Md. Code Regs. 20.50.11.01 - CVRZ, Voltage Survey Plan, and Voltage Survey Requirement
A. Within 60 days
after the effective date of these regulations, each electric company shall file
for Commission approval:
(1) A list and
location map for all CVRZs within its service territory, if applicable;
or
(2) If no CVRZs are designated
in its service territory, its voltage survey plan.
B. Within 30 days after the Commission
approves a CVRZ or CVRZs within an electric company's service territory, the
electric company shall file its voltage survey plan for Commission
approval.
C. Upon approval of the
electric company's voltage survey plan, the electric company shall conduct an
initial contact voltage survey of each CVRZ within 1 year of the approval and
shall conduct subsequent contact voltage surveys of each CVRZ as set forth in
its voltage survey plan.
D. The
electric company shall conduct its initial and each subsequent contact voltage
survey within each Commission-approved CVRZ of:
(1) All publicly accessible electric
distribution plant and electric company-owned or-maintained streetlights that
are capable of conducting electricity;
(2) Municipal-owned or governmental-owned
streetlights and traffic signals that are publicly accessible and are capable
of conducting electricity, if the consent of the municipal government or other
appropriate governmental authority is received; and
(3) All objects and surfaces that are
publicly accessible in public parks and playgrounds and that are capable of
conducting electricity, if the consent of the municipal government or other
appropriate governmental authority is received.
E. At least 60 days prior to implementing any
material change to its voltage survey plan, the electric company shall file for
Commission approval.
F. For areas
within each electric company's service territory which are not located in a
CVRZ, the electric company shall perform an initial contact voltage survey
within 3 years of the approval of the voltage survey plan on all publicly
accessible electric distribution plant, except for wooden poles, and publicly
accessible electric company-owned or-maintained streetlights that are capable
of conducting electricity. Subsequent contact voltage surveys for all equipment
capable of conducting electricity shall be conducted in accordance with the
voltage survey plan.
G.
Streetlights shall be tested for contact voltage after dark or when the light
is illuminated.
H. The Commission
may increase or decrease the frequency or scope of any contact voltage survey
requirement upon a showing of good cause.
I. Contact voltage readings shall be
conducted in accordance with acceptable methods described in the Institute of
Electrical and Electronic Engineers Standard 1695 - 2016.