require a study deposit
of the lesser of 50 percent of estimated nonbinding good faith study costs or
$10,000.
(f) In cases where no
interconnection upgrades are required, the interconnection facilities study
shall be completed and the results shall be transmitted to the interconnection
customer within 30 calendar days after the agreement is signed by the
parties.
(g) In cases where
interconnection upgrades are required, the interconnection facilities study
shall be completed and the results shall be transmitted to the interconnection
customer within 45 calendar days after the agreement is signed by the
parties.
F.
Interconnection Agreement.
(1) When a utility
determines, as a result of the interconnection studies conducted under a Level
4 review, that it is appropriate to interconnect the small generator facility,
the utility shall provide the applicant with an interconnection
agreement.
(2) The applicant shall
have either 30 calendar days, or another mutually agreeable time frame after
receipt of the interconnection agreement, to sign and return the
interconnection agreement.
(3) If
the applicant does not sign the interconnection agreement within 30 calendar
days, the request shall be considered withdrawn unless the applicant and
utility mutually agree to extend the time period for executing the
interconnection agreement prior to the expiration of the 30-calendar-day
period. A request for extension may not be unreasonably denied by the
utility.
(4) After the
interconnection agreement is signed by the applicant and utility,
interconnection of the small generator facility shall proceed according to any
milestones agreed to by the applicant and utility in the interconnection
agreement.
(5) The utility shall
approve the interconnection request and provide a permission to operate notice
within 20 business days of receipt of acceptable documents, subject to the
following conditions'.
(a) All milestones
agreed to in the interconnection agreement are satisfied;
(b) The small generator facility is approved
by electric code officials with jurisdiction over the
interconnection;
(c) The applicant
provides a certificate of completion to the utility;
(d) Upon request of the utility, the
applicant provides one or more photographs of the small generator facility site
location, components, metering equipment, and other related facilities and
equipment; and
(e) There is a
successful completion of the witness test, if conducted by the
utility.
G.
Level 4 Review Failure. If the interconnection request is denied, the utility
shall provide the applicant a letter explaining the reasons for denying the
interconnection request.